Temporary Works PE Endorsement for Gondolas and Suspended Platforms: What Contractors Must Submit to the PE
Introduction
A temporary works PE endorsement for gondolas and suspended platforms is the formal engineering sign-off by a registered professional engineer confirming that a suspended access scheme is structurally adequate, code-compliant, and safe for use on a commercial building in Singapore. At AEC Technical Advisory, we regularly review and endorse these systems for construction, façade rectification, repainting, and maintenance projects-working within the framework set by MOM’s Workplace Safety and Health Regulations and BCA requirements.
In short, contractors must submit layout drawings, structural calculations for support elements, manufacturer technical data and certificates, a detailed method statement for erection and dismantling, a task-specific risk assessment, inspection and maintenance records, and comprehensive site constraint information to the PE before any gondola installation begins. Temporary works designs must be submitted for PE review before installation, and a comprehensive documentation package is required for PE review of temporary works design.
This article focuses on commercial building works in Singapore where temporary suspended access systems-gondolas, motorised platforms, roof rigs, counterweighted outriggers, and parapet clamps-require a professional engineer’s endorsement for authority submissions or internal safety compliance. Permanent BMU systems designed as part of the base building are outside this scope; we are addressing project-specific, temporary gondola systems that need separate PE endorsement for each deployment.
The target audience is main contractors, specialist gondola and suspended platform subcontractors, safety officers, and project managers handling façade works on commercial properties. Whether you are coordinating a full curtain wall replacement or annual façade cleaning, the submission requirements are largely the same.
By the end of this article, you will:
- Know the exact documents and data to compile before engaging a PE
- Understand how to package submissions for faster PE turnaround (typically 5–10 working days)
- Recognise common gaps that trigger PE queries and delay endorsement
- Learn how to coordinate effectively between vendors, building owners, and the PE
- Have a practical pre-submission checklist you can use on your next project
Understanding Temporary Works PE Endorsement for Gondolas and Suspended Platforms
Temporary works in this context refer to all non-permanent structures and systems erected to provide access during building works-including the suspended scaffold platform itself, its suspension members, outriggers, counterweights, parapet clamps, and any structural strengthening needed to support them. PE endorsement is the design and structural sign-off under Singapore’s Professional Engineers Act, confirming that these temporary systems meet rigorous safety standards on project sites. PE endorsements are required for gondolas in Singapore, and they involve assessing design and safety standards in line with local construction regulations.
This endorsement is an engineering exercise, not a substitute for MOM licence applications or gondola operator training. However, it frequently links to BCA requirements for building works, WSH regulations for work at height, and sometimes MCST or SCDF requirements depending on the commercial building’s management structure.
Authorities, developers, and main contractors insist on PE endorsement for suspended platforms because the consequences of failure are severe: worker falls from height, collapse of support structures, damage to façade systems, and falling objects endangering the public at ground level. PE endorsements ensure compliance with local construction regulations and provide documented proof that every critical element has been assessed.
What Counts as Temporary Works for Suspended Access Systems and Suspended Scaffold
The range of systems that fall under temporary works for suspended access is broad. It includes modular gondolas, motorised suspended platforms, monorail-based cradle systems, roof rigs with counterweighted outriggers, parapet clamps, davit arms, and purpose-built suspension beams. Gondola systems are used for facade maintenance and repairs, and gondolas are essential for accessing high-rise building facades across Singapore’s commercial districts.
Critically, it is not just the gondola platform that constitutes temporary works. The support structures-roof beams carrying outrigger loads, parapet walls resisting clamp forces, davit posts anchored into RC slabs, and any spreader beams fabricated to distribute loads-all fall under temporary works requiring PE endorsement. Even when the gondola itself is a proprietary, certified system, the interface between that system and the building structure needs independent engineering verification.
Façade tie-back points, anchorages, and any strengthening or spreader beams installed to support the suspended scaffold are typically included in the PE’s temporary works design or review. Temporary works like gondolas require specific PE endorsements, and these must cover the full load path from the platform through the suspension members to the building structure.
Permanent BMU systems that were designed and installed as part of the original building are different-they would have been PE-endorsed during the base building design phase. Temporary, project-specific gondolas brought in for rectification, repainting, or periodic maintenance need their own separate endorsement each time they are deployed at a new location or configuration.
Role of the Professional Engineer (PE) in Gondola and Suspended Platform Projects
The PE’s role is to review all design loads-dead loads from the platform, wire ropes, counterweights, and motors; live loads from workers and materials; and environmental loads including wind and dynamic effects-and verify that every element in the load path can safely resist them. Structural calculations must verify the strength and safety factors for intended loads, and existing structural drawings must be verified against actual site conditions by the PE.
The professional engineer checks adequacy of support structures against relevant codes. Gondola systems must comply with Singapore Standard SS 598:2014, which is the Code of Practice for Suspended Scaffolds. The PE review should ensure compliance with local regulations like the Workplace Safety and Health Regulations, and design codes applied must be clearly indicated in structural calculations.
