Introduction
Falls from height remain a leading cause of workplace fatalities in Singapore, accounting for more than one third of all workplace deaths annually. For contractors, developers and engineers managing complex building projects, the Risk Management Facilitator (RMF) for work at height has become an essential role – one that structures risk assessments, integrates fall protection systems into design and method statements, and closes the persistent gaps between paper plans and site reality. This article distils practical lessons from real Singapore construction sites where RMF-led processes have directly shaped how work at height is planned, controlled and executed.
The scope here is deliberately narrow: how RMFs practically manage work-at-height risks on Singapore building, A&A and infrastructure projects – from concept design through to site execution. This is not a generic workplace safety theory guide. It is a case-insight piece grounded in project experience across façade works, roofing and solar PV retrofits, and M&E installations in atriums and plant rooms. The target readers are contractors, developers, site managers, WSH professionals and engineers who must comply with the WSH (Risk Management) Regulations, Work at Heights Regulations and related safety regulations.
An RMF for work at height adds value by facilitating structured hazard identification sessions with project teams, ensuring fall prevention plans are tailored to actual site conditions, coordinating risk control measures across design and construction disciplines, and verifying that what appears in documents is physically present and functional before workers perform work at height.
What you will get from this article:
-
Clarity on the RMF role for WAH and how it differs from WSHO and WAH Supervisor responsibilities
-
Common failure patterns – “paper-safe, site-unsafe” – observed on Singapore sites and how to fix them
-
Concrete lessons from façade, roof and M&E work at height projects
-
A step-by-step RMF workflow for WAH activities
-
A practical pre-work-at-height checklist to strengthen your own risk management systems
Understanding the Risk Management Facilitator Role in Work at Height
The Risk Management Facilitator is a role defined within Singapore’s WSH framework that bridges design, planning and site execution for risk management. In the context of work at height, the RMF facilitates hazard identification sessions with project teams, prepares critical safety submissions, and ensures risks are closed only after mitigation measures are verified. The RMF operates under the WSH Act – which governs workplace safety in Singapore – and the WSH (Design for Safety) Regulations, which were introduced in 2015. The RMF oversees the entire project lifecycle, from concept design through construction to handover, ensuring that WAH hazards are identified, assessed and controlled at every stage.
On complex projects – multi-storey developments, mixed-use buildings, dense urban infrastructure – the RMF role has become increasingly common because these sites present overlapping WAH activities (scaffolding, MEWPs, rope access, façade gondolas, rooftop plant installations) that demand coordinated risk management rather than siloed supervision. The role complements traditional safety officers and site supervisors by operating upstream: influencing how designs, method statements and schedules account for safe access and fall protection before workers step onto elevated work areas.
RMF vs WSHO vs Work-at-Height Supervisor on Singapore Sites
Understanding the distinction between these three roles is critical for any project team responsible for WAH activities.
The WSH Officer (WSHO) is a legally appointed role under the WSH Act, responsible for overseeing day-to-day workplace safety on site: conducting inspections, enforcing safety protocols, investigating incidents and near misses, and ensuring workers report hazards. Under the WSH (Work at Heights) Regulations 2013, supervision of WAH activities is mandatory, and the WSHO plays a key enforcement function.
The WAH Supervisor is a competent person who directly supervises specific work at height activities. Supervision is vital to ensure safety gear is used correctly and anchor points are secured. The WAH Supervisor verifies that workers follow Safe Work Procedures (SWPs), use personal protective equipment correctly, and connect to designated fall arrest systems before commencing elevated tasks. Workers must complete relevant WAH training for specified activities – Work at Height training lasts 16.5 hours including assessments, covering fall protection systems and hazard identification through both theoretical instruction and practical demonstrations.
The RMF sits upstream and across disciplines. Their sphere covers design risk assessment, coordination of method statements, early hazard elimination or engineering controls, and ensuring that designs or specified temporary works provide for anchorages, access and rescue capacity. The RMF does not enforce daily site behaviour but determines how that behaviour will be enabled and required through design documents, risk registers and fall prevention plans. The RMF updates the Hazard Register during construction phases and ensures compliance with safety regulations across all project stages.
Core Competencies of an Effective RMF for Work at Height
An effective RMF for WAH needs a specific competency profile that combines technical knowledge, regulatory understanding and facilitation skills:
Technical knowledge includes a strong grounding in structural and temporary works design, scaffolding systems (tube-and-fit, system scaffold), MEWP selection and operation, façade access methods (BMUs, gondolas, rope access), roof construction details (metal sheeting, fragile panels, skylight locations), and anchorage design. The RMF must understand load capacities, structural adequacy of roofs and slabs, and the practical limitations of various fall arrest systems.
