Post-Tensioning vs. Pre-Tensioning in Modern Construction
1. Prestressed concrete revolutionized structures, making them stronger, lighter, and more durable
1.1 Unlocking Concrete’s True Potential:
Concrete is the cornerstone of the modern built environment, renowned for its versatility, durability, and exceptional compressive strength.1
It is a material that excels at being squeezed. Its fundamental weakness, however, lies in its opposite: tension.
Plain concrete has a tensile strength that is a small fraction of its compressive strength, making it brittle and prone to cracking when pulled or bent.
The Problem with Tension
For over a century, the standard solution to this problem has been conventional reinforced concrete—embedding steel bars (rebar) in the tensile zones.
This passive reinforcement system is effective, but it is not without its limitations.
The rebar only engages and takes up the tensile force after the surrounding concrete has already cracked.
This cracking is an inherent feature of the design. To control these cracks and carry the load, structural members must often be thick, heavy, and spaced closely, leading to material inefficiencies, larger foundations, and limitations on architectural spans.3
1.2 The Principle of Prestress: Applying Proactive Compression
Prestressed concrete, a technology patented in its modern form by Eugène Freyssinet in 1928, represents a fundamental paradigm shift in structural design.3
Instead of passively waiting for cracks to form, prestressing proactively places the concrete under a state of pre-compression before any service loads are applied.4
This is accomplished by stretching high-strength steel tendons (wires, strands, or bars) and anchoring them against the concrete.
The stretched tendons are in a state of high tension, and in their attempt to return to their original, shorter length, they exert a massive compressive force on the concrete.
The principle is defined as a method of applying pre-compression to “control the stresses resulting due to external loads”.4
The internal compressive stresses are “introduced in a planned manner so that the stresses resulting from the imposed loads are counteracted to a desired degree”.3
A classic analogy is the construction of a wooden barrel.4 The wooden staves (the concrete) are weak on their own and would easily be pushed apart by the tensile (outward) pressure of the liquid inside.
By force-fitting metal bands (the tendons) around the barrel, the bands are placed in tension, which in turn induces a state of “initial hoop compression” on the staves.4
This pre-compression squeezes the staves together, allowing them to resist the liquid’s tensile forces without separating.
The “essence” of prestressed concrete is that this pre-compression creates an “almost ideal combination” of high-strength steel (pre-stretched to realize its full strength) and modern concrete (pre-compressed to minimize cracking).3
This active system 5 fundamentally changes the material’s behavior. When a load is applied to a prestressed beam, the load must first overcome the engineered pre-compression before it can induce any net tension in the concrete.
This results in members that remain uncracked under service loads, allowing for the design of structures that are significantly lighter, thinner, and capable of spanning far greater distances than their conventional reinforced concrete counterparts.3
1.3 Pre-Tensioning and Post-Tensioning: The Two Pillars of Prestressed Design
While the principle of prestressing is singular, its application is divided into two primary methodologies.
Both “post-tensioning and pre-tensioning create prestressed concrete”.5
The fundamental difference between them lies in the timing of the tensioning operation relative to the casting and curing of the concrete.6
- Pre-Tensioning: The steel tendons are stressed before the concrete is placed.6
- Post-Tensioning: The steel tendons are stressed after the concrete has been placed and has hardened to a sufficient strength.6
This simple divergence in process—stressing before versus stressing after—has profound implications. It dictates where the work is done (factory vs. site), how the force is transferred (bond vs. bearing), and ultimately, which solution is best suited for a given project.
This report will provide an exhaustive analysis of both methods, their processes, their applications, and the critical factors engineers and architects must weigh when choosing the right prestressed concrete solution.
2. Deep Dive: The Pre-Tensioning Process—Precision in the Plant
2.1 A Factory-Controlled Method:
Pre-tensioning is almost exclusively a factory-based operation, “normally used for factory production”.10
The entire process is industrialized and optimized for quality, efficiency, and repetition.
From Casting Bed to Project Site
The heart of a pre-tensioning plant is the “prestressing bench” or “casting bed”.4 These are long, robust, permanent fixtures, often hundreds of meters long 4, bookended by massive, fixed “abutments.”
These abutments are the unmoving anchors required to resist the immense forces of the stretched tendons.
This factory setting is the method’s defining characteristic, enabling a high degree of “plant-fabricated quality control” 13 that is difficult to achieve on an active construction site.
2.2 The Step-by-Step Manufacturing Process of Pre-Tensioned Concrete
The manufacturing of a pre-tensioned element, such as a bridge girder or a hollow-core slab, follows a precise, linear sequence.4
Step 1: Stressing the Tendons
Before any concrete is involved, the high-strength steel strands (tendons) are pulled from spools and stretched in parallel down the entire length of the casting bed.
Hydraulic jacks are used to apply a precise, predetermined tensile force to these strands.4 Once the required stress is achieved, the strands are mechanically locked in place at the abutments.4
Step 2: Placing Formwork
With the tendons now held in a state of high tension, steel moulds (forms) are set in place around them.15
These forms define the final shape of the member (e.g., an I-beam, a box beam, or a flat slab). Any non-prestressed reinforcement, such as shear stirrups, is also placed at this time.15
Step 3: Casting the Concrete
The concrete is then poured into the moulds, completely surrounding and encasing the tensioned tendons.4
As the concrete is placed, the tendons are held in their stressed position, separated from each other by the fresh concrete.
Step 4: Curing
The concrete is allowed to cure and harden, a process often accelerated with steam or other methods to increase the plant’s production throughput.16
During this curing, the concrete “becomes bonded to the concrete throughout their length” 4, forming an intimate connection with the surface of the steel strands.
Step 5: Detensioning—The Critical Transfer of Force
This is the most critical step in the pre-Tensioning process.
Once the concrete has achieved a specified minimum compressive strength (e.g., 3000-4000 psi) 10, the tendons are released from the end abutments, typically by cutting them.4
Freed from the external anchors, the high-tension steel strands “tend to regain their original length by shortening”.4
However, they are now locked firmly within the hardened concrete.
As they attempt to shorten, they pull inwards on the concrete, “transfer[ring] a compressive stress to the concrete through bond”.4
This action transfers the prestressing force, putting the entire member into a state of permanent compression.
The long-line method allows for multiple identical elements to be cast and detensioned at once along the same set of strands.
2.3 The Physics of Force Transfer: How Bond Creates Compression
In pre-tensioning, there is no mechanical anchorage at the ends of the element. The force transfer is entirely reliant on the “bond” between the steel and the concrete.4
This bond is a powerful physical phenomenon comprising three mechanisms 4:
- Chemical Adhesion: The natural chemical bond that forms at the interface of the steel and the cement paste.
- Mechanical Interlock: The primary mechanism. The tendons are “twisted strands,” not smooth wires. These helical grooves create a mechanical interlock with the hardened concrete, making it impossible for the strand to pull through without taking the concrete with it.4
- Friction: Frictional forces at the interface, enhanced by the radial expansion of the strand during detensioning.
This radial expansion is part of a phenomenon known as the Hoyer Effect.4
When a tendon is first stretched, its diameter shrinks slightly (due to the Poisson’s effect).
When the tendon is cut (detensioned) and the stress is released, the tendon’s diameter expands back to its original size.
