A sewer diversion submission in Singapore is made to PUB, the national water agency, by a Qualified Person (QP) under the Sewerage and Drainage Act. PUB may consider diverting an existing public sewer to allow better use of a development site, at the developer’s cost. The submission must show a PE-endorsed design, a verified sewer position and a construction method that will not damage the public system. Approval has to be in hand before any work starts. This guide sets out the route, the documents, the sequence of clearances and the points where submissions most often stall.
TL;DR
- PUB may consider diverting a public sewer for better land use, but the developer bears the cost, and PUB approval is required to remove, abandon or seal any sewer within a site.
- The structural design of sewers and manholes must be carried out by a Professional Engineer (PE). Submissions are made by a QP, or by a PE where BCA approval is not needed.
- Documents are built around the Sewer Information Plan, a survey, a CCTV report, a method statement and a PE analysis of impact on the sewerage system.
- Clearances run in stages: Development Control (DC) and Detailed Plan (DP) clearance before works, then TOP or CSC clearance on completion.
- The Code of Practice on Sewerage and Sanitary Works (COPSSW) 3rd Edition added new requirements effective 1 September 2025.
Table of Contents
- When a Sewer Diversion Needs PUB Approval
- Who Prepares and Endorses the Submission
- Documents and Technical Standards
- The Submission Sequence Step by Step
- Supervision and Safety Duties During the Works
- What Changed in 2025
- Where Diversion Submissions Go Wrong
- How We Support Sewer Diversion Submissions
- Our Perspective
- FAQ
- Sources
When a Sewer Diversion Needs PUB Approval
A public sewer is owned and protected by PUB. Moving, sealing or building over one is therefore never a purely private design decision. Three provisions in the Code of Practice and PUB’s guidance define the territory.
Diversion for better land use. Clause 1.2.6 of the COPSSW 3rd Edition (March 2025) states that PUB may consider the proposed diversion of existing public sewers for better land utilisation of a development, when carried out at the developer’s cost. The wording is permissive. PUB considers the proposal; it does not owe the developer a diversion.
Unavoidable crossings. Under clause 1.2.7 of the same code, where infrastructure such as viaducts, road or rail tunnels, link-bridges, underpasses or permanent earth retaining structures must cross public sewers, diversion is to be explored first. If diversion cannot be carried out, PUB must be consulted on the need for and size of additional sewers. These are to be provided at least 5 m horizontally from the outer edge of the affected sewer and parallel to it, unless PUB accepts otherwise.
Removing, abandoning or sealing sewers. PUB’s Used Water FAQ states that PUB approval is required to remove, abandon or seal up any sewer within a development site. A QP must purchase the Sewer Information Plan to verify whether a sewer is truly unused, and a thorough inspection to locate all existing sewers must be carried out before work begins. Many diversions begin here: a sewer assumed to be disused turns out to be live.
PUB also describes the building plan requirement as protective. It exists to minimise flood risk to developments, safeguard public health and water resources, and protect the integrity of the public sewerage and drainage systems during construction, according to the Building Plan Submission Process Flow page.
Simplified submission is not for diversions
PUB allows a simplified submission for minor works, for example additions and alterations to a single landed house, or to a factory or non-food shop, where the works comply with COPSSW. The conditions rule out a diversion: no building above a public sewer or within its setback, no change to the drain-line connection, no new on-site facilities and no used water pumping system. Any project that touches a public sewer line should be treated as a full submission.
A worked example
CORENET X, the government’s integrated regulatory submission system, uses a useful case. An LTA cut-and-cover road tunnel that requires the diversion of a sewer deeper than 1.5 m involves PUB at both the Design Gateway and the Construction Gateway. For PUB, access to sewers requires Form B and a submission through the B&P Portal for Permission to Carry Out Works in the Public Sewerage System (POWS). The pattern applies to private developments as well: design-stage agreement first, then construction-stage control.
Who Prepares and Endorses the Submission
A Qualified Person is a registered architect or a professional engineer holding a practising certificate. The COPSSW sets out who does what.
| Task | Who is responsible |
|---|---|
| Structural design of sewers and manholes | A Professional Engineer (PE) |
| POWS plan where BCA approval is required | A QP who is a PE (Civil or Geotechnical), or a QP (Architect) with PE (Civil or Geotechnical) endorsement |
| POWS plan where BCA approval is not required | A PE (Civil or Geotechnical) or, if PUB permits, the contractor |
| Supervision of specified activities in a Public Sewer Corridor | A PE (Civil or Geotechnical), where applicable |
The Feb 2022 WRN Advisory Notes add that the POWS application is made by the contractor, and prepared and submitted by the appointed QP if the plan needs the Commissioner of Building Control’s approval. Otherwise it is prepared by the appointed registered PE, or by the contractor if PUB permits.
Two practical consequences follow. First, the endorsing engineer needs competence in both civil and geotechnical behaviour, because a diversion changes ground loading and excavation support around live infrastructure. Second, the PE who endorses the design is normally the same professional who must stand behind the construction method, so the appointment should be made before the drawings are finalised, not after.
