Lift installation approval in Singapore runs in three gates under the Building Control (Fixed Installations) Regulations 2025, which took effect on 1 October 2025. The developer or owner appoints a registered fixed installation (FI) works contractor, a QP (Plans) and a QP (Supervisor). The Building and Construction Authority (BCA) must approve the plans before work starts. A permit to operate (PTO) must be in hand before the lift is used. Each gate has its own documents, its own responsible professional and its own failure points, and most delays arise from the hand-offs between them.
This article sets out who does what, which documents move between parties, how the shaft and building works connect to the lift submission, and what changes when an existing lift is altered or replaced. It is written for developers, owners, main contractors, architectural firms and engineering professionals who carry the legal duty for the installation.
TL;DR
- From 1 October 2025, the BC (FI) Regulations replace the earlier BMSM regime: appoint an FI works contractor, a QP (Plans) and a QP (Supervisor), obtain plan approval before works, and obtain a PTO before operation.
- The QP (Plans) and QP (Supervisor) must each also be a Specialist Professional Engineer (SPE) in lift and escalator engineering.
- For PTO applications submitted from 1 January 2026, the QP must submit the EITC Inspection Report as part of BCA’s review.
- Major alteration or replacement ends the existing PTO, so plan approval, supervised works and a new PTO apply again.
- Lift shafts, pits, machine rooms and builders’ work sit within the wider building plan approval and need coordinated structural, architectural and M&E input.
Table of Contents
- What changed on 1 October 2025
- Who must be appointed, and what each is accountable for
- Stage 1: Plan approval before any work starts
- Stage 2: Installation under supervision
- Stage 3: EITC, the inspection report and the PTO
- When an existing lift is altered or replaced
- Common points where lift approvals stall
- How lift approval fits into the wider BCA submission
- Where AECTechnicalSG supports the approval path
- Our perspective
- FAQ
- Sources
What changed on 1 October 2025
Before October 2025, a single specialist engineer typically witnessed the examination, inspection and testing of a new lift and applied for the PTO. BCA’s regulatory updates page describes the new model as a split between a QP (Plans) and a QP (Supervisor). The QP (Plans) ensures the design complies and submits the plans. The QP (Supervisor) supervises the examination, inspection, testing and commissioning (EITC), certifies that it was carried out under his or her supervision, and applies for the PTO on the developer’s behalf.
The practical effect is that responsibility is separated and recorded at each stage. A project team that treats lift approval as a late-stage task before handover is exposed, because plan approval is now a precondition to starting works, not a formality to be tidied afterwards.
Who must be appointed, and what each is accountable for
The regulations define the two QP roles precisely. Under the Building Control (Fixed Installations) Regulations 2025, a plan submission QP is a qualified person who is also an SPE, and a supervisor QP is likewise a QP who is also an SPE. An SPE is registered under the Professional Engineers Act 1991 in the specialised branch of lift and escalator engineering and holds a valid practising certificate in that branch. A civil or structural Professional Engineer who is not registered in that branch cannot fill either role.
The appointments are:
| Role | Principal accountability | Stage |
|---|---|---|
| Developer or owner | Appoints the team, obtains approval and the PTO | All stages |
| FI works contractor | Prepares and submits documents to the QP (Plans), carries out EITC, facilitates BCA inspection | Plan submission to PTO |
| QP (Plans) | Confirms design compliance and submits plans to BCA | Before works |
| QP (Supervisor) | Supervises installation and EITC, certifies, applies for the PTO | During works and commissioning |
The contractor and its workers must also be registered. BCA states that anyone who installs, maintains, inspects or tests fixed installations must be registered with BCA, and that PTOs are applied for, renewed and managed through the Lifts and Escalators Application (LEAP) portal.
The independence logic is not new. When the earlier lift regime was introduced, a 2016 BCA factsheet explained that the annual examiner had to be an engineer registered in lifts and hoists who was not an associate, partner, director or employee of the lift owner, so that the certificate comes from an independent party. The 2025 model carries that principle into the installation stage by assigning design submission and site supervision to named, accountable professionals.
Stage 1: Plan approval before any work starts
Plan approval is the first gate. The FI works contractor must submit the relevant documents to the QP (Plans) and ensure they are valid and complete. BCA lists these as drawings, type testing certificates, layout plans, floor plans, site plans and lift specifications.
BCA publishes the submission instruments on its Fixed Installation Regulations page:
- The FI Plan Submission Regime Guide, updated in September 2025, which now includes the requirement to submit an Authorisation form for the appointment of the plan submission QP and the FI works contractor.
- The Guide for Fixed Installation Plan Submission via FormSG, updated in October 2025, with more detailed instructions for the Annex A FI detail sheet.
- The Approved Document for Fixed Installations, which gives acceptable solutions for lifts, escalators and mechanised car parking systems.