This expansion “creates a ‘wedge effect’ in the concrete,” powerfully locking the strand in place and significantly enhancing the bond-based force transfer.4
This transfer of force does not happen at the exact end of the beam but over a short, defined length known as the “transmission length” or “transfer length”.4
The factory-controlled environment is pre-tensioning’s greatest strength, but it also creates its primary limitation.
The strength is undeniable: “plant-fabricated quality control” 13 results in products that are “more reliable” 12 and “durable”.18 The process is repeatable, efficient for “similar prestressed members” 19, and not subject to on-site weather conditions.20
The limitation is a direct consequence of this. The finished “precast” product must be transported from the factory to the project site.8
This physical constraint of transportability (what can fit on a truck or train) fundamentally limits the maximum size, shape, and scale of pre-tensioned elements, which in turn restricts architectural and design flexibility.22
3. Deep Dive: The Post-Tensioning Process—Flexibility on the Site
3.1 An In-Situ Solution: Building the System as You Go
Post-tensioning operates on the opposite principle. It is an “on-site” or “cast-in-place” method.7
Rather than manufacturing a product in a factory, post-tensioning is a construction method used to build a structure.
This approach immediately solves the primary limitation of pre-tensioning: transport. Because the stressing occurs after the concrete is cast in its final position, the method is “preferred when the structural element is heavy”.8
There are no transportable size restrictions, which “allows almost any shape to be constructed” 22 and enables the creation of large, seamless, monolithic structures directly on site.
3.2 The Step-by-Step On-Site Process of Post-Tensioning
The on-site procedure for post-tensioning a typical elevated slab in a building or parking garage follows a well-defined sequence.14
Step 1: Formwork and Rebar
Formwork is erected on-site to create the mould for the slab or beam.24 Conventional rebar is placed to handle shear and other secondary stresses.
Step 2: Positioning Ducts and Anchorages
This is a key step. A network of hollow ducts, or “sheathing,” is laid out within the formwork according to the engineer’s plans.14
These ducts, typically made of plastic or metal, are the “sleeves” through which the tendons will later be threaded.
Crucially, these ducts are not laid flat. They are “draped” in a specific parabolic profile.26 The duct is secured “low at the midpoint of a beam” (to counteract the tensile stresses at the bottom of the span) and “high at the supports” (to counteract the tensile stresses at the top of the slab over a column).26
Mechanical “anchorage” devices are fixed at the ends of the ducts at the edge of the formwork.26
Step 3: Casting the Concrete
Concrete is poured into the formwork, completely encasing the draped ducts and the rebar.6 At this stage, the ducts are either empty or contain tendons that are unbonded and free to move.
Step 4: Curing
The concrete is cured on-site until it achieves a specified compressive strength required for stressing, often around 2,000 to 3,000 psi, which can be achieved in 3 to 10 days.24
Step 5: Stressing the Tendons
Once the concrete is strong enough, the stressing operation begins. High-strength steel strands (tendons) are fed through the ducts (if not already present).14
A powerful, portable hydraulic jack 13 is attached to the “tendon tail” 28 that protrudes from the “live end” anchorage.29
The jack “pull[s] them tight,” 25 stretching the tendons to a precisely specified force.
This force is immense; a single half-inch strand in a slab can be pulled with 33,000 pounds of force, which might “stretch—about 8 inches in a 100-foot cable”.26
This stressing should only be performed by qualified, certified workers.26
Step 6: Anchoring and Finishing
While the jack holds the tendon at its full extension, small, conical “wedges” are set into the “anchorage” device.30
These wedges grip the strand. The jack’s pressure is then released. The tendon attempts to shorten, but the wedges bite in, “locking” the force into the anchorage.
This force is then transferred to the concrete not by bond, but by bearing.18
The anchorage “bears” against the hardened concrete, imparting the compressive force to the entire slab.
The excess tendon tail is then cut off, and the “stressing pocket” is filled with a protective grout to prevent corrosion.26
3.3 A Critical Distinction: Bonded vs. Unbonded Post-Tensioning
Within post-tensioning, a critical choice must be made between two distinct systems: bonded and unbonded.3
Bonded Post-Tensioning
- Process: In a bonded system, the tendons are fed through a hollow, typically corrugated (plastic or metal) duct. After stressing and anchoring, the entire duct is “injected with a cement-based slurry (grout)”.25
- Mechanism: This special grout flows to fill all voids in the duct and then hardens, “creat[ing] a bond between the tendon, grout, and surrounding concrete member”.3
- Advantages: This bond provides “higher ultimate strength” 33, “improved crack control” 3, and “improved fire performance”.3 Most importantly, it creates system redundancy. If the member cracks, the bonded tendon responds similarly to rebar, controlling the crack locally.3 A local failure in the tendon or anchorage is not catastrophic, as the force can be “transferred by bond in a manner similar to ordinary pre-tensioned members”.34 This makes bonded systems the standard for critical, high-load structures like bridges.
Unbonded Post-Tensioning
- Process: In an unbonded system, each tendon is individually “coated with grease” (a corrosion-inhibiting compound) and “encased in a plastic sheathing” before it is ever brought to the site.25 This greased-and-sheathed strand is then laid out in the formwork.
- Mechanism: No grout is applied after stressing.25 The tendon “is permanently free to move relatively to the concrete”.28 The prestressing force is transferred to the concrete only by the anchorages at each end.35
- Advantages: This system is “light and flexible,” and the unbonded “mono strand can be easily and rapidly installed”.31 This speed and lower cost make it the dominant, economical solution for buildings, parking garages, and residential slabs-on-ground.26
The choice between bonded and unbonded is one of the most significant in modern construction, representing a direct trade-off between initial cost and long-term robustness.
The unbonded system is faster and more economical to install 31, which is why it is the default for commercial and residential buildings where speed and budget are primary drivers.26
However, this economy comes with a risk. The unbonded system’s durability relies entirely on two components: the end anchorages 35 and the integrity of the thin plastic sheathing.36
If this sheathing is damaged during or after construction, “moisture that does enter the tendon sheathing can degrade the PT coating, eventually resulting in corrosion”.36
Because the tendon is unbonded, a single strand break (from corrosion or accidental cutting) can result in a 100% loss of force for that entire tendon, as the force cannot be redistributed to the concrete through bond.
Bonded systems, in contrast, are more expensive and complex. Grouting is an additional, highly-skilled step that requires specialized equipment and quality control.38
However, this extra step provides a far more robust, redundant, and durable structure, which is why it is the required standard for most major public infrastructure, such as bridges.3
3.4 The Hardware That Makes It Work: A Look at Anchorages, Wedges, and Ducts
Post-Tensioning systems are “proprietary designs” 30 available from several specialized suppliers, with all components manufactured to rigorous industry standards, such as those set by the Post-Tensioning Institute (PTI).39
The key components of the system include:
- Anchorage Assembly: This is the complete device that transfers the force. It consists of a “bearing plate” (which sits against the concrete) and an “anchor head” or “wedge plate” (which holds the wedges).30
- Wedges: The conical, toothed pieces of steel that grip the “tendon tail” and prevent it from slipping back into the duct after stressing.28
- Duct/Sheathing: The hollow conduit, (e.g., corrugated plastic 41) in bonded systems or the individual plastic sheathing in unbonded systems, that creates the void for the tendon.
