Regularisation is the after-the-fact approval of building works that were carried out without the required approval. In Singapore it runs through a qualified person (QP), who submits the as-built works to the Commissioner of Building Control and obtains the other approvals the works need, such as URA’s. The route is a full technical submission, not a form, and the works must be shown to be safe and compliant. Where they cannot be, they are altered or removed. Owners, developers and project teams who start with a clear picture of the as-built condition reach a decision sooner.
TL;DR
- Unauthorised works are building works carried out in contravention of the Building Control Act or the building regulations, including works that depart from approved plans.
- BCA directs the owner to engage a QP, who submits the plans to the Commissioner of Building Control and obtains other approvals, such as URA’s.
- The offence under section 20(1) carries a fine of up to S$200,000, imprisonment of up to 2 years, or both, plus daily fines for continuing contraventions.
- Works that cannot be approved as built may have to be strengthened, altered or removed, so the structural position should be established before anything is submitted.
- A PE-led team that handles the drawings, calculations and the authority submissions together shortens the path from discovery to approval.
Table of Contents
- What counts as unauthorised works
- Who is responsible: the QP and the PE
- The regularisation process, step by step
- When the works cannot be approved as built
- Penalties and enforcement if the works are left as they are
- Rules that have recently changed
- Starting a regularisation with AEC Technical
- FAQ
- Sources
What counts as unauthorised works
The Building Control Act defines “unauthorised” as any building erected, or building works commenced or carried out, in contravention of the Act or the building regulations. In practice this covers three situations:
- Works built with no approval at all, such as an extension, a new structure or a demolition.
- Works built differently from the approved plans, such as a larger footprint, an added storey level or a changed structural layout.
- Works started before the plans were approved or before a permit was in force.
BCA advises owners to compare the as-built condition with the approved plans to identify unauthorised works. That comparison is the first task in any regularisation, and it is often where the problem is first seen: a unit or house acquired from a previous owner, a due diligence review, or the start of a new project.
Works that do not need approval
Not every alteration needs a submission. BCA’s guide on building works not requiring approval states that insignificant works do not require plan submission to BCA, but owners must still observe safety and good practice and obtain any other required approvals. The Straits Times reported in October 2024 that minor works, such as a single-storey open-sided shelter or a gazebo under 10 sqm, do not need BCA approval, while most erection, extension, demolition, alteration and repair works do. BCA was at that time reviewing the scope of alteration works that can be done without approval, so the current list on BCA’s page should be checked before any decision is made.
Exemptions also exist for owner-occupied landed houses. BCA’s exemptions page states that headroom requirements do not apply to attics of 10 sqm or less or to toilets and bathrooms, and that certain staircase, barrier, lighting and ventilation requirements are exempted for such houses. These exemptions relax specific technical requirements. They do not remove the need to submit the works for approval.
Two approvals, two authorities
Building approval and planning approval are separate. BCA regulates the safety and construction of the works. URA requires planning permission for development and building works, including a change of use, subject to its Exemption List. Works that add gross floor area (GFA) or affect planning parameters need URA approval as well as BCA approval. Many regularisation cases are decided on the URA side, because a structure may be safe and still exceed the permitted envelope, setback or GFA.
Who is responsible: the QP and the PE
A qualified person is a person registered as an architect under the Architects Act 1991, or as a professional engineer (PE) under the Professional Engineers Act 1991, who holds a valid practising certificate. The Act places clear duties on the QP:
- Section 7 requires all building works to be carried out under the supervision of an appropriate QP.
- Section 9 requires a QP who prepares plans to ensure the works are designed in accordance with the Act and the prescribed requirements, to notify the Commissioner of any contravention the QP knows of or could reasonably know of, and to supply copies of approved plans to the site supervisor and other QPs.
- BCA’s ST plan guidelines state that the appointed structural QP is responsible for obtaining structural plan approval and securing the building permit before construction begins.
For regularisation this division is practical. The architect QP deals with the layout, the planning parameters and the Approved Document requirements. The structural PE is the one who must be satisfied that the as-built structure is adequate, and who endorses the structural drawings and calculations. Where the works touch fire safety, M&E systems or drainage, the other agencies and engineering disciplines enter the same submission.
