A structural alteration in Singapore needs a Building and Construction Authority (BCA) structural plan submission made by a Qualified Person (QP) who is a registered Professional Engineer, followed by a permit before work starts. Whether an Accredited Checker (AC) must also certify the design depends on one question: does the work materially affect the key structural elements of the building? Owners, developers and contractors who settle that question early, and who choose a QP with a complete document set, avoid most resubmissions. Our engineering and submission team handles this as PE endorsement and statutory authority submissions for Singapore projects.
TL;DR
- Only a QP who is a registered Professional Engineer in the civil or structural discipline can apply for structural plan approval, according to BCA’s structural plan submission page.
- Alterations that do not materially affect key structural elements go with PE-endorsed plans and an Appendix D certificate. Work that does, such as strengthening, needs an AC certificate.
- BCA’s stated processing time is 7 working days without AC certification, and 10 working days for a first submission with AC certification (14 for later ones). The permit takes a further 7 working days.
- New projects are submitted through CORENET X, where joint submissions at the Construction Gateway are processed within up to 20 working days.
- Structural works need an appointed, accredited site supervisor, scaled to the value of the works.
Table of Contents
- When a structural alteration needs a BCA submission
- Who acts as the Qualified Person
- What a structural alteration submission contains
- When an Accredited Checker is needed
- The CORENET X process
- Timelines to plan around
- Site supervision once the permit is issued
- Where submissions go wrong
- How we handle structural alteration submissions
- Our perspective
- FAQ
- Sources
When a structural alteration needs a BCA submission
Under the Building Control Act, a permit is required for all building works except the insignificant works listed in the First Schedule of the Building Control Regulations. This is stated on BCA’s structural plan submission page. Removing or altering a column, beam, load-bearing wall or floor slab is not insignificant work. Adding a floor, opening a slab for a new staircase or reconstructing part of a slab all fall under the structural plan process.
The practical dividing line is between two routes for additions and alterations (A&A):
| Situation | What BCA requires |
|---|---|
| Structural stability or integrity is not affected | PE-endorsed structural plans with an Appendix D certificate; no AC certificate |
| Work materially affects key structural elements (for example strengthening works) | AC certificate in addition to the QP’s submission |
The AC exemption is written into law. The Fourth Schedule of the Building Control Regulations 2003 exempts from AC checking structural works that consist of repairs, alterations and additions to an existing building which do not materially affect its key structural elements. The judgment of what counts as “materially” is an engineering one, and it belongs to the QP. It should be made and documented before fees, drawings and schedules are fixed, because it decides the route, the cost and the timeline.
For a wider view of what triggers approval, see our overview of what requires BCA submission approval.
Who acts as the Qualified Person
The QP is the person of record for the submission. For structural plans, BCA allows only a QP who is a registered Professional Engineer in the civil or structural discipline to apply. The QP signs the structural plans, endorses the design calculations and appoints the site supervisors during the permit application.
Two consequences follow for project teams:
- The architect or main contractor cannot lodge structural plans on their own. The structural QP must be appointed before the submission is prepared, not after the architectural scheme is frozen.
- The QP carries design responsibility and supervision responsibility. An alteration scheme that cannot be built safely within the existing structure is better found at concept stage than at AC review.
Our structural and civil engineering consultancy covers both PE endorsement for structural and geotechnical works and the authority submission itself, so design, calculations and lodgement stay with one team.
What a structural alteration submission contains
BCA lists the core items on its structural plan submission page:
- Form BCA-BE-STAPPV01 (BEV/A1)
- Structural plans signed by the QP and endorsed design calculations
- Building plans
- URA planning permission or the lodgement receipt
- Plan fee computation, and buildability calculations where applicable
Plan fees are based on the gross floor area, and BCA does not begin processing until the fees are paid and verified.
For an alteration, the quality of the existing-building information often decides the outcome. As-built drawings, material test results and a record of what is being demolished or retained give the QP a sound basis for the calculation. Gaps here are the usual cause of queries. Our guide on preparing BCA structural calculations sets out how the calculation package is built, and the BCA plan submission requirements page lists the wider document set.
Alterations to HDB properties
HDB properties carry their own requirements. HDB’s circular, effective 26 December 2025, relaxes building plan submission requirements: submissions to HDB are no longer required for A&A works to commercial properties and Town Council improvement works, and the QP(ST) may make concurrent submissions to all relevant authorities while obtaining HDB’s Landowner Endorsement. The same circular’s checklist requires:
- As-built structural plans attached
- Proposed works demarcated and colour-coded: cyan for existing, magenta for proposed, yellow for demolished
- A minimum superimposed dead load of 120 kg/m² in structural adequacy checks
- No hacking or coring of existing reinforced concrete members, with the exception of ground floor and first storey slabs for sanitary works
- Reinstatement in at least Grade 40 (C32/40) concrete
For piling and structural plans on HDB properties, HDB’s civil and structural guidelines call for submission at least 3 months before foundation, sub-structure and super-structure works begin, and as-built piling plans within 28 days of completing piling.