- Trumpet: A tapered fitting that connects the duct to the bearing plate, allowing the bundled strands to “transition from the wedge plate pattern into a tight bundle inside the duct”.28
- Grout Caps and Vents: Used in bonded systems. “Grout vents” 42 are placed along the duct to allow air and water to be expelled, ensuring the duct fills completely with grout. “Grout caps” 28 are used to seal the anchorage after stressing and provide an inlet port for grout injection.
4. Post-Tensioning vs. Pre-Tensioning:
The choice between pre-tensioning and post-tensioning is a pivotal decision in a project’s design phase. While both achieve the same goal of pre-compression, their methodologies, costs, and applications are vastly different.
The following table synthesizes the comparison points from a wide range of technical sources.7
A Head-to-Head Comparison
Table 1: Post-Tensioning vs. Pre-Tensioning: A Comparative Analysis

| Feature | Post-Tensioning | Pre-Tensioning |
| Tensioning Timing | After concrete is cast and cured [6, 7] | Before concrete is cast [6, 7] |
| Location of Work | On-site (in-situ) [7, 10, 24] | Factory / Precast Plant (off-site) [7, 10, 12] |
| Force Transfer | Bearing: At mechanical anchorages at ends [18, 19, 35] | Bond: Continuous bond between strand and concrete [4, 18, 19] |
| Tendon Profile | High Flexibility: Can be “draped” in any curve to follow bending moments [16, 22, 26] | Limited: Typically straight or “harped” (simple, single-point deflections) 22 |
| Design Flexibility | Very High: “Almost any shape”.22 Ideal for complex, monolithic, or curved structures 24 | Low: Limited to shapes/sizes that are “easily transportable” [8, 19, 22, 23] |
| Typical Element | Heavy, large-scale, or custom members.8 Slabs, beams, foundations 7 | Small, repetitive, transportable members.8 Beams, piles, hollow-core [3, 7] |
| Structural Continuity | Excellent: Ideal for creating continuous, monolithic structures and rigid frames 45 | Limited: Difficult to create continuous structures; typically used as simple-span elements 22 |
| Key Equipment | Portable hydraulic jacks, ducts/sheathing, anchorages, wedges [13, 25, 30] | Long-line stressing beds, massive abutments, anchor grips 4 |
| Durability | Variable: Reliant on quality of on-site work (grouting/sheathing) 7 | High: High-quality, durable element due to factory control 13 |
| Economics | Higher “initial” on-site cost 7 but reduces overall project cost via material savings [11, 46, 47] | “Cheaper” per-element cost 18 due to mass production. |
A deeper analysis of this comparison reveals two critical, high-level takeaways that go beyond the technical data.
- The “Product vs. System” Distinction
The most fundamental way to frame the debate is to understand that the two methods are not just different techniques; they are different design philosophies.
- Pre-tensioning is a manufacturing process used to create discrete products.10 The unit of construction is the “element”—a girder, a slab, a pile.3 An engineer buys a pre-tensioned girder as a finished component.
- Post-tensioning is a construction method used to create integrated systems.10 The unit of construction is the “structure”—a monolithic floor system, a continuous bridge, a building frame.45 An engineer builds a post-tensioned slab.
This distinction explains why their applications are so different.
The decision is not merely “pre- vs. post-,” but a strategic choice between a prefabrication philosophy and an in-situ philosophy.
- The “Local vs. Global” Cost Paradox
The economics of prestressing can be misleading if not analyzed correctly.
- Locally: It is true that pre-tensioning is “cheaper” on a per-element basis because it avoids the cost of on-site sheathing and labor.18 It is also true that post-tensioning has a “higher initial cost” on-site due to the need for specialized equipment and skilled labor.7
- Globally: The total project economics often tell the opposite story. Post-tensioning “saves money on multiple fronts”.11 By enabling thinner slabs and longer spans, it triggers a cascade of savings:
- Less concrete and steel used.46
- Lighter building weight, which “reduced[s] foundation loads”.45
- Lower “floor-to-floor height,” which reduces the total building height and saves money on exterior façade components.45
Therefore, the “more expensive” method (post-tensioning) often produces the “less expensive” total building.
This “global” economic analysis is a critical insight for architects, developers, and project owners.
5. Applications and Case Studies: When to Use Pre-Tensioning
5.1 The Backbone of Infrastructure: Why Pre-Tensioning Dominates Precast
Pre-tensioning is the default choice for the precast concrete industry.
Its applications are defined by the “product” philosophy: elements that can be mass-produced in a factory, trucked to a site, and erected quickly.7
The key drivers are the economics of “bulk” production 21 and the superior, “reliable” quality achieved in a controlled plant environment.13
5.2 Application Focus:
This is the quintessential application for pre-tensioned concrete.
Pre-tensioned girders are the “leading choice for bridge construction across the country”.20
Bridge Girders (I-Beams, U-Beams, Box Girders)
Engineering Rationale:
The reasons for this dominance are clear. Pre-tensioned girders offer a long service life and require less maintenance.20
The factory-controlled pre-compression “minimizes cracking and increases the member’s durability”.51
The method is “particularly economical when longer beam lengths are required,” with standard shapes suitable for spans up to 200 feet.51
However, the single most significant driver in modern infrastructure is construction speed.
Because the girders are “fabricated off-site, then transported and erected into place at the job site,” they are the core of “Accelerated Bridge Construction” (ABC).20
This methodology “facilitate[s] the rapid construction of a bridge,” which is critical for projects “where minimal traffic disruption is necessary”.51
5.3 Case Study in Practice: Accelerated Bridge Construction (ABC)
A Federal Highway Administration (FHWA) case study of the Mill Street Bridge replacement in New Hampshire provides a perfect example.52
- Project: Replacement of two short-span bridges with a single 115-foot span.52
- Challenge: The project required an accelerated timeline to minimize disruption to the community.
- Solution: The design used “all precast concrete elements,” centered on “precast prestressed adjacent box beam bridges”.52
- Rationale: These pre-tensioned elements were chosen specifically because they “allow for a simple superstructure that can be built very quickly because there is no need for a reinforced concrete deck” to be cast on-site.52
- Outcome: The contractor was given a 14-day construction window for the bridge installation. By using pre-tensioned, precast elements, the entire bridge was completed in eight days.52 This case study is a clear, real-world demonstration of the “rapid construction” advantage 51 that defines pre-tensioned girders.
5.4 Application Focus: Hollow-Core Slabs, Piles, and Other Elements
While bridges are the most visible application, pre-tensioning is used for many other essential “products”:
- Hollow-Core Slabs: Efficient, lightweight floor and roof slabs. The “hollow” cores reduce the slab’s self-weight and material use, making them economical and easy to install.3
- Prestressed Piles: The pre-compression induced by pre-tensioning makes concrete piles “very strong and durable”.3 This pre-compression is ideal for withstanding the immense impact stresses and tensile “whip” of being “driven” into the ground by a pile hammer.