The typical failure at this stage is an incomplete or inconsistent package. Examples include a lift specification that does not match the shaft dimensions on the architectural plan, a type testing certificate that does not cover the model submitted, or an Authorisation form that names a contractor different from the one that later mobilises. Each of these returns the submission to the project team and pushes the start of works back. Checking the lift supplier’s technical data against the approved building plans before the QP (Plans) signs is the most effective way to avoid it.
Standards the design must meet
The design reference for electric passenger and goods lifts is SS 550:2020, the Singapore Standard code of practice for installation, operation and maintenance. According to its published preview, it specifies safety rules for permanently installed new passenger or goods lifts with traction or hydraulic drive. Its technical committee drew on BCA, HDB, JTC, LTA, SCDF, NEA and the industry bodies. Other lift types follow other codes: BCA’s EITC templates cover ASME lifts, SS 550 traction and hydraulic lifts, EN 81-40 stairlifts, EN 81-41 vertical platform lifts, hybrid lifts, SS 626 escalators and mechanised car parking systems.
Since 2020, BCA has required owners to engage specialist professional engineers in lifts and escalators to certify design plans, and has required lift models and key safety components to be certified by independent certification bodies. This is why type testing certificates sit in the submission package.
BIM for larger projects
Where the project’s Gross Floor Area exceeds 5,000 m², the streamlined BIM process is mandatory and, according to BCA’s BIM page, now includes FI works such as lifts, escalators and car parking systems. For any new FI installation or major alteration or replacement, prior BCA approval is required, and the submitted models must meet the minimum data-structure and component-information requirements in BCA’s BIM Guide for Fixed Installation. Teams on such projects should confirm early that the lift model is built to those requirements, since a model that fails the data checks stalls the whole submission. The team can read more on BIM submission for QPs on 5,000 m² and larger projects.
Stage 2: Installation under supervision
Once plans are approved, a BCA-registered FI works contractor performs the installation under the supervision of the QP (Supervisor). The supervising QP is not a passive signatory: the QP certifies that the EITC was carried out under his or her supervision. That makes a documented supervision routine essential, with site visits, inspection records and photographs tied to the approved plans. The same discipline applies to building works on the same project, and the team can see how it is structured in the guide to a site supervision plan for BCA.
Shaft and building works need particular attention. BCA’s earlier guidance already stated that installation of any new lift, including platform, chair and stair lifts, and related building works such as shafts had to be approved by BCA with QPs engaged to supervise the works. That guidance is dated 2012 and the regulations have since been replaced, but the principle that the lift and the structure around it are approved together has continued to shape how project teams plan the work. In practice this means the pit depth, overhead clearance, machine room loads, fire-rated shaft construction and builders’ work openings are fixed in the structural, architectural and M&E drawings before the lift supplier’s installation begins. A late change to a lift model can alter any of these.
Stage 3: EITC, the inspection report and the PTO
A valid PTO is required before owners can operate lifts, escalators and mechanised car parking systems, as BCA’s legislations page states. The documents involved are listed on BCA’s forms and certificates page:
- Certificate of Supervision of Installation.
- Certificate of Lift Examination, Inspection and Testing.
- Lifts PTO Application.
The same page states that QPs must submit the EITC Inspection Report as part of BCA’s review for all PTO applications submitted from 1 January 2026. BCA provides templates, updated in September 2025, for each lift type listed above. Using the correct template for the installed lift type, and completing every field from actual test records, is the basic discipline of this stage. BCA’s FI plans submission details sheet was also updated in May 2026 to reflect the updated SS 626:2024 code for escalators and moving walks, so teams working on escalators should confirm they hold the current version.
The PTO itself is a permit issued by the Commissioner of Building Control under regulation 32, and the regulations define “operate” broadly, including allowing or authorising operation, according to the text of the 2025 Regulations. An owner who lets tenants or the public use a lift before the PTO is issued is therefore exposed, even if the lift has physically been commissioned. Fit-out schedules, handover dates and temporary occupation applications should be sequenced so that the PTO is not the last item discovered on the critical path.
After the PTO: maintenance and annual testing
Approval does not end with the PTO. Regular maintenance and testing are required under Regulation 39 of the 2025 Regulations. BCA states that all lifts undergo annual inspection and testing by a BCA-registered FI service contractor with an independent SPE or FI Inspector present. Owners should plan the maintenance contract and the annual test schedule as part of project handover.
When an existing lift is altered or replaced
Modernisation projects fall under the same regime. Under BCA’s legislations page, when a lift undergoes major alteration or replacement works, its PTO ceases. The sequence is then:
- The owner notifies the Commissioner in writing and, where required, obtains plan approval before starting works.
- A BCA-registered FI works contractor performs the works, supervised by a Supervisor QP.
- The Supervisor QP certifies that the lift is fit for operation.
- The owner applies for a new PTO.