Regulatory and standards knowledge encompasses the WSH Act, WSH (Work at Heights) Regulations 2013 (amended 2024), WSH Risk Management Regulations, Design for Safety Regulations, Codes of Practice (including the Code of Practice for Working Safely at Heights and Code on WSH Risk Management), and Singapore standards such as SS 280 for scaffolding. Familiarity with approved skills related courses for WAH and Design for Safety Professional (DfSP) accreditation through MOM is expected.
Facilitation and documentation skills are equally important: convening multi-disciplinary workshops, maintaining risk registers and DfS registers, communicating residual risks clearly, and producing visual aids that translate complex hazard information for a multilingual workforce. Effective workplace safety includes clear communication and documentation of risks and procedures – a primary duty the RMF fulfils.
How RMFs Integrate into the Project Lifecycle
The RMF’s involvement spans concept design to Temporary Occupation Permit (TOP) and Certificate of Statutory Completion (CSC). At concept design, the RMF works with architects and engineers to design for safe access – for example, specifying permanent anchor points, parapets of adequate height, cat ladders and rooftop walkways. During tender, the RMF clarifies WAH requirements so contractors can price realistic control measures rather than cutting corners. Before key WAH phases, the RMF facilitates risk assessment workshops with the multi-disciplinary team. After incidents or near misses, the RMF leads reviews and updates the risk register.
Early design decisions have outsized impact. Including permanent davit sockets during building construction eliminates the need for complex temporary anchorages during future façade maintenance. Designing parapets at ≥1.1 m removes the need for temporary guardrails along roof edges. These upstream interventions – driven by the RMF – reduce complicated temporary works and risky methods later. To be effective, however, RMFs need a structured toolkit for WAH risk management, which the next section covers.
The RMF Toolkit for Work at Height Risk Management
With the RMF role defined and positioned within the project lifecycle, the practical question becomes: what specific tools and processes does the RMF apply to WAH scenarios on Singapore jobsites? This section focuses on practical application of hazard identification and control – not compliance language, but methods that produce safer outcomes on active sites.
Structured Hazard Identification for Work at Height
The RMF leads HAZID and risk assessment workshops specifically for WAH tasks: façade installation, re-roofing, skylight replacement, M&E trunking above ceilings, and rooftop equipment mounting. Risk assessments must include hazard identification and risk evaluation steps – this is a legal requirement before work starts under the WSH Risk Management Regulations.
Key inputs to these workshops include architectural and structural drawings, temporary works designs, construction sequence plans, prior near-miss data from similar sites, supplier equipment manuals, and existing condition surveys (particularly for A&A and retrofit projects). Workers should be actively engaged in identifying hazards specific to their tasks – the RMF ensures that site supervisors, scaffold contractors, lift specialists, M&E subcontractors and maintenance teams participate, surfacing real-world issues often missed in office-only meetings.
For example, a roof survey during HAZID may reveal mixed materials – some sheets non-fragile metal, others fragile translucent panels – that are not differentiated on drawings. Without site walks, the risk assessment would fail to identify this critical WAH hazard.
Developing Risk Assessments, FPPs and SWPs that Actually Work On Site
The RMF coordinates alignment between Risk Assessments (RA), Fall Prevention Plans (FPP) and Safe Work Procedures (SWP) for each WAH activity. Employers must conduct risk assessments before new work starts, and employers must implement risk control measures based on assessment findings. High-risk industries must create site-specific fall prevention plans under regulations – site-specific guidelines are essential for a successful fall prevention plan.
Mismatches between documents and site reality are common. Three examples from Singapore sites illustrate:
-
Missing anchor points: An RA specified full-body harness with double lanyard for roof-edge work, but design drawings showed no fixed anchor points at that location. The method was physically impossible to implement safely. The RMF identified this during a pre-construction review and drove the installation of horizontal lifeline anchorages before the work phase commenced.
-
Assumed non-fragile roof: An RA for re-roofing assumed all roof sections were structurally sound for foot traffic. A site walk revealed fragile skylight panels interspersed with metal sheeting – unmarked and unguarded. The RMF required the contractor to install temporary decking over fragile sections, add warning signs, and revise the FPP accordingly.