- Other Elements: The method is used for a wide variety of “similar prestressed members” 19, including “railway ties” 7, building “wall panels” 54, and “lintels”.3
6. Applications and Case Studies: When to Use Post-Tensioning
6.1 Shaping the Modern Cityscape: Why Post-Tensioning Enables Architectural Vision
Post-tensioning is the “in-situ” solution that defines modern cityscapes.8
Its applications are defined by the “system” philosophy: creating large, monolithic, and structurally efficient structures on-site.
The key drivers are “design flexibility” 7, the ability to achieve “longer spans” 7, and the creation of “thinner structural members”.11
6.2 Application Focus: High-Rise Buildings and Parking Structures
This is the quintessential application for post-tensioning.
For commercial offices, high-rise residential buildings, and parking structures, post-tensioning is not just an option; it is often the only economical and practical solution.29
Engineering Rationale:
The rationale for using post-tensioning in buildings is a “compounding virtuous cycle” of economic and structural benefits.
- Thinner Slabs: The primary benefit. Post-tensioning allows for “longer, thinner slabs” than any other method.45
- Material Savings: This immediately “reduces the amount of concrete and reinforcing steel required” 45, a direct “upfront” cost saving.46
- Lighter Buildings: The thinner, lighter slabs “lower floor weight” 45, which “reduces the overall weight of the structure”.7
- Foundation Savings: This reduced building mass leads to “reduced foundation loads”.45 This is a massive economic benefit, as foundations are one of the most expensive and high-risk parts of a project.
- Height and Façade Savings: Thinner slabs also mean “lower floor-to-floor height”.45 This “can reduce a building’s overall height” and “lower costs for components like façade treatments”.50
- Massive ROI Increase: Crucially, for high-rises, the lower floor-to-floor height allows designers to “accommodate more floors” within a given zoning height limit 29, dramatically increasing the “return on investment for developers”.56
- Open Spaces: Simultaneously, the method allows for “larger spans between columns”.45 This creates the “large, uninterrupted spaces” 56 and “open interiors” 50 that are highly valued in commercial offices 56 and essential in parking garages (for “maximizing available space for car parking”).29
This powerful cascade of interconnected benefits 57 is why post-tensioning has become the dominant structural system for these building types.
6.3 Application Focus: Slabs-on-Ground and Foundations
Post-tensioning is also a superior solution for foundations, particularly residential and commercial “slabs-on-ground” built on “expansive or soft soils”.11
Engineering Rationale:
Unstable soils expand and contract with moisture changes, causing conventional slabs to heave, settle, and crack. Post-tensioning actively “compensates for poor site conditions”.57
The grid of tendons, stressed in both directions, “squeez[es] the slab together” 46, putting the entire foundation in a state of permanent compression.45
This “vise grip” 46 “significantly removes the risk of shrinkage cracks” 57 and creates a stiff, monolithic mat that can “float” on the unstable ground, resisting the differential soil movements that would “destroy traditional slabs”.46
As one case study noted, this strength was used to build tennis courts over an unstable former city dump, preventing the “cracking or vibrating that would likely occur with a more traditional concrete system”.50
6.4 Case Study in Practice: The Curitiba Residence
A case study of a high-end, modern residence in Curitiba, Brazil, perfectly illustrates how post-tensioning is an enabling technology that makes bold architectural visions a physical reality.58
- Project: A four-level modern home with a strong “Scandinavian influence”.58
- Challenge: The architect demanded a “fair-faced concrete finish” (requiring minimal cracking) and an “open view”.58 This translated to extreme structural challenges: a 42-foot span and a 16-foot cantilever on the first floor, all with a “limited slab thickness of only 10 in.”.58 This was structurally impossible with conventional reinforcement.
- Solution: The engineer used 0.5-inch unbonded post-tensioning tendons to achieve the 10-inch-thick slab spans.58
- Innovative Solution: The design required “stayed columns” (tensile elements) to hang the first floor from the roof. To build these “tensile elements” out of concrete without them cracking, the engineer used post-tensioning thread bars to “compress these stayed columns, until the tensile stresses were less than the compression inserted by the post-tensioning”.58
- Outcome: “The post-tensioning solutions allowed the architectural project to be safely, efficiently, and durably constructed while maintaining aesthetics”.58
This case study is the perfect example of post-tensioning’s value.
It was not merely a “cheaper” or “stronger” alternative; it was the only solution that could make the architect’s design physically achievable.56
7. Advanced Systems: The Best of Both Worlds
While pre-tensioning and post-tensioning are often presented as competing choices, the most advanced structural designs use them as collaborating partners.
These “hybrid prestressing systems” 59 combine both methods to create solutions that are superior to what either could achieve alone.
7.1 Hybrid Design: Connecting Pre-Tensioned Girders with Post-Tensioning
This “spliced girder” system 60 is designed to “fill the gap” between the maximum span of a transportable pre-tensioned girder (around 160 feet) and the span of a large-scale, cast-in-place segmental bridge.60
The method involves using multiple, shorter pre-tensioned girder segments, which are manufactured in a factory.
These segments are transported to the site, erected on piers, and “spliced” together. Post-tensioning tendons are then fed through ducts running the entire length of the spliced segments and tensioned on-site.60
This “makes these precast concrete bridges continuous” 60, allowing precast technology to be used for much longer spans while achieving the structural benefits of a continuous, monolithic system.
7.2 Application Focus: Transverse Post-Tensioning in Bridges
A more common and critical hybrid system involves using post-tensioning to solve the single greatest weakness of precast girder bridges.62
- Problem: Standard “Accelerated Bridge Construction” (ABC) often uses precast, pre-tensioned “adjacent box-girders”.62 These are set side-by-side, and the “longitudinal cracks over the shear keys” (the grouted joints between the beams) are a notorious failure point.62
- Consequence: These cracks “jeopardize the durability” of the bridge. They allow “chloride-laden water to penetrate… causing corrosion of the steel reinforcement” (both the rebar and the prestressing strands). This leads to “severe deterioration and premature replacement” of bridges that were designed to be durable.62
- The “Hybrid” Solution: After the pre-tensioned girders are set in place, “transverse ties” in the form of “several post-tensioned tendons” are threaded through the adjacent beams, perpendicular to the direction of traffic.62
- Mechanism: These tendons are then tensioned, actively “squeezing” the beams together. This transverse compression “minimize[s] differential deflections” and “minimize[s] the tensile stresses that cause longitudinal cracking at the joints”.62 This system creates a “high degree of monolithic action,” effectively transforming an assembly of individual beams into a single, unified, and far more durable structural slab.62
This hybrid approach represents the synthesis of the two philosophies.
It uses pre-tensioning for what it does best: create high-quality, economical, transportable products (the girders) in a factory.10
It then uses post-tensioning for what it does best: create robust, monolithic, on-site systems.24
The post-tensioning “stitches” the precast elements together, solving the precast system’s greatest weakness (the joints 62) to create a continuous, high-performance structure.
8. The Engineer’s Decision Matrix:
The selection of a prestressing system is a critical engineering decision driven by project-specific requirements, including geometry, cost, schedule, and structural goals.43
The following decision matrix provides a practical framework for architects, engineers, and developers to navigate this choice.