A QP cannot endorse what the QP cannot verify. This is why the quality of the as-built information decides how fast a case moves. A measured record of the existing works, such as the as-built survey requirements that surveyors follow, gives the QP the dimensions and levels the drawings and calculations are based on.
The regularisation process, step by step
1. Establish what was built and what was approved
Collect the approved plans, any permits and the completion records, then compare them with the site. List each deviation: area, height, structural member, opening, use. A legal search alone reveals only works that have been brought to BCA’s attention, so a clean search does not confirm that the property matches its approvals. For a buyer, BCA recommends having a competent person inspect the property.
What goes wrong here: owners list the visible additions and miss the hidden ones, such as altered slabs, removed walls or relocated stairs. An incomplete list leads to a submission that has to be reopened.
2. Appoint the QP
The works are submitted through a QP. Appoint the architect QP, the structural PE, or both, depending on the scope. At this stage our team can review the deviations list and advise which disciplines the case needs. We provide PE endorsements for structural and geotechnical works, architectural design and submissions, and statutory authority submissions, so the discipline split does not need separate appointments with separate handovers. See our PE endorsement and authority submissions page for the scope.
3. Survey and investigate the as-built structure
The QP needs measured drawings of the works and, for structural elements, enough information to assess capacity: member sizes, reinforcement where it matters, foundations and connections. Where records are missing, the structure may have to be opened up or tested. Hidden elements are the most common reason a case runs longer than planned. Our article on whether renovation works can affect structural safety explains the typical structural risks of alterations.
4. Check the works against current requirements
Regularisation is judged against the rules in force at the time of submission, not the rules when the works were built. That is the main reason cases are rejected: the works breach the current URA envelope, setback or GFA limits, or the structure does not meet current loading requirements. Settle these questions before preparing full drawings:
- Does URA allow the GFA, height and setbacks as built?
- Does the structure satisfy current design codes with the actual member sizes?
- Are fire safety, escape routes and shelter requirements met? BCA states that civil defence shelter aspects have been incorporated in BP and ST submissions since 1 April 2023.
5. Prepare the drawings and calculations
The submission set normally contains as-built architectural plans, structural plans and calculations, and supporting documents for other disciplines. Each deviation is shown against the approved plans. The structural calculations analyze the as-built condition, not the intended one. Our guides on BCA plan submission requirements and the building permit submission process set out the documents in detail.
6. Submit to BCA, URA and the other agencies
The QP submits to BCA and obtains URA’s written permission where planning parameters are affected, together with any other approvals, such as SCDF for fire safety, PUB for drainage or NEA. Submissions go through CORENET. According to BCA, from 1 October 2025 all new projects with a GFA of 30,000 sqm or more must use CORENET X, and others use CORENET 2.0. BCA’s September 2025 release describes CORENET X as a one-stop, jointly reviewed process for regulatory approval. Our team manages BCA, URA and SCDF submissions, which means agency comments are answered by the same people who prepared the drawings.
7. Close out the approved works
Once approval is granted, any physical works the approval requires are carried out under QP supervision, and the project is closed as the approval conditions direct. Section 7 of the Act applies to this work: it must be supervised by an appropriate QP. Our guide to the site supervision plan for BCA shows how supervision is documented.
When the works cannot be approved as built
Regularisation does not always mean approval of everything. There are three possible outcomes:
- Approval as built. The works comply, or comply once the QP’s calculations confirm adequacy.
- Approval with rectification. The structure is strengthened or modified, then approved. Where the QP cannot be satisfied that a structure is adequate, physical work or opening up for inspection may be needed in addition to the paperwork.
- Partial regularisation. Part of the works is approved and the non-compliant part is removed and the premises reinstated.
The decision between these depends on two questions: whether URA permits the work in planning terms, and whether the structure can be shown to be safe. Answer both early. An owner who spends on full drawings before the URA position is clear risks paying for a submission that cannot succeed.