-
Scaffold vs boom lift substitution: A subcontractor switched from system scaffold to boom lift mid-project without updating the RA or verifying ground conditions for outrigger loading. The RMF caught this during a monitoring round and halted the activity until a revised RA was completed with structural PE confirmation of slab capacity.
Fall prevention plans should be customized for dynamic site changes – adhering to the hierarchy of controls prioritizes engineering controls over PPE, and collective fall prevention methods should be utilized before relying on personal protective equipment.
Using Digital Tools and Visual Aids on Singapore Sites
The RMF leverages digital tools and visual communication to bridge the gap between documented controls and on-site understanding. BIM screenshots showing façade edges, roof parapet heights, access routes and anchor points can be extracted and annotated for toolbox briefings. Photo-markups comparing actual site conditions against drawings help supervisors verify that planned preventive measures are physically in place.
Practical digital tools used on Singapore sites include electronic permit-to-work (e-PTW) systems, digital RA/FPP tracking platforms, and QR-coded method statements posted at site entrances and work zones. A worker or supervisor can scan a QR code to access the current version of the method statement and FPP for that specific task area.
Key points on visual aids for WAH:
-
Annotated roof plans showing safe walkway routes, anchor point locations and fragile zones reduce misinterpretation for multi-language workforces
-
Photo comparisons of good vs poor edge protection are more effective than text-only SWPs during toolbox talks
-
Digital PTW systems ensure that permit-to-work requirements – including onsite inspections by competent persons before authorizing work – are traceable and auditable
Practical Case Insights from Singapore Work-at-Height Projects
This section distils lessons from actual project experience, anonymised but specific enough to be instructive. Three distinct WAH scenarios are examined: façade and gondola works, roof and solar PV installations, and M&E works in plant rooms and atriums. Practical lessons from Singapore emphasize risk management for work at height across these varied contexts.
Case 1 – Façade Access and Gondola Operations in a CBD Office Tower
Setting: A 35-storey office tower in the Downtown Core requiring façade panel replacement and sealant rectification. Access was via building maintenance units (BMUs) and suspended scaffolds. Multiple façade contractors operated simultaneously, with limited roof space and proximity to busy roads and pedestrian walkways.
Initial risk profile: The project involved concurrent WAH activities at different levels, falling-object exposure over public areas, and constrained roof access for BMU rigging. Emergency rescue protocols had to be established and practiced before work began – suspension trauma can occur within minutes if a worker is left hanging in a harness after a fall arrest event.
RMF actions: The RMF convened coordination workshops with all façade contractors, the building owner’s facilities team, and the structural PE. Key interventions included:
-
Verifying all anchor points and lifelines against structural capacity before BMU deployment
-
Segregating drop-zones at ground level with hoardings and public diversion routes
-
Pre-rigging rescue retrieval systems at each gondola station
-
Controlling the interface between façade works and concurrent rooftop plant maintenance through a shared PTW system
Results: Near misses from falling objects reduced significantly after hoarding and netting were reconfigured based on the RMF’s drop-zone analysis. Rescue readiness improved – pre-rigged retrieval systems meant any suspended worker could be retrieved within the critical window. Clearer exclusion zones at ground level addressed public safety concerns that the building owner had initially underestimated.
Case 2 – Re-Roofing and Solar PV Installation on Existing Industrial Buildings
Scenario: Retrofitting metal roofs in the Jurong/Pioneer industrial area with new sheeting and PV panels. Plant operations continued below the roof during installation.
Pre-RMF issues typically found: Fragile roof sections unmarked and unguarded, unclear walkway routes across the roof, inconsistent harness use among workers, ad-hoc ladder positioning against roof edges, and no defined stop-work triggers for weather events. These conditions are precisely the kind of WAH hazards that result in fatalities – the construction industry in Singapore has seen recurring rooftop fall incidents where lack of guardrails, barriers and warning signs contributed directly to deaths.
RMF interventions: The RMF worked with the structural engineer and roofing contractor to:
-
Conduct a detailed roof-condition survey identifying all fragile panels, marking them with high-visibility paint and physical barriers
-
Specify temporary walkways (roof crawl boards) along designated safe routes
-
Update the RA/FPP to account for changing conditions including weather alerts and lightning risk
-
Establish clear stop-work criteria: all WAH activities to cease when lightning warning is active or wind speed exceeds 40 km/h
Near-miss prevented: During Week 3 of installation, a supervisor observed a worker preparing to traverse an unmarked section of translucent sheeting that had not yet been covered with temporary decking. The RMF-led stop-work protocol was invoked, the area was immediately cordoned, and the RA was updated to include that zone. Without the structured process, this could have resulted in a fall through the fragile panel to the factory floor below.