Choosing the Right Solution
Table 2: The Engineer’s Decision Matrix: Pre-Tensioning vs. Post-Tensioning
| Project Factor | Choose Pre-Tensioning if… | Choose Post-Tensioning if… |
| Project Type | …your project involves repetitive, modular components.[21, 44]
Examples: Bridge Girders, Hollow-Core Slabs, Piles, Railway Ties [3, 7] |
…your project is a large, monolithic, or cast-in-place structure.[8]
Examples: High-Rise Slabs, Parking Garages, Slabs-on-Ground, Segmental Bridges 29 |
| Design Geometry | …the design is linear and based on standard, transportable shapes with straight or simple “harped” tendon profiles.22 | …the design is geometrically complex, curved, or requires “architectural freedom” and “almost any shape”.[7, 22, 23] |
| Primary Structural Goal | …your goal is high-quality, highly durable, individual elements capable of withstanding high loads and impacts (e.g., pile driving).54 | …your goal is to achieve the longest possible spans [44], the thinnest possible slabs 45, and a continuous, monolithic system. |
| Site Constraints & Schedule | …you have good site access, a laydown area, and crane capacity. Your primary goal is rapid, all-weather installation of finished components.[20, 43, 51] | …you are on a tight urban site [64], or need on-site flexibility for adjustments.54 Speed is achieved via faster floor-to-floor construction cycles.45 |
| Economic Driver | …you are looking for the lowest cost-per-element by leveraging factory-based mass production.[12, 18] | …you are looking for the lowest total project cost via system-wide material reduction (less concrete, steel, foundation, and façade).[11, 47, 50] |
| Labor Requirement | Requires a certified precast plant and a skilled crane/erection crew. | Requires specialized, certified on-site labor for stressing and (if bonded) grouting operations.[7, 26] |
9. Lifecycle Considerations: Durability, Maintenance, and Repair
9.1 The Achilles’ Heel: Corrosion Risk in Prestressed Systems
Prestressed concrete’s primary vulnerability is the corrosion of its high-strength steel tendons.65 This risk is more acute than with conventional rebar for two reasons:
- High Stress: The tendons are under enormous stress. “Minimal pitting” from corrosion can be enough to “rupture the stressed strand,” leading to “serious structural ramifications”.65
- Low Tolerance: The chloride threshold known to initiate corrosion in prestressed strands is approximately half that of conventional reinforcement.65
In pre-tensioned elements, the dense, high-quality concrete from the factory provides “plant-fabricated quality control” and excellent protection.13 The risk is highest at the exposed cut ends of the girders, where moisture can ingress.
In post-tensioned systems, the risk is entirely dependent on the quality of the on-site installation.
In bonded systems, “grout voids” (air pockets) 66, “poor grout quality” 67, or bleed water 66 can leave the strands exposed.
In unbonded systems, any damage to the “plastic sheathing” 37 or “improperly repaired” sheathing 36 can allow moisture and chlorides to enter, “degrade the PT coating,” and cause catastrophic corrosion.36
9.2 The Complexity of Repair: Why You Can’t “Just Drill a Hole”
The “active” compressive force that makes prestressed concrete so efficient is also a double-edged sword.
The high-tension energy stored in the tendons is significant and potentially dangerous.68
This is a critical warning for building owners and maintenance crews: “You never want to cut these tendons unless you mean to and you’ve totally planned for it”.68
Unlike a passive rebar system, “just drilling a hole” for a new pipe or conduit “complicate[s] future modifications”.50
Accidentally cutting a tendon can cause a localized failure and, in unbonded systems, a complete loss of that tendon’s force.
Furthermore, the damage is almost always hidden “in a grout, duct, and concrete system that makes ongoing corrosion difficult to detect before it is too late”.66
This “hidden damage” 69 means that inspection and repair are highly specialized fields, often requiring “non-destructive testing” (NDT) like Ground Penetrating Radar (GPR) to locate the tendons before any concrete is removed.67
9.3 Focus: Repairing Unbonded Post-Tensioning
Repairing unbonded post-tensioned slabs is a common but complex task.
The problem is typically corrosion at an anchorage or at a low point in the drape where water has collected after “infiltrat[ing]” damaged sheathing.36
The repair process is specialized and must follow industry guidelines, such as those from the Post-Tensioning Institute (e.g., “PTI DC80.3-12”).37
- Locate and Expose: Concrete is carefully removed to expose the damaged tendon and anchorage.
- Assess Damage: The extent of corrosion is evaluated.
- Repair or Replace:
- For minor sheathing damage, the sheathing must be “restor[ed]… to a watertight condition” to “keep the repair concrete out… and allow the strand to remain unbonded”.36
- For significant corrosion or a broken tendon, the entire tendon can be de-tensioned, pulled out of its sheathing, and a “new dead end” can be installed and a new tendon “push[ed] through” and “fully tensioned”.70 This “replace-ability” is a unique (though difficult) benefit of the unbonded system.
- Restore: The new tendon is stressed, the anchorage pocket is filled with high-strength, non-shrink grout, and the concrete is patched.70
9.4 The Durability Advantage of Pre-Tensioning
When comparing lifecycles, pre-tensioned, precast elements generally have a durability advantage.
This “reliable” 18 and “durable” 20 nature is not inherent to the method itself, but to its process.
The “plant-fabricated quality control” 13 ensures proper concrete cover, superior concrete mixes, and eliminates the on-site variables (weather, workmanship, grout quality) that can plague post-tensioned systems and lead to long-term durability issues.
10. The Future of Prestressing: Innovations in Materials and Technology
The field of prestressed concrete is not static.
Continuous innovation is focused on enhancing its strengths (efficiency, long spans) and, more importantly, solving its primary weakness: steel corrosion.
10.1 Beyond Steel:
The future of prestressing, particularly in harsh environments, is moving away from traditional carbon steel. The industry is aggressively researching and deploying alternative materials 72, such as High-Strength Stainless Steel (HSSS) and, most notably, Fiber-Reinforced Polymers (FRPs) like Carbon Fiber Reinforced Polymer (CFRP).73
The Rise of Corrosion-Resistant Tendons
These new materials are not simple “drop-in replacements.” They present a complex series of engineering trade-offs, as shown in the data below.
Table 3: Material Properties: Traditional Steel vs. Advanced Tendons (CFRP)
| Property | Traditional Carbon Steel Strand | Carbon Fiber (CFRP) Tendon |
| Corrosion Resistance | Poor: Highly susceptible to chlorides.65 | Excellent / Immune: [73] |
| Ultimate Tensile Strength | ~270 ksi [73] | ~341 ksi (Higher) [73] |
| Elastic Modulus | ~28,500 ksi [73] | ~22,400 ksi (Lower) [73] |
| Yield Behavior | Ductile: Has a clear yield point, providing warning of failure.[73] | Brittle: “No plastic behavior;” fails elastically without warning.[73] |
| Weight | Heavy | “Light Weight” [73] |
| Field Modification | Can be bent (within limits). | “FRP bars cannot be Field Bent” [73] |
| Initial Cost | Baseline | “Higher Initial Cost” [73] |
| Long-Term Cost | High (if maintenance/repair needed) | “Lower life cycle costs” (due to no corrosion) [73] |
This comparison reveals the complex challenge for engineers. CFRP is a “perfect” material in terms of strength and corrosion, but its “brittle” nature (no plastic behavior) and “lower elastic modulus” (it stretches more for the same load) fundamentally change the design calculations for deflections, ductility, and prestress losses.75
10.2 Smarter and Thinner: The Future of Design and Installation
In addition to new materials, new technologies are refining the design and installation process:
- Design Trends: Architects continue to push for “ultra-thin slabs” 78 in high-rises and “hybrid systems” 78 that combine the efficiency of post-tensioned concrete with the lightness of steel frames.