The consequence for building owners is that the lift is out of service from the day the PTO ceases until the new one is issued. Replacement programmes for residential, commercial and industrial buildings should therefore be scheduled with the approval period and the commissioning period built in, and with temporary access arrangements for occupants.
Common points where lift approvals stall
- Appointment sequence. The Authorisation form requires the plan submission QP and the FI works contractor to be named. Changing either after submission can mean resubmission.
- Document validity. Type testing certificates and specifications must be valid and complete when they reach the QP (Plans).
- Shaft coordination. Structural, architectural and M&E drawings must reflect the lift supplier’s final data. Differences found at installation cause rework in concrete and steel.
- BIM data. On projects above 5,000 m², lift models must meet BCA’s data requirements.
- EITC records. The inspection report is now part of BCA’s review of PTO applications, so incomplete test records delay the permit.
- Occupation before the PTO. Using the lift before the permit is issued is the most serious sequencing error, because the regulations treat allowing operation as operating.
How lift approval fits into the wider BCA submission
Lift installation approval is a submission under the fixed installation regime, but it rarely stands alone. The building plans that contain the shaft, the structural frame carrying the machine room and the electrical supply all go through the broader BCA building plan process. Teams that want to see how those submissions are staged can consult the guides on BCA plan submission requirements, how to submit BCA plans in Singapore and the construction approval workflow. Coordination between the lift submission and the building submission is where project schedules are most often protected or lost.
Where AECTechnicalSG supports the approval path
AECTechnicalSG provides BCA submissions and approvals, statutory authority submissions, PE endorsements, structural and geotechnical engineering, architectural design, M&E engineering design and BIM modelling for projects in Singapore. For a project with a new lift, these services cover the building-side work that surrounds the lift submission: the structural design and checks for the shaft and machine room, the architectural and M&E coordination, the BIM model on larger projects and the BCA submission process. Our positioning is timely, responsive and competitively priced service with direct communication. Developers and owners can review the full service list on the AECTechnicalSG services page.
For project teams planning a new building or a lift replacement, the useful first step is to share the drawings and programme so that submission sequencing can be agreed before the lift supplier is fixed.
Our perspective
Lift approval is often treated as the lift contractor’s problem. Under the 2025 regulations, that view leaves the developer or owner holding the legal duty without the information to manage it. The appointments, the plan approval and the PTO all belong to the owner, and the owner’s project team is the only party that sees the structure, the architecture, the services and the lift together.
We see the approval as a coordination exercise first and a form-filling exercise second. The documents the QP (Plans) needs are only reliable when the shaft geometry, structural loads, fire separation and electrical supply in the building submission agree with the lift data. That is the work our structural, architectural and M&E teams do as part of BCA submissions and PE endorsements, and it is why we advise bringing the building design and the lift submission into one programme from the earliest design stage.
The 2025 change to a split QP model rewards teams that document as they go. A supervisor who certifies the EITC needs a record that stands up on its own. We recommend that owners agree the evidence trail with their QPs and contractor before works begin, and that submissions on projects above 5,000 m² treat BIM data as a design deliverable, not a late conversion.
Aman
FAQ
What approvals are needed to install a lift in Singapore?
The developer or owner must appoint an FI works contractor, a QP (Plans) and a QP (Supervisor), obtain BCA approval of the plans before works begin, and obtain a PTO before the lift is operated. These requirements apply from 1 October 2025 under the BC (FI) Regulations. Building works around the lift, such as the shaft, follow the wider building plan process.
Does the QP for a lift have to be a Professional Engineer?
Yes, but a specific kind. Both the plan submission QP and the supervisor QP must be a qualified person who is also a Specialist Professional Engineer registered in the lift and escalator engineering branch and holding a valid practising certificate in that branch.
What must be submitted for the permit to operate?
BCA’s forms page lists the Certificate of Supervision of Installation, the Certificate of Lift Examination, Inspection and Testing, and the Lifts PTO Application. For PTO applications submitted from 1 January 2026, the QP must also submit the EITC Inspection Report. Applications are made through the LEAP portal.
Is a new PTO needed when a lift is replaced?
Yes. When a lift undergoes major alteration or replacement, its PTO ceases. The owner notifies the Commissioner, obtains plan approval where required, has a registered FI works contractor carry out the work under a Supervisor QP, and then applies for a new PTO.
Sources
- Regulatory updates, Building and Construction Authority
- Building Control (Fixed Installations) Regulations 2025, Singapore Statutes Online
- Fixed Installations Legislations, Building and Construction Authority
- Fixed Installations (Lifts, Escalators and Mechanised Car Parking System) Legislations, BCA
- Fixed Installation Regulations guidebooks, BCA
- Forms and Certificates, BCA
- Building Information Modelling (BIM), BCA
- SS 550:2020 preview, Singapore Standards eShop
- Changes to Building Control Act, BCA newsroom
- New Regulatory Regime for Lifts, 2016 factsheet, National Archives of Singapore