Case 3 – M&E and Interior Works at Height in Atriums and Plant Rooms
Context: M&E installation above 6 m in a shopping mall atrium and on rooftop plant decks. Equipment included scissor lifts, boom lifts and tower scaffolds. Work was scheduled around mall operating hours.
Typical hazards: Working over public areas during transition periods, unstable or unconfirmed ground conditions for MEWP outriggers, overhead live electrical services, cluttered and confined plant room spaces limiting rescue access, and fatigue from night-shift scheduling.
RMF-led solutions: The RMF introduced zoning to separate public areas from active WAH zones using protective decks and temporary hoardings. After-hours work sequencing was agreed with the mall operator. MEWP selection checks were formalized – verifying that the specific task requirements matched equipment reach, capacity and outrigger footprint. Critically, slab capacity for boom lift outrigger loads was verified with the structural PE before any MEWP was positioned, preventing potential equipment tipping or slab failure.
Case takeaways:
-
Never assume slab can take MEWP load – involve structural PE early
-
Coordinate isolation of M&E services before any cutting, drilling or anchoring at height
-
Schedule high-risk WAH during low-occupancy periods in live operational environments
-
Ensure rescue path from elevated plant rooms is physically walkable and not obstructed by equipment or services
Implementing an RMF-Led Process for Work at Height
The case insights above reveal a consistent pattern: structured RMF involvement, applied early and maintained throughout execution, prevents the disconnects between planning and site reality that cause WAH accidents. This section presents a practical step-by-step process suitable for contractors, developers and building owners who want to formalise RMF involvement in WAH management.
Step-by-Step RMF Workflow for Work at Height Activities
-
Confirm legal and client requirements for WAH: Identify applicable safety regulations – MOM requirements, WSH Council guidelines, building owner rules – and confirm whether the project triggers DfS Regulations (e.g. contract sums ≥ S$10 million). Work at height risk assessments are legally required before work starts.
-
Map all planned WAH tasks over the project timeline: Using drawings and method statements, identify every activity where people involved will perform work at height – including often-overlooked tasks like antenna installation, waterproofing, gutter maintenance and temporary lighting rigging.
-
Conduct RMF-facilitated RA/FPP workshop with multidisciplinary team: Before high-risk WAH phases, convene architects, structural engineers, temporary works designers, scaffold contractors, M&E specialists and safety officers. The RMF facilitates hazard identification sessions with project teams to surface risks that no single discipline would catch alone.
-
Align design details and temporary works with RA outcomes: Ensure anchor points, parapet heights, access routes and temporary edge protection reflect the risk control measures identified in the RA. Verifying physical controls before work starts can prevent accidents during work at height.
-
Translate controls into SWPs, PTWs and toolbox talk scripts: Ensure multi-language briefings and visual aids are prepared. Regular training sessions enhance workers’ safety skills at height – toolbox talks should include practical demonstrations of harness connection, anchor point checks and rescue procedures.
-
Monitor implementation on site: Conduct sample checks, observation rounds and feedback loops with supervisors and workers. The RMF ensures risks are closed only after mitigation measures are verified – not just documented.
-
Manage changes formally (MOC): When method, equipment, or site conditions shift, trigger a formal re-assessment process. New risks introduced by design changes, material substitutions or scope additions must be captured in updated RAs, FPPs and SWPs.
-
Capture lessons learned: At project close-out, compile WAH-specific findings – what controls worked, what was difficult to implement, which near misses occurred – and update organisational WAH standards for future projects. Workers must report incidents and near misses immediately throughout the project, building the data needed for meaningful lessons learned.
Choosing and Coordinating Access Systems: Scaffolds, MEWPs and Rope Access
Access system selection is one of the most consequential decisions the RMF influences. The main options on Singapore sites include tube-and-fit scaffold, system scaffold, MEWPs (scissor lifts, boom lifts), rope access and BMUs. Each has distinct suitability depending on the specific task requirements:
Evaluation criteria the RMF uses:
-
Height and reach: System scaffold suits full-height façade access; boom lifts offer flexibility for spot access at varying heights
-
Load capacity: Heavy cladding panel installation may require scaffold with goods hoist; rope access is limited to light tools and materials
-
Duration of works: Short-duration tasks favour MEWPs; extended façade programmes justify scaffold investment
-
Building footprint and site restrictions: Dense urban sites may lack space for scaffold base; MEWPs need confirmed ground or slab capacity
-
Wind exposure: Suspended platforms and rope access are highly sensitive to Singapore’s sudden wind gusts and thunderstorms
-
Rescue options: Rope access requires standby rescue team; MEWP platforms can self-rescue if operational; scaffold may trap injured workers at height
-
Cost and programme impact: Scaffold erection/dismantling adds time; MEWP rental is daily cost; rope access is labour-intensive but mobilises quickly
Access selection should be a facilitated, cross-disciplinary decision – not a last-minute subcontractor choice driven solely by cost. The RMF ensures all people involved in the decision weigh safety, practicality and compliance equally.