For a wider view of the approval chain, see our guide to the role of PUB in construction and the walkthrough of the PUB sewer connection approval process.
Documents and Technical Standards
The contents of the package depend on the size of the sewer and the nature of the works. PUB’s March 2023 WRN Advisory Note lists what is required for specified activities in a Public Sewer Corridor for sewers under 900 mm:
- A Sewer Information Plan (SIP).
- A layout plan showing the minimum setback distances.
- A survey plan endorsed by a Registered Surveyor.
- A pre-construction CCTV report and video.
- A method statement, detailed drawings and machinery details.
- A PE’s analysis that the construction method will not impact or damage the sewerage system.
- Any other documents PUB may require.
For sewers of 900 mm or larger, or Deep Tunnel Sewerage System (DTSS) tunnels, the same note adds a Construction Impact Assessment Report (CIAR), an instrumentation and monitoring plan, and web-based IP camera details for works within the sewer setback.
The Sewer Information Plan is the starting point because every other drawing depends on it. Our guide on sewerage interpretation plan checks explains what the plan shows and where its limits lie. The monitoring side is covered in settlement monitoring and PUB sewer rules.
Design standards for the diverted line
The replacement alignment is a new sewer and must meet the COPSSW design basis. The figures below come from the COPSSW 3rd Edition:
- Minimum new sewer size: 200 mm diameter.
- Minimum depth: 1.5 m below ground level, unless this is not permitted.
- Sizing: design peak flow at no more than half bore for pipes up to 1.0 m, and two-thirds bore for larger pipes.
- Velocity: about 1.5 m/s at design peak flow, within a 0.9 m/s minimum and a 2.4 m/s maximum.
- Residential flow: 230 litres per capita per day for public housing or 250 for private housing, with a peak factor of 3 and 3.5 persons per dwelling unit.
- Sewers and manholes to follow PUB’s Standard Drawings (Annex B), with manhole spacing not exceeding 120 m, manhole walls and platform undersides lined with HDPE, and all manholes and connections passing the water-tightness test in Annex D.
A short example shows how the numbers interact. A private residential development of 200 units at 3.5 persons per unit houses 700 people. At 250 litres per capita per day the average flow is 175,000 litres a day, and the peak factor of 3 applies to that figure when the sewer is sized. A diversion that lengthens the route reduces the fall available, so the velocity limits, not just the diameter, usually decide whether the new alignment works.
The Submission Sequence Step by Step
PUB’s Submission Process page and the Building Plan Submission Process Flow establish that the QP must obtain DC clearance and DP clearance before sewerage, sanitary and drainage works proceed. The sequence for a diversion looks like this.
- Establish the facts on site. Obtain the Sewer Information Plan, commission the survey and run the CCTV inspection. Errors at this step carry through every later drawing.
- Pre-consult PUB. PUB’s Quick Submission Guides list a Pre-Consultation Application Form on Sewerage Matters. Early agreement on the diversion principle avoids redesign. Where a requirement of the Code cannot be met, an Application for Deviation on Sewerage Matters is available. The guides themselves do not amend the Code or release a QP from liability for non-compliance.
- Apply for DC clearance. This confirms the development control parameters, including the proposed treatment of the existing sewer.
- Apply for DP clearance. The detailed sewer layout, longitudinal sections, manhole details and structural design are submitted using the PUB-DPCLR submission, with DC clearance using PUB-DCCLR.
- Obtain permission for works in the public sewerage system. Application Prior to Work in Public Sewerage System (Form B/QP) is needed before workers enter public sewers, manholes or confined spaces. Where specified activities fall in a Public Sewer Corridor, the POWS application applies.
- Construct, supervise and record. Works start only after approval.
- Request completion clearances. PUB-BPU-COMPOFWORK can be used for TOP or CSC clearance for sewerage and sanitary works. PUB-DRATOP serves drainage TOP clearance, and PUB-DD-CSIDRA with a Handing Over form serves drainage CSC clearance. Since September 2022, PUB issues the clearance to the QP directly, upon issuance of the last required TOP Clearance or Compliance Certificate for Drainage or Sewerage.
Timing
PUB’s WRN Advisory Notes (Feb 2022 edition) state that POWS submissions are reviewed within 14 working days, with approval granted with or without conditions if the documents are in order. That period is for a complete package; a submission with missing items restarts the conversation. PUB publishes no fee in the pages reviewed for this article, so fees should be confirmed on the PUB website at the time of submission.
Approval can lapse. Under the same notes it ceases if the activity does not start within the commencement window, if conditions are breached, if the QP or PE ceases supervision, or if PUB revokes it. Contractors planning a diversion should align the approval with the real construction programme, and the QP or PE should confirm continuity of supervision before the start date.
For the drainage side of the same clearance process, the guide on how to obtain PUB drainage clearance covers the forms in more detail.