The PE may endorse either a full temporary works design prepared by a firm like AEC Technical Advisory, or a design originated by the specialist vendor that the PE has independently checked and accepted. In both cases, installation must comply with PE certified designs and drawings.
Under the Professional Engineers Act and Building Control Act, the PE carries legal responsibility for the adequacy of the endorsed design. This is precisely why complete, accurate submissions from contractors are not optional-they are the foundation the PE relies on. Understanding what a PE signs off on helps contractors appreciate why thoroughness matters.
To perform these duties efficiently, the PE relies on a clear, standardised set of documents from the contractor. The next section details exactly what that submission package must contain.
The Core Submission Package Contractors Must Prepare
Most PE reviews are delayed not by engineering complexity, but by missing or incomplete information from contractors. A well-prepared submission that arrives with all seven document categories complete can typically be endorsed within 5–10 working days. An incomplete one can stretch that timeline to weeks of back-and-forth queries.
This section walks through each document category the contractor should prepare before sending to AEC Technical Advisory or any PE. All documents should be in digital format-PDF for reports and certificates, DWG plus exported PDF for drawings-with legible mark-ups and clear labelling.
1. Site Information and Project Context
The PE needs full project context before starting any structural review. Provide the following:
- Project identification: Project name, full address, main contractor, building owner or MCST, contact persons for each party
- Purpose of gondola use: Façade cleaning, painting, curtain wall replacement, glass repair, cladding inspection, etc.
- Planned duration of use: Specific dates (e.g. January–June 2027), including mobilisation and demobilisation
- Schedule awareness: Any overlap with monsoon season or windier months that affects operational planning
Contractors should mark proposed gondola locations on existing CAD floor plans, roof plans, and elevations. Provide recent photographs of roof edge conditions, parapet walls, and any rooftop obstacles. Typical constraints that must be documented include setback distances from parapet edges, plant rooms on the roof, air-con ledges, glass canopies, link bridges, MRT protection zones near the façade line, and any load restrictions imposed on the roof structure.
Complete context prevents the PE from making design assumptions that may later clash with site reality. When a contractor submits a roof plan showing a clear, unobstructed area, but the actual roof has three condenser units and a solar panel array in that zone, the entire design review must restart.
2. Layout Drawings and Gondola Positioning
Detailed engineering drawings must show the exact positioning of structural components. The contractor or gondola subcontractor should prepare:
- Dimensioned roof plan: Showing suspension beam or counterweight layout, parapet clamp positions, outrigger placement, anchor points, and access routes for personnel reaching the roof edge
- Elevation views: Indicating gondola drop zones, travel limits (maximum descent from roof, height above ground), and clearance to the building façade
- Cross-sections: Through parapet walls and roof beams showing attachment details and load transfer paths
Preferred formats are AutoCAD DWG plus exported PDFs, with north point, scale, and key dimensions clearly marked-setback from roof edge, beam spans, parapet thickness, and distance between suspension points. Detailed drawings for suspended scaffolds must include clearance gaps and connection details.
For buildings with multiple façade orientations or varying conditions, propose typical layouts for each façade zone and label them clearly (e.g. “Zone A – North Façade”, “Zone B – Atrium Side”). This helps the PE assess each configuration systematically rather than guessing which setup applies where.
Highlight no-go areas over glass roofs, fragile canopies, or skylights, and show any existing permanent access systems that must be avoided or integrated. PE-stamped working drawings must show the exact positioning of rigging and structural supports once the review is complete.
3. Structural and Loading Data for Support Elements
Contractors must provide structural information for the roof slab or supporting structure where the gondola system will bear its loads. This includes:
- As-built structural drawings: Slab thickness, beam sizes, reinforcement details (bar sizes, spacing, cover), material grades
- Known load restrictions: Any imposed limits from the building’s original structural design or subsequent A&A works
- Condition information: Known weaknesses, previous damage, waterproofing layers, voids beneath the roof slab
Gondola vendor catalogues alone are not sufficient. The PE requires actual design loads applied to the existing structure, including self-weight of the platform, live loads from workers and tools, wind loads derived per SS 598 and CP3 or SS EN 1991-1-4, impact factors, and dynamic effects. Counterweight specifications must include mass, material, and fixing method.
If no original structural drawings are available-common in older commercial buildings-the contractor should arrange a simple structural investigation. Cover meter scans can identify reinforcement, and core tests can determine concrete strength. Submit these results to the PE as part of the package.