When an Accredited Checker is needed
The AC is an independent engineer who reviews the QP’s design. Under the Building Control (Accredited Checkers and Accredited Checking Organisations) Regulations, the AC evaluates and reviews the structural design in the plans and performs original calculations to determine whether key structural elements are adequate. The AC must also notify the Commissioner of Building Control of any contravention or non-compliance with the Act in connection with the structural design.
In a case that needs an AC, BCA expects the AC to submit a certificate, a checklist, an evaluation report and independent calculations. The compiled regulations list the tasks in detail: identifying the relevant Code of Practice, checking design and wind loadings, identifying key structural elements, and analysing those elements together with the foundation system, piles and earth retaining structures, as set out in the compiled AC regulations.
Independence is a legal requirement. An AC may not issue a certificate where he has a professional or financial interest in the building works, and the AC must declare this. Penalties for breaching the duty to check the structural plans and calculations of major building works are a fine of up to $100,000, imprisonment of up to 2 years, or both, as the amended Building Control Act provides. Teams should appoint the AC as an independent party from the start and keep the QP’s design team separate from the checking team.
The CORENET X process
BCA states on its structural plan submission page that CORENET X replaces CORENET 2.0 and is mandatory for all new projects by 1 October 2026. Teams planning an alteration submission today should assume CORENET X as the route and confirm on the portal how a project already in progress is onboarded.
The workflow has two main stages, with a third that is optional. According to CORENET X’s submission workflows:
- Design Gateway: early coordination of the scheme with the agencies.
- Construction Gateway: detailed submission, including the structural package.
- Piling Gateway (optional): used where piling is to start ahead of the main works.
Relevant agencies issue Written Directions or Approvals within up to 20 working days for joint submissions, and at each round only agencies with Written Directions respond. Processing starts only after fees are paid and verified. There is no 72-hour fee payment deadline, and fees below $10,000 are encouraged to be paid by credit card.
What the structural package looks like
The CORENET X structural submission and IFC-SG requirements document sets out the Construction Gateway package:
- A complete set of IFC-SG models for all structural elements and details
- 2D drawings limited to general notes and special details, such as slab reinforcement, transfer plates, precast joints, prestressed details and steel connections
- Design calculation reports from the QP and AC, plus the geotechnical QP and AC where needed
- Site investigation report in pdf and AGS format
- Impact assessment report and topography
- A completion letter of pre-consultation for complex structures
For alteration and conservation projects, the workflows page notes that teams no longer need to colour-code BIM elements in magenta, cyan and yellow. The IFC+SG Status parameter is populated instead, so new, existing and removed elements are identified in the data rather than by colour. Our guides on CORENET X BIM submission for QPs and the requirements to check before a BIM submission cover model preparation.
Large projects have a further concession. Under the RABW framework described in CORENET X’s refinements guidance, eligible projects (for example a gross floor area above 40,000 sqm with five or more blocks of at least four storeys) may submit detailed structural design and calculations in a limited number of part ST submissions, with the full coordinated structural BIM carcass model required at the first Construction Gateway submission.
From 1 April 2023, relevant aspects of civil defence shelter plans are incorporated in the Building Plan and Structural Plan submissions instead of being lodged separately, according to BCA’s building plan submission page.
Recent portal releases also affect admin. The CORENET X release notes record PayNow via 2C2P for payments up to $200,000, assigned QPs initiating amendments directly, and Licensed Specialist Builders being assignable as project parties for Manpower, Constructability and Specialist Building Works.
Timelines to plan around
BCA’s published processing times on its structural plan submission page are:
| Route | Processing time |
|---|---|
| Without AC certification | 7 working days from complete documents |
| With AC certification, first submission | 10 working days |
| With AC certification, subsequent submissions | 14 working days |
| CORENET X Construction Gateway joint submission | Up to 20 working days |
| Permit to carry out structural works | 7 working days |
These apply to applications that meet regulatory requirements in the first instance. BCA may take longer where the QP has a history of poor submission quality. A complete first submission is therefore the main schedule control, more than any later chasing.
A realistic programme for a structural alteration counts the whole chain: site survey and as-built verification, design and calculation, AC review where required, URA permission where the work needs it, structural submission, permit, and only then the start of structural works. Each step depends on the previous one, so a missing as-built drawing early is a delay at every step after.