Supervision and Safety Duties During the Works
The diversion itself is a high-risk activity: excavation beside live sewers, confined spaces and temporary flow arrangements. PUB places a due-diligence duty on the supervisor of a specified activity in a public sewer corridor. Under the WRN Advisory Notes, the supervisor must supervise and inspect the works, take all reasonable steps to ensure compliance with the approved plan and PUB’s conditions, notify PUB of any contravention, keep records at the premises, and submit a declaration and certificate of completion of works to PUB.
These duties overlap with the Design for Safety obligations that project teams carry under Singapore’s workplace safety framework: hazards such as trench collapse, sewer gas and temporary diversion failures are best identified at design stage, when the alignment, depth and bypass arrangements can still change. Teams should review the current requirements with the Ministry of Manpower and their appointed safety professionals.
Temporary works need the same attention. Shoring, dewatering, temporary pipe supports and bypass pumping are all designed items, and a PE-endorsed temporary works design belongs in the method statement from the start.
What Changed in 2025
PUB’s circular for the COPSSW 3rd Edition records the following relevant items, with new requirements taking effect from 1 September 2025 according to PUB’s Codes of Practice page:
- Clause 1.2.7, a new clause based on existing practice, requires diversion to be explored before additional sewers are considered where infrastructure crosses a public sewer.
- A CCTV inspection is required before DC clearance for certain reused drain-line connections, reflecting a PUB circular dated 1 December 2023.
- Drains up to 2 m wide may over-cross sewers with a minimum vertical clearance of 1 m.
- Updated standards apply, including RC pipes to SS 183 and manhole and inspection chamber frames and covers to SS EN 124.
Submissions prepared against the 2nd Edition drawings or specifications should be checked against the current code before they go to PUB. The Codes of Practice page also lists the standard requirements for abandoning a disused sewerage system, which matter when the old line is sealed after the new alignment goes live.
Where Diversion Submissions Go Wrong
- Unverified sewer status. A line treated as disused without a Sewer Information Plan check.
- Setback conflicts. New foundations or retaining structures drawn inside the sewer setback.
- Thin method statements. Missing machinery details or no analysis of the effect on the sewer.
- Mismatched endorsements. The wrong discipline of PE signing off, or a QP without the right PE endorsement.
- Programme mismatch. Approval lapses because the start date slips beyond the commencement window.
Most of these are avoidable with an early design check. The related guide on PUB submission and POWS design checks lists the items to settle before filing.
How We Support Sewer Diversion Submissions
A diversion draws on several disciplines at once: structural and geotechnical design, PE endorsement, temporary works and authority submissions. AECTechnicalSG offers PE endorsements for structural and geotechnical engineering, statutory authority submissions to agencies including PUB, and temporary works design. Our stated approach is timely, responsive and affordable service with direct, clear communication. Fees are project-based; no prices are published, so scope is discussed on enquiry. The full list of services is on our services page.
Developers, contractors and owners with a sewer on their site can bring us the Sewer Information Plan and the proposed layout, and the engineering and the submission can be handled together under one team.
Our Perspective
A sewer diversion is decided in the first few weeks, long before the first excavator arrives. The Sewer Information Plan, the survey and the CCTV record fix what is actually in the ground, and PUB’s review depends on how well the design answers that evidence.
We prepare PE endorsements and statutory submissions so that the structural, geotechnical and authority work reads as a single package. That is why we encourage appointing the engineer before the layout is frozen: a diversion that works on paper but crosses a setback or lacks a supervision plan is returned, and the programme absorbs the delay.
Our aim is a submission that PUB can review in one pass, with responsive communication from the first enquiry to the completion clearance.
Aman
FAQ
Does every sewer diversion need PUB approval?
Yes, where a public sewer is affected. PUB may consider diversion for better land use at the developer’s cost, and approval is required to remove, abandon or seal any sewer within a development site. The route runs through DC and DP clearance.
Who can submit a sewer diversion proposal to PUB?
A Qualified Person submits building plans to PUB. For POWS plans, the submitter is a QP who is a PE (Civil or Geotechnical), or a QP (Architect) with PE endorsement, where BCA approval is required. Otherwise it is a PE or, if PUB permits, the contractor.
How long does PUB take to review a POWS submission?
PUB’s WRN Advisory Notes (Feb 2022 edition) state a review within 14 working days when documents are in order. Reviews for DC and DP clearance follow their own timelines, so confirm the current schedule with PUB.
What if the diversion cannot meet the Code?
PUB’s Quick Submission Guides list an Application for Deviation on Sewerage Matters. The QP stays responsible for compliance, so the deviation case needs full engineering justification.
Sources
- Code of Practice on Sewerage and Sanitary Works, 3rd Edition (March 2025)
- PUB Used Water Frequently Asked Questions
- PUB Building Plan Submission Process Flow
- PUB Submission Process
- PUB Quick Submission Guides
- PUB WRN Advisory Notes (March 2023)
- PUB WRN Advisory Notes (February 2022)
- CORENET X infrastructure works
- PUB circular for COPSSW 3rd Edition
- PUB Codes of Practice and Standard Drawings