An engineering design review in Singapore is a structured check, made before approval and again before construction, that a design meets the Building Control Act, the Approved Document and the Design for Safety (DfS) duties, and that its risks are recorded for the people who will build and maintain it. It is done by named parties with defined legal roles: the qualified person (QP), the accredited checker and, for safety, the DfS review team. Developers and building owners who understand who reviews what, and at which stage, avoid redesign after submission and disputes on site. AEC Technical Advisory covers structural and geotechnical design, PE endorsement and BCA, URA and SCDF submissions, so the review and the submission can be handled in one engagement.
TL;DR
- A Singapore design review has three layers: the QP’s own compliance duty, the accredited checker’s independent structural check, and the DfS review meetings that run from inception to construction.
- The accredited checker must review the structural design and perform original calculations on key elements. The regulations list 16 mandatory tasks.
- DfS reviews are staged (concept, detailed design, pre-construction) and recorded in a DfS Register that stays with the structure.
- Detailed structural plans must carry the signature of the QP and the accredited checker, and a QP certificate on the first and last sheets.
- The cheapest time to change a design is before tender. Schedule reviews early, then close out every action in writing.
Table of Contents
- What a design review means on a Singapore project
- Compliance routes the review tests against
- What the accredited checker must verify
- Design for Safety: reviewing for the people who build and maintain
- The staged review: what to assess and when
- A practical checklist for an engineering design review
- How to record findings, decisions and actions
- Who must be involved, and when
- Where we help in the review process
- Start your review with AEC Technical Advisory
- FAQ
- Sources
What a design review means on a Singapore project
In product engineering, a design review is a meeting where peers critique a design. In Singapore construction, the term covers more, because several reviews are required by law and each has a different owner.
- The QP’s compliance review. The Building Plan submission page of the BCA states that a QP must be a registered Architect (Board of Architects) or a Professional Engineer (Professional Engineers Board) holding a valid practising certificate. Before applying for plan approval, the QP obtains written URA permission and ensures compliance with the Fifth Schedule objectives and performance requirements, the Approved Document and the Code on Accessibility.
- The accredited checker’s independent review. For major building works, the Building Control Act requires an accredited checker, appointed through an accredited checking organisation above a prescribed value limit. Geotechnical works also need a specialist accredited checker.
- The DfS review. Under the Workplace Safety and Health (Design for Safety) Regulations, developers and designers must address foreseeable risks to those who build, maintain, clean, repair and demolish the structure.
A project team that treats these as one exercise usually finds gaps. A structure can pass a structural check and still carry an unrecorded hazard for maintenance crews. Equally, a thorough DfS register does not substitute for the checker’s calculations.
Compliance routes the review tests against
The Building Control Act 1989, section 9(2) sets the logic reviewers work from. Plans prepared in accordance with the acceptable solutions in the Approved Document are deemed to comply with the prescribed objectives and performance requirements. A QP using an alternative solution has two options: take all reasonable steps and exercise due diligence to ensure the solution meets the requirements, or obtain certification from a specialist approved by the Commissioner of Building Control.
This changes what a reviewer looks for:
- Acceptable-solution designs: the review confirms that each provision has been applied correctly and that nothing in the drawings departs from it.
- Alternative-solution designs: the review examines the evidence behind the due-diligence claim or the specialist certification. The BCA page notes that alternative solutions are evaluated by a QP and submitted for BCA acknowledgment.
A reviewer who cannot tell which route a design takes cannot tell what evidence to ask for. The first review question is therefore simple: which provisions are met by acceptable solution, and which are alternative solutions?
What the accredited checker must verify
The Building Control (Accredited Checkers and Accredited Checking Organisations) Regulations give the most precise definition of a structural design review anywhere in Singapore practice. The checker must evaluate, analyse and review the structural design, and perform original calculations to determine the adequacy of key structural elements. The Second Schedule lists 16 mandatory tasks. They include checking:
- the adopted code of practice, design loadings and wind loading;
- computer program assumptions and limitations, and the engineering models used;
- material standards;
- the structural concept and key elements;
- stability and robustness, including lateral loads, ties and bracing;
- foundations and piles, covering capacity, uplift, group effects, negative skin friction and joint capacities;
- earth retaining structures, columns, long-span trusses and beams, and transfer beams;
- joint connections;
- consistency of structural detailing with the calculations.
The last item is the one design teams most often underestimate. Calculations and drawings are frequently produced by different people at different times, and a revision to one is not always carried to the other. A review that explicitly traces each key member from calculation to detail drawing catches this before the checker does.
What the signed plans must show
The current Building Control Regulations, in the consolidation in force from 17 April 2026, require detailed structural plans to be signed or endorsed by the QP who prepared them and by an accredited checker, unless exempt under regulation 12. The plans must bear a QP certificate on the first and last sheets stating that the loads imposed by all building works shown have been taken into consideration. These requirements were introduced by amendments effective 18 December 2023.