Integrating Design-for-Safety (DfS) with Work at Height Risk Management
The RMF and Design for Safety Professional (DfSP) can collaborate from concept stage to eliminate hazards that would otherwise require complex WAH controls during construction and building maintenance. Safety submissions are required at critical project phases under the DfS Regulations, and these submissions should explicitly address foreseeable WAH risks.
Examples of early DfS inputs that reduce future WAH exposure:
-
Permanent davit arms and anchor rails designed into roof slabs during construction eliminate the need for temporary anchorages during every future façade maintenance cycle
-
Parapets designed at ≥1.1 m along all roof edges remove the requirement for temporary guardrails – a measure that is frequently poorly installed or removed prematurely on site
-
Integrated roof walkways and cat ladders provide safe access routes to plant equipment, removing ad-hoc ladder use and uncontrolled traversal of fragile roof areas
These design interventions represent the highest level of the hierarchy of controls – elimination and engineering controls – and deliver safety benefits across the entire building lifecycle. Even with good processes, however, common challenges persist on active Singapore sites.
Common Challenges on Singapore Work-at-Height Sites and How RMFs Address Them
Fast-track schedules, multiple layers of subcontracting, a multilingual workforce, and tropical weather all complicate the RMF’s task of maintaining effective risk management for WAH activities. Each challenge below describes a frequent problem and the practical, RMF-led solution.
Challenge 1 – “Paper-Safe, Site-Unsafe” Risk Assessments
Risk assessments and fall prevention plans are sometimes generic documents copied from templates, not reflecting actual site conditions. An RA may call for full guardrails while the actual roof has parapets too low to qualify. A subcontractor may use a different method from what the RA describes, but no updated assessment is produced.
RMF solutions: Joint site walks before RA sign-off, with photo-embedded RAs showing actual conditions. Spot-checks comparing RA assumptions against physical reality. Involving workers and supervisors in RA review sessions so that assumptions about anchor points, roof condition, ground stability for MEWPs and edge protection are verified by the people who will perform work at those locations.
Challenge 2 – Worker Behaviour, Shortcuts and Multi-Language Communication Gaps
Differing risk perceptions among workers from various industries and backgrounds, language barriers, and production pressure create conditions where shortcuts occur – harnesses unclipped, guardrails removed for “convenience,” ladder positioning improvised.
RMF responses: Tailored toolbox talks using pictures and demonstration-based briefings rather than text-heavy documents. Engaging key influencers – experienced foremen and charge-hands – as safety champions. Simple pre-climb checklists (harness condition, anchor connection, edge protection in place) in multiple languages. Training and certification are essential for workers involved in height work, and the RMF verifies that all WAH personnel hold valid height training certifications, including the required safety pass.
Challenge 3 – Management of Change (MOC) for Work at Height
Design changes, material substitutions and scope additions frequently occur on Singapore projects without triggering a re-assessment of WAH risks. Switching from system scaffold to boom lift without updating the RA. Changing roof material mid-project from non-fragile metal to a profile that includes fragile translucent panels. Adding new PV rows to an already-assessed roof area.
RMF MOC framework for WAH:
-
Trigger list: Any change in access method, work equipment, roof or façade material, scope of elevated work, or structural loading must trigger review
-
Quick re-assessment: The RMF convenes a focused session with the relevant contractor, structural PE and WSHO to update the RA, FPP and SWP
-
Approval and communication: Revised documents are signed off, updated in the digital PTW system, and communicated through a toolbox briefing before work resumes
Challenge 4 – Weather, Lightning Risk and Night Works
Singapore’s tropical climate introduces dynamic risk to elevated work. Sudden thunderstorms, lightning, high wind gusts and slippery surfaces from rain are daily realities, not occasional events. WAH activities on exposed roofs, suspended platforms and scaffolds are directly affected.