Penalties and enforcement if the works are left as they are
Section 20(1) of the Building Control Act makes it an offence to commence or carry out, or to permit or authorise, building works without approved plans or without a permit in force. As quoted in the High Court’s 2025 SGHC 227, the penalty is a fine of up to S$200,000 or imprisonment of up to 2 years or both, with up to S$1,000 per day for a continuing contravention and a further S$2,000 per day if it continues after conviction.
Two points matter for owners and developers:
- The offence reaches those who permit or authorise the works, not only those who carry them out. Developers and owners cannot treat it as the contractor’s risk.
- BCA states that owners found with unauthorised additions or alterations have committed an offence and will be subject to enforcement action. It also warns that unauthorised works may be a safety hazard if not properly designed by a QP.
Enforcement can also be physical. Under the Building Control (Fixed Installations) Regulations 2025, in force from 1 October 2025, the Commissioner may order cessation, demolition or alteration of fixed installations or works that contravene the rules. The order is served on the owner of the installation or the developer or builder of the works. If it is not complied with, the Commissioner may carry out the demolition or alteration and recover the cost from the defaulter.
Rules that have recently changed
The Building Control Regulations 2003 show amendments in December 2024, April 2025, October 2025 and in 2026, the latest on 17 April 2026, according to the Singapore Statutes Online listing. BCA’s Building Control Act page also lists subsidiary legislation introduced in 2025, including the Reportable Matters Regulations and the Fixed Installations Regulations. For a regularisation submission, the consequence is simple: the case is measured against the version of the rules in force when it is submitted, so the QP should confirm the current requirements at the start.
Our view as engineers
Most regularisation cases that run long share one cause: the structural question is asked last. Owners prepare architectural drawings first, then find that the slab, beam or foundation cannot be shown to carry the as-built loads.
Our approach is to settle the structural and planning positions together at the outset, so that the choice between approval, rectification and removal is made on facts. We provide structural and geotechnical engineering, PE endorsement, and BCA, URA and SCDF submissions within one team, which is designed to keep the drawings, calculations and agency responses consistent. Our service is built on timely responses, clear communication and competitive fees.
For owners and developers, that means one point of contact from the first comparison of as-built and approved plans to the close of the approved works.
Aman
Starting a regularisation with AEC Technical
We handle regularisation as a combined engineering and submission engagement: structural and geotechnical assessment, PE endorsement, architectural drawings, and submissions to BCA, URA, SCDF and the other authorities your works involve. Hourly consultation is also available for an initial review of whether your works can be regularised. Send us the approved plans and a description of the as-built works through our services page, and our team will advise on the route.
For structural questions before submission, our structural and civil engineering consultancy page sets out what the engagement covers.
FAQ
Who can submit a regularisation application?
Only a qualified person, meaning a registered architect or a professional engineer with a valid practising certificate, can submit the plans to the Commissioner of Building Control. The owner appoints the QP, who also obtains the other required approvals, such as URA’s.
Does regularisation always mean the works stay?
No. The works must meet current planning and building requirements and the structure must be shown to be safe. If they do not, they can be strengthened or altered to comply, or the non-compliant part is removed. Checking the URA and structural position first avoids unnecessary drawing costs.
Are the owner or the contractor liable for unauthorised works?
Section 20(1) covers any person who carries out, permits or authorises building works without approval. That includes owners and developers as well as contractors, and each can face the fine of up to S$200,000 or imprisonment of up to 2 years.
Do small renovation works need approval?
Insignificant works do not need plan submission to BCA, but safety and other required approvals still apply. BCA’s list of works not requiring approval is the reference, and a QP can confirm whether a particular alteration falls inside it. Our guide on what requires BCA submission approval covers the usual cases.
Sources
- BCA: Building works not requiring approval
- Singapore Statutes Online: Building Control Act 1989
- BCA: Exemptions for building works requiring approval
- URA: Planning Permission
- The Straits Times: BCA reviewing scope of alteration works
- BCA: Guidelines for ST Plan Applications
- BCA: Building Plan submission
- BCA: New licensing regime news release, 3 September 2025
- Singapore eLitigation: 2025 SGHC 227