- Smart Technology (Installation): The risk of human error is being reduced. “Automated tensioning systems” 78 with real-time monitoring ensure precise force is applied. Real-time concrete monitoring systems 79 can eliminate the “hairline cracks” 80 that form from stressing concrete too early. By providing real-time data on concrete strength, these systems prove the exact moment the slab is ready for tensioning, “mitigating the risks associated with premature tensioning”.79
- Smart Technology (Lifecycle): The “hidden damage” problem 66 is being solved by “embedded IoT sensors”.81 These sensors can be integrated into precast elements or cast into post-Tensioned slabs to monitor for stress, moisture, or corrosion. This enables “proactive maintenance” 83 and “more efficient maintenance” 31 before a small problem becomes a catastrophic failure.
10.3 Sustainability: Optimizing Materials for a Greener Life Cycle
Prestressed concrete is an inherently sustainable and “green” building practice.45 Its core benefit is “material optimization”.78
By “using less concrete and steel” 3 to achieve the same or greater structural capacity, the “carbon footprint of the construction” is significantly reduced.78
Life-Cycle Assessment (LCA) studies, which analyze the environmental impact of a structure from “cradle to grave,” confirm this.84
The results show that a better design (like post-tensioning) that may have a slightly higher manufacturing impact can lead to a much lower global environmental impact over the structure’s life by reducing material consumption, maintenance, and energy use.84
11. Conclusion: Making the Final Choice
11.1 Summary of Key Differences and Selection Drivers
The 10,000-word analysis of “Post-Tensioning vs. Pre-Tensioning” confirms that there is no single “best” solution. Instead, there are two highly optimized, mature technologies that serve different purposes.
The choice is not simply “stressing before vs. stressing after.” The true decision is a strategic one between two different construction philosophies:
- Pre-Tensioning is the philosophy of prefabrication. It is a manufacturing process for creating discrete products. It should be chosen when the primary project drivers are speed of installation, maximum quality control, and economy through repetition.12 It is the solution for components.
- Post-Tensioning is the philosophy of in-situ construction. It is a construction method for creating monolithic systems. It should be chosen when the primary project drivers are design flexibility, architectural freedom, the longest possible spans, and maximum total-project material efficiency.43 It is the solution for structures.
11.2 The Enduring Value of Prestressed Concrete in Construction
Both pre-tensioning and post-tensioning—and increasingly, the hybrid systems that combine them 62—are essential tools in the modern structural engineer’s toolkit.
They are the technologies that allow us to build “safer, longer-lasting, and more visually appealing” structures.54
By actively placing concrete in compression, they unlock its true potential, enabling the construction of bridges, skyscrapers, and foundations that are more economical, more resilient, and more sustainable than ever before.45
11.3 Final Recommendations for Engineers and Architects
The successful implementation of any prestressed concrete system depends on rigorous engineering and exacting quality control.
The complexity of the forces involved, the high-stakes risk of corrosion, and the specialized nature of the hardware and labor leave no room for error.
It is the final recommendation of this report that all professionals—designers, contractors, and inspectors—adhere to the latest consensus-based standards, design guides, and certification programs.
Consultation with, and adherence to, the technical manuals published by the Post-Tensioning Institute (PTI) 37 and the American Concrete Institute (ACI) 85 is not just a best practice; it is an essential requirement for ensuring a safe, durable, and successful project.
Works cited
- The Vital Role of a Structure Design Engineer » Technical Civil, accessed November 6, 2025, https://technicalcivil.com/role-of-a-structure-design-engineer/
- Self-Healing Concrete: The Future of Sustainable Infrastructure – Technical Civil, accessed November 6, 2025, https://technicalcivil.com/self-healing-concrete-2/
- Prestressed concrete – Wikipedia, accessed November 6, 2025, https://en.wikipedia.org/wiki/Prestressed_concrete
- PRESTRESSED CONCRETE STRUCTURES – RGM College Of …, accessed November 6, 2025, https://rgmcet.edu.in/assets/img/departments/CIVIL/materials/R15/3-2/PSC/PSC%20UNIT%204.pdf
- C O N A CM – BBR Adria, accessed November 6, 2025, http://www.bbr-adria.com/fileadmin/bbr_network/PDFs/Brochures/BBR_CONA_CMX_Vol1_SysApp_EN_Rev3_1216.pdf
- How Prestressed Concrete Works – M.T. Copeland Technologies, accessed November 6, 2025, https://mtcopeland.com/blog/what-is-prestressed-concrete/
- Post-Tensioning in Concrete: A Complete Guide (Definition, Types …, accessed November 6, 2025, https://constructionjobfind.com/post-tensioning-in-concrete/
- Differences of Pre-Tensioning vs Post-Tensioning | MOMENT, accessed November 6, 2025, https://www.moment-solutions.com/the-difference-between-pre-tensioning-and-post-tensioning/
- Understanding Prestressing: Pre-tension or Post-tension – FORCE | Engineering services, accessed November 6, 2025, https://www.force-s.com/post/understanding-prestressing-pre-tension-or-post-tension
- Pre-stressed concrete – HSE, accessed November 6, 2025, https://www.hse.gov.uk/non-metallic-minerals/pre-stressed-concrete.htm
- ASEPT, accessed November 6, 2025, http://www.aseng.in/
- What Is Pre-Tensioned Reinforced Concrete? Benefits and Applications, accessed November 6, 2025, https://barrowmixconcrete.com/what-is-pre-tensioned-reinforced-concrete-benefits-applications/
- Prestressed Concrete 101 – Williams & Works, accessed November 6, 2025, https://williams-works.com/prestressed-concrete-101/
- SECTION 1 INTRODUCTION TO POST-TENSIONED CONCRETE, accessed November 6, 2025, https://www.post-tensioning.org/Portals/13/Files/PDFs/Education/140204-1-PTI%20EDC-130-PT%20Introduction-54.pdf
- Prestressed concrete production in the precast plant, accessed November 6, 2025, https://prestressed-concrete.paul.eu/fileadmin/Files/prestressed-concrete/B147.26_02-en.pdf
- Prestressed vs. Post-Tension Concrete, accessed November 6, 2025, https://nitterhouseconcrete.com/prestressed-vs-post-tension-concrete/