In practice, this makes the certificate statement a review item. Someone must confirm that the loads from every element shown, including additions such as rooftop equipment, façade systems and temporary works interfaces, have been accounted for before the QP signs.
Design for Safety: reviewing for the people who build and maintain
DfS is where the review extends beyond code compliance. According to the WSH Guidelines on Design for Safety, the developer must ensure that foreseeable design risks are eliminated or, where that is not reasonably practicable, reduced as low as reasonably practicable at source, with collective protective measures preferred. Designers must prepare design plans that eliminate foreseeable risks to anyone who constructs, maintains, repairs, cleans, refurbishes or demolishes the structure.
The same guidelines list the competencies a designer should bring to the table beyond design skill:
- awareness of the significant design hazards for construction, operation and maintenance workers;
- knowledge of WSH legislation, codes of practice and regulatory requirements;
- understanding of the structure’s intended purpose;
- knowledge of risk management processes and technical design standards;
- an appreciation of how construction methods affect the design;
- the ability to source and apply data on human dimensions, capacities and behaviours.
The earlier edition of the guidelines adds a point that suits any review: identifying risks and designing around them should be repeated until the team is satisfied the design cannot be changed further to eliminate all risks.
The staged review: what to assess and when
The WSH Guidelines recommend the GUIDE process in three phases. Each has a different subject, and a review held at the wrong stage tends to be either too vague to be useful or too late to change anything.
| Stage | Focus | Typical items reviewed |
|---|---|---|
| GUIDE-1: concept design | Location, traffic, surrounding buildings, general constraints | Risks recorded from materials and structural concepts |
| GUIDE-2: detailed design, maintenance and repair | Detailed architectural and structural design | Construction methods, access and egress, confined spaces, maintenance and repair methods; contractor input on design-and-build |
| GUIDE-3: pre-construction | Temporary works and specialist contractor designs | Shoring, trenches, deep excavation, confined spaces, formwork, falsework |
Source for the table: WSH Guidelines (DfS).
The REDAS DfS Good Practice Guide notes that since 2022 the updated guidelines also allow life-cycle-stage considerations, the Designer’s RAG List and a hazard-based checklist. Teams may adopt or adapt a framework, and the life-cycle framework remains the most widely used.
Meeting frequency for a typical residential project
The same REDAS guide gives indicative timing for a typical residential project:
- at inception, once massing and orientation are available;
- every 1 to 3 months during concept and schematic design;
- before tender preparation and tender calling, at detailed design;
- at main contract award and before significant work starts, at pre-construction;
- every 1 to 4 months during construction, tapering as residual risks close, with follow-up reviews to close out actions.
These are indicative, not fixed rules. Complex sites with deep excavation or tight neighbouring structures justify the shorter end of each range.
Scheduling reviews so they can still change the design
The value of a review falls sharply once drawings are issued for tender. Booking review dates against the programme, and assigning each finding an owner and a due date, keeps the process from slipping. A construction task management guide shows one way to structure recurring tasks and follow-ups across a project team, which suits the close-out cycle of review actions.
A practical checklist for an engineering design review
Singapore regulations fix the accredited checker’s scope and the DfS record-keeping, but they do not prescribe a single internal checklist for the design team’s own review. The following is the structure our engineers use as a working framework, built from the regulatory items above and organised so that each line has an owner.
- Basis of design. Confirm the adopted codes, design loadings, wind loading, material standards and the Approved Document provisions relied on. State which parts are acceptable solutions and which are alternative solutions.
- Approvals in place. Check URA permission and any other authority conditions that the design must respect before the plan application.
- Structural concept. Confirm load paths, stability, robustness, lateral load resistance, ties and bracing.
- Geotechnical inputs. Confirm that the site investigation, foundation type, pile capacities and earth retaining structures are consistent with the ground information.
- Software and models. Record assumptions and limitations of any computer programs and the engineering models used.
- Calculation to drawing consistency. Trace key members from the calculation to the detail drawing. Confirm that connections and joints match.
- Buildability and temporary works. Identify temporary works, shoring and formwork that depend on the permanent design.
- Safety in construction and maintenance. Identify access, egress, confined spaces, and maintenance and repair methods, and state the residual risks.
- Signatures and certificates. Confirm that the QP certificate on the first and last sheets and the checker’s endorsement are in place.
A checklist is only as good as the person ticking it. The point of listing each item is that every line must trace to a named reviewer and a dated outcome.
How to record findings, decisions and actions
The DfS process has the most developed record-keeping. The REDAS guide states that the DfS Register must be set up and kept by the DfS Professional (DfSP) and contain:
- the records of every DfS review meeting, with minutes and attendance as key evidence that the process was carried out and that stakeholders were involved;
- Design Risk Assessment Forms covering all identified hazards, risks and mitigation measures, including residual risks and the information stakeholders need to implement the agreed controls.