Site supervision once the permit is issued
The QP appoints site supervisors for structural works at the time of the permit application. According to BCA’s site supervisor requirements, supervisors must be accredited by the Joint Accreditation Committee of the Institution of Engineers Singapore and the Association of Consulting Engineers Singapore. For works up to $7.5 million, an appropriate QP, resident engineer (RE) or resident technical officer (RTO) provides immediate supervision. Larger works need full-time supervision, with the number of REs and RTOs rising with value, up to 2 REs and 3 RTOs, or 1 RE and 5 RTOs, for works above $150 million.
Supervision has to be tracked as carefully as design. Contractors often use construction task management routines to keep inspections, instructions and records in one place, which helps the QP’s supervision records stay current. Our permit checklist for detached house rebuilds shows how the permit stage is prepared in practice.
Where submissions go wrong
- Wrong route chosen. Treating strengthening or removal of primary elements as a simple A&A, then being asked for AC certification late.
- Incomplete existing-building data. Calculations built on assumed rather than verified conditions.
- Planning and structural plans out of step. URA permission or the lodgement receipt is a listed submission item, so the architectural and structural schemes must match.
- Late appointment of the QP. The structural scheme then has to adapt to decisions already fixed.
- Model data errors. On CORENET X, IFC-SG models with incorrect status parameters or missing elements fail to give agencies a reliable picture.
Each of these is cheaper to fix before lodgement. BCA also notes that processing time can lengthen for QPs with poor submission history, which makes first-time quality a continuing concern for the QP, not a one-off.
How we handle structural alteration submissions
Our services cover structural and geotechnical engineering, PE endorsements, BCA submissions and approvals, URA and SCDF submissions, temporary works design and BIM modelling, so the multi-agency parts of an alteration can be managed together. The offers page at aectechnicalsg.com/services lists each service. We state our positioning as timely, responsive and affordably priced work, with direct and clear communication with clients. For a first discussion on a specific building, the structural engineer consultation cost guide explains how engagements are scoped, and our hourly consultation service suits early route-setting questions.
Our perspective
We see the structural alteration submission as an engineering decision first and a filing second. The route, with or without an AC, follows from how the existing structure will carry the new loads, and that judgment is best made by the QP who will sign the design.
That is why we prefer to have design, calculations, authority submission and supervision under one accountable team. A single team sees the existing-building data, the calculation and the CORENET X model at once, so inconsistencies surface before the agencies find them.
With CORENET X, the model itself is now part of the evidence. Teams that treat the IFC-SG data as an afterthought will spend their time answering queries, and teams that build it with the calculation will not.
Aman
FAQ
Does every structural alteration need an Accredited Checker?
No. Repairs, alterations and additions to an existing building that do not materially affect its key structural elements are exempt from AC checking under the Building Control Regulations. They still need PE-endorsed plans with an Appendix D certificate. Work such as strengthening that materially affects key structural elements needs an AC certificate.
Who can lodge a structural alteration submission?
Only a QP who is a registered Professional Engineer in the civil or structural discipline can apply for structural plan approval. Owners and contractors engage the QP, and the QP signs the plans and endorses the calculations.
How long does BCA take to approve structural plans?
BCA’s stated times are 7 working days without AC certification, and 10 working days for a first submission with AC certification, rising to 14 for later submissions. CORENET X joint submissions at the Construction Gateway take up to 20 working days, and the permit takes 7 working days. These apply to complete, compliant submissions.
Is CORENET X compulsory for alterations?
BCA states that CORENET X is mandatory for all new projects by 1 October 2026 and replaces CORENET 2.0. Teams with projects already under way should confirm the onboarding position on the CORENET X portal.
Who supervises structural works on site?
Supervisors are appointed by the QP during the permit application and must be accredited by the Joint Accreditation Committee. For works up to $7.5 million, a QP, RE or RTO provides immediate supervision. Larger works need full-time supervision.
Sources
- BCA: Structural Plan submission
- Building Control Regulations 2003, Singapore Statutes Online
- HDB circular on further relaxation to building plan submission requirements
- HDB guidelines on civil and structural plan submission
- Building Control (Accredited Checkers and Accredited Checking Organisations) Regulations
- Compiled AC Regulations (BCA)
- Building Control Act amendments (BCA)
- CORENET X: submission workflows
- CORENET X structural submission and IFC-SG requirements
- CORENET X: refinements to the new process
- BCA: Building Plan submission
- CORENET X release notes
- BCA: Site supervisor requirements
- Construction task management guide