- Transfer Control of Prestressing Strands, accessed November 6, 2025, https://www.pci.org/PCI_Docs/Publications/PCI%20Journal/1992/November/Transfer%20Control%20of%20Prestressing%20Strands.pdf
- Differences of Pre-Tensioning vs Post-Tensioning – PowerPlay, accessed November 6, 2025, https://www.getpowerplay.in/resources/blogs/what-is-the-difference-between-pre-tensioning-and-post-tensioning/
- What is a post tensioned concrete slab? – NoBroker, accessed November 6, 2025, https://www.nobroker.in/forum/what-is-a-post-tensioned-concrete-slab/
- Why Prestressed Concrete Girders are Best for Durable Bridges, accessed November 6, 2025, https://hub.countyprestress.com/news/why-prestressed-concrete-bridge-girders-are-the-preferred-choice-for-long-lasting-bridges
- A CASE STUDY ON PRE-TENSIONING & POST TENSIONING SYSTEMS OF A PRESTRESSED CONCRETE – Semantic Scholar, accessed November 6, 2025, https://pdfs.semanticscholar.org/aa2a/805d8042130afe5308a48a3ee402041713c0.pdf
- ASEP CASTED 2020 eBOOK Pages 201-250 – Flip PDF Download …, accessed November 6, 2025, https://fliphtml5.com/kbxac/ithz/basic/201-250
- SSL PT Manual 2011 External | PDF | Prestressed Concrete | Building Materials – Scribd, accessed November 6, 2025, https://www.scribd.com/document/341815985/Ssl-Pt-Manual-2011-External
- The difference between Post-Tensioned Concrete and Precast?, accessed November 6, 2025, https://eraeng.com/what-is-the-difference-between-post-tensioned-concrete-and-precast/
- Post-Tension Concrete: How It Works, Pros & Cons, etc., accessed November 6, 2025, https://fmpconstruction.com/post-tension-concrete/
- How Post-Tensioned Slabs Are Built – Concrete Network, accessed November 6, 2025, https://www.concretenetwork.com/post-tension/basics.html
- Understanding the Basics of Post Tensioned Slab on Grade Foundations – YouTube, accessed November 6, 2025, https://www.youtube.com/watch?v=UBuv-QhWxP4
- TAB.3‐13 Post‐Tensioning Terminology (PTT), accessed November 6, 2025, https://www.post-tensioning.org/Portals/13/Files/PDFs/Publications/131120-PTI-PTT.pdf
- Post-Tension Concrete Explained: Techniques, Benefits, and Tools – Enerpac Blog, accessed November 6, 2025, https://blog.enerpac.com/post-tension-concrete-explained-techniques-benefits-and-tools/
- GROUTING OF BRIDGE POST-TENSIONING TENDONS – NET, accessed November 6, 2025, https://fdotwww.blob.core.windows.net/sitefinity/docs/default-source/construction/training/selfstudy/tutorial/final-grouting-training-manual-7-30-02.pdf?sfvrsn=73e9fe50_0
- Bonded vs Unbonded Post-Tensioning System, accessed November 6, 2025, https://www.hyxpcwire.com/resources/the-bonded-vs-unbonded-post-tensioning-system.html
- SECTION 3 DESIGN OF POST- TENSIONED COMPONENTS FOR FLEXURE, accessed November 6, 2025, https://post-tensioning.org/Portals/13/Files/PDFs/Education/140204-3-PTI%20EDC-130-Flexure-55.pdf
- Types of Post Tensioning – UCONPT Structural Systems, accessed November 6, 2025, https://uconpt.com/types-of-post-tensioning.html
- Detailing for Post-Tensioned | Structural Technologies, accessed November 6, 2025, https://www.structuraltechnologies.com/wp-content/uploads/2018/02/PT_Detailing.pdf
- Bonded Vs Unbonded | PDF | Prestressed Concrete – Scribd, accessed November 6, 2025, https://www.scribd.com/document/44375617/Bonded-vs-Unbonded
- Sheathing Repairs – Post-Tensioning Institute, accessed November 6, 2025, https://www.post-tensioning.org/Portals/13/Files/pdfs/Education/FAQ16.pdf
- Deterioration, Evaluation, and Repair of Post- Tensioned Condominium Structures, accessed November 6, 2025, https://www.post-tensionproducts.com/wp-content/uploads/2023/06/Deterioration-Evaluation-and-Repair-of-Post-Tensioned-Condominium-Structures-.pdf
- Post Tensioning Tendon Installation and Grouting Manual – Federal Highway Administration, accessed November 6, 2025, https://www.fhwa.dot.gov/bridge/construction/pubs/hif13026.pdf
- PTI Publications – Post-Tensioning Institute, accessed November 6, 2025, https://www.post-tensioning.org/publications.aspx
- Post-Tensioning Institute > Publications > Store, accessed November 6, 2025, https://www.post-tensioning.org/store.aspx
- PRESTRESSED CONCRETE CONSTRUCTION MANUAL – nysdot, accessed November 6, 2025, https://www.dot.ny.gov/divisions/engineering/structures/repository/manuals/PCCM_3rd_Edition_4-2017_rev2019.pdf
- PRESTRESSING DETAILS GENERAL NOTES AND ANCHORAGE DETAILS, accessed November 6, 2025, https://dot.ca.gov/-/media/dot-media/programs/engineering/documents/mets/pt-systems-combined-example-drawings-a11y.pdf
- Understanding the Difference Between Precast vs Post-Tensioned Concrete Slabs – Heldenfels Enterprise, accessed November 6, 2025, https://heldenfels.com/understanding-the-difference-between-precast-vs-post-tensioned-concrete-slabs/
- The Difference Between Pre-Tensioning And Post-Tensioning – Knowledge – Precast Concrete Magnet, accessed November 6, 2025, https://www.precastconcretemagnet.com/info/the-difference-between-pre-tensioning-and-post-102758968.html
- Post-Tensioning Institute > Education > PT Applications > Buildings, accessed November 6, 2025, https://www.post-tensioning.org/education/ptapplications/buildings.aspx
- What Are Post-Tension Slabs & Why Are They Used? – Valcourt Building Services, accessed November 6, 2025, https://www.valcourt.net/blog/what-are-post-tension-slabs-why-are-they-used/
- Post-Tensioned Building Analysis and Design – A Case Study – iarjset, accessed November 6, 2025, https://iarjset.com/upload/2018/march-18/IARJSET%204.pdf
- Post-tensioning systems – VSL, accessed November 6, 2025, https://vsl.com/home/technologies/post-tensioning-systems/
- Advantages and Benefits of Unbonded Post-Tensioning, accessed November 6, 2025, https://gti-usa.net/wp-content/uploads/2020/04/Advantages-and-Benefits-of-Unbonded-Post-Tensioning-English-March-2007.pdf
- Pros and Cons of Post-Tensioned Concrete: An Architect’s Perspective, accessed November 6, 2025, https://neumannmonson.com/blog/pros-cons-post-tensioned-concrete
- Prestressed Concrete Bridge Girders – Structure Magazine, accessed November 6, 2025, https://www.structuremag.org/article/prestressed-concrete-bridge-girders/
- Appendix D: Case Studies – Connection Details for PBES – ABC …, accessed November 6, 2025, https://www.fhwa.dot.gov/bridge/prefab/if09010/appd.cfm
- 10 Practical Applications of Prestressed Concrete – Civil Engineering, accessed November 6, 2025, https://civiltoday.com/civil-engineering-materials/concrete/403-10-practical-applications-of-prestressed-concrete