The DfSP’s delegated duties are convening the review meetings and maintaining the register. The DfSP facilitates, and the guide says developers should still attend. The WSH guidelines add that the register stays with the structure from inception to demolition and is shared with all stakeholders. Design risk information should be presented clearly and concisely, for example as advisory notes on drawings made immediately available to those carrying out the work.
The same discipline suits non-DfS reviews. For each finding, record:
| Field | Purpose |
|---|---|
| Finding and drawing reference | Identifies exactly what was questioned |
| Decision | Accept, revise or escalate, with the reason |
| Owner and due date | Prevents open items drifting past tender |
| Residual risk | Passes on what the design could not eliminate |
| Close-out evidence | Revised drawing, calculation or certificate reference |
Who must be involved, and when
Under section 7 of the Building Control Act, all building works must be carried out under the supervision of an appropriate QP. Structural elements of prescribed large building works require full-time supervision by a site supervisor or team working under the QP’s control and direction. Critical works on small-scale building works, such as concreting, piling, pre-stressing and high-friction grip bolt tightening, need immediate supervision by a QP or a site supervisor under a QP.
Section 8 places a duty on the developer. If the builder has not appointed QPs, the developer must appoint appropriate QPs to prepare plans and supervise works, together with a licensed builder. For geotechnical works, geotechnical-engineer QPs are required for plans and supervision. The accredited checker and, for geotechnical works, a specialist accredited checker and a licensed specialist builder to monitor instruments, complete the line-up.
On site, the supervising QP must keep the site records required under section 9(4)(d) of the Act at the works premises, as the Building Control Regulations prescribe. Design review findings that affect construction methods belong in those records.
Where we help in the review process
Our work lines up with the review layers described above. We provide structural and geotechnical engineering design, PE endorsement, structural engineering design checks outside the authority process, temporary works design and façade design. We also manage BCA, URA, SCDF, JTC, LTA, PUB and NEA submissions. For owners of completed buildings, we carry out BCA periodic structural and façade inspections. Our own positioning is timely, responsive and affordable service with clear communication.
For teams that want more background before a review, our guides on BCA plan submission requirements, Design for Safety in engineering and how to ensure design safety in construction projects set out the submission and safety context in more detail.
Our perspective
A design review earns its fee when it happens while the design can still move. We see the same pattern across submissions: the structural calculation, the architectural drawing and the safety record are treated as three separate deliverables, and conflicts surface only when an authority or checker raises them.
Our approach is to keep engineering design, PE endorsement and authority submissions under one roof, so that the person who reviews the design also understands what BCA, URA and SCDF will ask of it. A finding raised at concept stage costs a conversation. The same finding raised after tender costs a revision and a delay.
We therefore encourage developers to bring engineers in at inception, to set review dates against the programme, and to insist that every finding ends with a named owner and a closed record.
Aman
Start your review with AEC Technical Advisory
If your project needs a structural design check, PE endorsement, geotechnical input or a coordinated authority submission, our engineering and architectural services cover each stage described above. For endorsements and temporary works design, see our PE endorsement and authority submissions page.
Tell us the project stage, the authority involved and the drawings you hold, and our team will advise which review steps fit.
FAQ
Who carries out an engineering design review in Singapore?
Three parties share it. The QP (an Architect or Professional Engineer with a valid practising certificate) is responsible for compliance of the plans. The accredited checker independently reviews the structural design on major works. The DfS review team, facilitated by a DfSP where one is appointed, reviews safety risks at set stages.
What does an accredited checker actually check?
The checker evaluates and reviews the structural design and performs original calculations on key elements. The Second Schedule of the accredited checker regulations lists 16 mandatory tasks, from design loadings and material standards to piles, retaining structures, joints and the consistency of detailing with calculations.
When should design reviews be held?
DfS guidance recommends GUIDE-1 at concept, GUIDE-2 at detailed design and GUIDE-3 before construction. The REDAS guide suggests meetings at inception, every 1 to 3 months during concept design, before tender, at contract award and every 1 to 4 months during construction. These are indicative intervals, so set them against your own programme.
What must be recorded after a DfS review?
Minutes with attendance for every meeting, and Design Risk Assessment Forms covering hazards, risks, mitigation and residual risks. These are kept in the DfS Register, which stays with the structure from inception to demolition and is shared with stakeholders.
Do structural plans need a certificate from the QP?
Yes. Under the Building Control Regulations as amended with effect from 18 December 2023, detailed structural plans must be endorsed by the QP and an accredited checker, unless exempt under regulation 12. They must carry a QP certificate on the first and last sheets that all loads from the building works shown have been considered.
Sources
- BCA: Building Plan submission
- Building Control Act 1989, Singapore Statutes Online
- Building Control (Accredited Checkers and Accredited Checking Organisations) Regulations
- Building Control Regulations, consolidation of 17 April 2026
- Building Control Regulations, version valid to 4 October 2024
- WSH Guidelines: Design for Safety (2022 edition)
- WSH Guidelines: Design for Safety (2016 edition)
- REDAS DfS Good Practice Guide