The RMF sets objective stop-work criteria – for example, all WAH activities to cease when the National Environment Agency issues a lightning alert within the site radius, or when sustained wind exceeds defined thresholds for gondolas and MEWPs. These triggers are integrated into PTWs and shift planning. Night works add complexity: reduced visibility affects hazard identification, worker fatigue increases error rates, and rescue operations become harder. The RMF ensures adequate task lighting, fatigue management scheduling and standby rescue readiness for night WAH activities.
Challenge 5 – Coordination in Brownfield and Live Operational Environments
WAH in occupied shopping malls, hospitals, schools and industrial plants requires more complex coordination. Public safety, service continuity, noise restrictions and shared access routes all add layers of concern.
RMF solutions: Stakeholder mapping to identify all affected parties. Scheduling noisy or high-risk WAH during off-peak hours. Installing protective decks and hoardings to separate work zones from occupied areas. Obtaining advance approval for public diversion routes. Coordinating with building management for isolation of live M&E services before any anchoring or cutting at height.
Structured RMF involvement is now both a compliance requirement and a competitive advantage – project teams that manage work at height through a formalised, facilitated process experience fewer stoppages, lower incident rates and more predictable programmes.
Conclusion and Next Steps
The RMF’s unique value lies in making work at height “design-safe, method-safe and site-safe” on Singapore projects. Across façade works in the CBD, industrial roof retrofits in Jurong and M&E installations in live commercial buildings, the consistent lesson is that upstream facilitation – structured hazard identification, realistic risk assessments, verified physical controls and formal change management – prevents the failures that lead to falls, injuries and fatalities. Falls from height continue to cause over one third of Singapore’s workplace fatalities; fines for WAH lapses have reached S$170,000 in cases like EC Builders, and fatal incidents on major projects like the Jurong Region Line have prompted parliamentary scrutiny and tighter enforcement.
The RMF does not replace the WSHO or WAH Supervisor – it strengthens both by ensuring that the systems, documents and physical controls they rely on are robust, site-specific and current. For any organisation managing WAH activities properly, the question is no longer whether to engage an RMF but how early in the project lifecycle to do so.
Next steps for project teams:
-
Identify upcoming WAH activities on current projects and confirm whether a named RMF is in place with clear responsibilities
-
Review existing RA/FPP/SWP bundles for at least one critical WAH task and compare them to site reality through a joint site walk
-
Plan an RMF-facilitated workshop before the next major WAH phase, involving all relevant contractors and supervisors
-
Integrate WAH considerations into ongoing and future DfS reviews, particularly for permanent anchorage and access provisions
AEC Technical Advisory provides RMF services, DfS integration and PE design for both permanent and temporary WAH controls across building, infrastructure and A&A projects in Singapore. If your project involves elevated work and you want to strengthen the link between design intent and site safety, reach out for a technical discussion.
Additional Resources and Practical Checklists
These resources help project teams put the ideas discussed above into practice quickly.
Key Singapore references:
-
WSH (Risk Management) Regulations and Code of Practice on WSH Risk Management (2021, updated effective 1 January 2025)
-
WSH (Work at Heights) Regulations 2013 (amended 2024) and WSH Council Technical Advisory for Working at Height
-
WSH (Design for Safety) Regulations 2015
-
WSH Council guidelines on Fall Prevention Plans and Permit-to-Work systems
-
Code of Practice for Working Safely at Heights (ACOP, updated effective 1 January 2025)
RMF Pre-Work-at-Height Checklist:
-
☐ Drawings and method statements reviewed; access system selected and justified based on task requirements, site constraints and rescue capability
-
☐ RA/FPP/SWP aligned, tailored to the specific task and building typology, and verified on site through joint walk
-
☐ Anchor points, edge protection and fall protection equipment confirmed physically present, correctly installed and load-certified
-
☐ Rescue plan established and practiced; retrieval equipment pre-rigged at work location
-
☐ Toolbox briefing conducted with visual aids, practical demonstrations and attendance recorded; multi-language materials provided
-
☐ Weather and operational constraints considered; stop-work triggers defined in PTW (lightning, wind, rain, visibility)
-
☐ All WAH personnel verified as holding current height training certification and valid safety pass
-
☐ Change management process confirmed: any shift in method, equipment or conditions triggers re-assessment before work resumes
Suggested visual documentation for your projects:
-
Annotated roof plan image showing safe walkway routes, anchor point locations and fragile zones marked with colour coding
-
Side-by-side photo comparison of compliant vs non-compliant edge protection installations
-
Photograph of an RMF-led site briefing with annotated drawings displayed for the work crew