- Pretensioning and Post tensioning of concrete: A comparison, accessed November 6, 2025, https://www.converge.io/blog/pretensioning-and-post-tensioning-of-concrete
- Strength with Post Tensioning in Saudi Arabia | SFMGC, accessed November 6, 2025, https://sf-mgc.com.my/post-tensioning-in-saudi-arabia/
- Post tensioning in building structures | Converge.io, accessed November 6, 2025, https://www.converge.io/blog/post-tensioning-in-building-structures
- Why Should Buildings Use Post-Tensioning Systems? – Valcourt Building Services, accessed November 6, 2025, https://www.valcourt.net/blog/why-should-buildings-use-post-tensioning-systems/
- PTI JOURNAL Case Studies – Post-Tensioning Institute, accessed November 6, 2025, https://www.post-tensioning.org/Portals/13/Files/PDFs/Publications/Reprints/2021_June/PJ2021_V17_N1_Case_Study_Post_Tensioning_in_Stayed_Columns_EVEHX.pdf
- Self-Launching Erection Machines for Precast Concrete Bridges – Marco Rosignoli, accessed November 6, 2025, https://www.marcorosignoli.com/blogs/publications/self-launching-erection-machines-for-precast-concrete-bridges
- Continuous Prestressed Concrete Girder Bridges Volume 1: Literature Review and Preliminary Designs, accessed November 6, 2025, https://static.tti.tamu.edu/tti.tamu.edu/documents/0-6651-1.pdf
- Design Comparison of Prestressed vs. Post-Tensioned Precast Concrete Bridge Beams, accessed November 6, 2025, https://www.pci.org/PCI/News-Events/Papers/2002/Transportation/Design-Comparison-of-Prestressed-Vs-PostTensioned-Precast-Concrete-Bridge-Beams.aspx?WebsiteKey=5a7b2064-98c2-4c8e-9b4b-18c80973da1e
- Transverse post-tension- ing design and detailing of precast …, accessed November 6, 2025, https://www.pci.org/PCI_Docs/Publications/PCI%20Journal/2009/Fall/Transverse%20post-tensioning%20design%20and%20detailing%20of%20precast%20prestressed%20concrete%20adjacent-box-girder%20bridges.pdf
- Acoustic Emission Monitoring of Prefabricated and Prestressed Reinforced Concrete Bridge Elements and Structures – ROSA P, accessed November 6, 2025, https://rosap.ntl.bts.gov/view/dot/66314/dot_66314_DS1.pdf
- DURABILITY AND REPAIR ISSUES FOR PRESTRESSED CONCRETE STRUCTURES, accessed November 6, 2025, https://www.infracorr.com/news/prestressed-concrete
- FHWA-HRT-24-148: Corrosion-Induced Major Tendon Failures in Post-Tension (PT) Concrete Bridges, accessed November 6, 2025, https://highways.dot.gov/media/56751
- Common Challenges in Post-Tension Slabs and How to Overcome …, accessed November 6, 2025, https://www.coloscapesconcrete.com/common-challenges-in-post-tension-slabs-and-how-to-overcome-them/
- How Prestressing Works! (Structures 6-4) – YouTube, accessed November 6, 2025, https://www.youtube.com/watch?v=D4LjkuyE-yg
- Post-Tension Repair: Common Concrete Problems & Myths of Post Tensioning Debunked, accessed November 6, 2025, https://aprilservices.com/2025/10/30/post-tension-repair-common-concrete-problems-myths-of-post-tensioning-debunked/
- What Happens When A Post-Tension Slab Fails? – Dalinghaus Construction, accessed November 6, 2025, https://www.dalinghausconstruction.com/blog/post-tension-slab-failure-solutions/
- Evaluation, Repair and Protection of Unbonded Post-Tensioning in Parking Structures – Concrete Preservation Alliance, accessed November 6, 2025, https://www.wesavestructures.info/uploads/content/PostTensioning.pdf
- Understanding Pre and Post Tensioning Systems in Modern Bridge Construction -, accessed November 6, 2025, https://deevinss.com/understanding-pre-and-post-tensioning-systems-in-modern-bridge-construction/
- CFRP & HSSS Strands in Prestressed Concrete Design – NET, accessed November 6, 2025, https://fdotwww.blob.core.windows.net/sitefinity/docs/default-source/structures/innovation/frp/fts18-cfrp-hsss_prestressed.pdf?sfvrsn=62e31211_2
- The Use of Unbonded Tendons for Prestressed Concrete Bridges – DiVA portal, accessed November 6, 2025, http://www.diva-portal.org/smash/get/diva2:431710/FULLTEXT01.pdf
- Comparison of prestress loss of BFRP tendons and steel strands in the… – ResearchGate, accessed November 6, 2025, https://www.researchgate.net/figure/Comparison-of-prestress-loss-of-BFRP-tendons-and-steel-strands-in-the-prestressing-stage_fig1_346499392
- Transfer and Development Lengths of FRP Prestressing Tendons, accessed November 6, 2025, https://www.pci.org/PCI_Docs/Publications/PCI%20Journal/2000/March-April/Transfer%20and%20Development%20Lengths%20of%20FRP%20Prestressing%20Tendons.pdf
- DESIGN RECOMMENDATIONS FOR CONCRETE STRUCTURES PRESTRESSED WITH FRP TENDONS FHWA CONTRACT DTFH61-96-C-00019 Final Report August – ROSA P, accessed November 6, 2025, https://rosap.ntl.bts.gov/view/dot/50274/dot_50274_DS1.pdf
- Innovative Trends in Post-Tension Slabs for Modern Architecture …, accessed November 6, 2025, https://www.coloscapesconcrete.com/innovative-trends-in-post-tension-slabs-for-modern-architecture/
- Post-Tensioned Concrete: Enhancing Strength with Real-Time Monitoring and Innovation, accessed November 6, 2025, https://www.converge.io/blog/post-tensioning
- Risks of delaying tensioning of PT tendons? : r/StructuralEngineering – Reddit, accessed November 6, 2025, https://www.reddit.com/r/StructuralEngineering/comments/190u0jz/risks_of_delaying_tensioning_of_pt_tendons/
- 2025: The Future of Precast Concrete in the USA – BIG Block Retaining Walls by LondonBoulder |, accessed November 6, 2025, https://www.londonboulder.com/2025-the-future-of-precast-concrete-in-the-usa/
- 9 Emerging Trends Reshaping the Precast Concrete Industry in 2025. – Modular Pulse, accessed November 6, 2025, https://modularpulse.com/post/emerging-trends-reshaping-the-precast-concrete-industry-in-2025
- ASSESSMENT OF PRESTRESSED CONCRETE BRIDGES – CHALLENGES – DiVA portal, accessed November 6, 2025, https://www.diva-portal.org/smash/get/diva2:1476577/FULLTEXT01.pdf
- Life-Cycle Assessment: A Comparison between Two Optimal Post-Tensioned Concrete Box-Girder Road Bridges – MDPI, accessed November 6, 2025, https://www.mdpi.com/2071-1050/9/10/1864
- 14.1 PCI Standard Design Practice – Precast/Prestressed Concrete Institute, accessed November 6, 2025, https://www.pci.org/PCI_Docs/Design_Resources/Misc/PCI-SDP.pdf
- 423.10R-16: Guide to Estimating Prestress Losses – American Concrete Institute, accessed November 6, 2025, https://www.concrete.org/Portals/0/Files/PDF/Previews/423.10R-16_preview.pdf