Load data checklist for the submission:
- Maximum working load (SWL) of the gondola system
- Number of workers per platform drop
- Equipment and material weight per drop
- Cable and counterweight masses
- Wind speed design threshold
- Dynamic or impact factors per SS 598 Table 2
4. Manufacturer Technical Data and Certificates
Manufacturer data must include technical data sheets and load ratings for the specific gondola or suspended platform model being used. The submission should contain:
- Product data sheets: Model number, rated load capacity, wire rope sizes, motor types and ratings, brake types, control systems
- Assembly and installation diagrams: Showing how the system is configured, including suspension beams or parapet clamps
- Safety device descriptions: Secondary brakes, safety ropes, override devices, tilt alarms, dead-man’s switches, emergency stop mechanisms. Safety devices must be included in equipment specifications for scaffolding systems
- Test certificates: Type-test reports, factory load test certificates, SS 598 compliance declarations, CE marking or equivalent conformity documents
Documents should clearly indicate serial numbers or batch numbers that match the actual equipment to be installed on site, allowing full traceability. The PE needs to verify that the certified equipment is what will actually be deployed-not a different model from the same manufacturer’s range.
For any locally fabricated steelwork-custom spreader beams, outrigger frames, or connection brackets-provide mill certificates for the steel grade, welding procedure specifications (WPS), welder qualification records, and details of corrosion protection or galvanisation. These are subject to the same level of PE scrutiny as the proprietary gondola components.
5. Method Statement and Erection / Dismantling Procedure
Contractors must submit a detailed method statement covering the full lifecycle of the gondola on site. The method statement should detail the sequence for delivery and installation of scaffolds, and procedures must be documented for safe installation and dismantling of scaffolds.
Key contents the PE will look for:
- Delivery and staging: How equipment arrives on site, temporary storage locations, access routes to the roof
- Erection sequence: Anchorage points installed first, then outriggers positioned, counterweights placed, platform assembled, suspension ropes rigged, safety devices connected and tested
- Proof load testing: Load test conducted before first operational use
- Operational procedures: How the gondola is moved between zones, re-rigged for different façade faces, or adjusted for varying setbacks
- Dismantling sequence: Reverse of erection, with specific attention to safe removal of counterweights and outriggers
- Lifting methods: Use of cranes or hoists to bring equipment to roof level, including crane positioning and lifting plans if applicable
The PE needs to understand how the physical configuration shown in the design will be achieved on site-including temporary bracing during erection, ballast placement sequence, and tie-backs used before the system is fully stabilised.
Format the method statement with numbered steps, annotated photos or diagrams of critical stages, and clear role assignments identifying who is responsible for each action. A well-structured method statement aligned with the temporary works coordinator’s documentation duties significantly reduces PE queries.
6. Risk Assessment and Work-at-Height Safety Measures
A task-specific risk assessment must be submitted, and a risk assessment must be conducted outlining operational hazards during installation. The RA or Safe Work Procedure (SWP) should address:
- Fall from height: Workers on the platform and on the roof edge during erection
- Falling objects: Tools, materials, or debris falling to ground level, especially in CBD areas with pedestrian traffic
- Equipment failure: Winch brake failure, rope rupture, outrigger displacement
- Weather: Wind gusts exceeding design thresholds, rain affecting grip and visibility
- Rescue scenarios: Platform stuck mid-façade, power loss, rope failure requiring emergency retrieval
Control measures should reference MOM’s Code of Practice for Working Safely at Heights and include double lifelines, independent safety ropes, harness use, exclusion zones at ground level with signage, and a documented emergency retrieval plan.
The PE does not replace the Workplace Safety and Health Officer, but needs to verify that the engineering design aligns with the assumed controls in the risk assessment. For example, if the design calculates loads based on two workers per gondola, but the risk assessment assumes three, this inconsistency must be resolved before endorsement.
| Hazard | Risk Level (Before Controls) | Key Controls | Residual Risk |
|---|---|---|---|
| Fall from height – platform | High | Safety harness + independent lifeline, guardrails on platform | Low |
| Falling objects to ground | High | Exclusion zone, debris netting, toolbox tethering | Low |
| Winch brake failure | High | Secondary safety brake, safety rope with automatic locking device | Low |
| Wind exceeding threshold | Medium | Wind speed monitor, cease-work protocol at 35 km/h | Low |
| Platform stuck mid-façade | Medium | Rescue plan, manual descent procedure, trained rescue team | Low |
7. Inspection, Testing, and Maintenance Records
A Certificate of Inspection must be issued post-installation of scaffolds by the PE, and the contractor should compile and submit the following records:
- Pre-use inspection checklists: Visual checks of rope condition, brake functioning, structural members, connections
- Third-party load test reports: Proof load test results before first use
- Commissioning records: Safety device functional tests, tilt alarm verification, emergency stop tests
- Previous incident or defect reports: For the same equipment, including corrective actions taken
- Personnel working on suspended scaffolds must have proper training certificates-submit copies for all operators and riggers
For recurring gondola use on the same building-such as annual façade maintenance cycles-the PE may request previous endorsement documents or as-built records to cross-check consistency. Guidance from safety authorities requires submission of detailed technical documentation for suspended work platforms.
Suspended scaffolds must be inspected weekly by a scaffold supervisor and thoroughly examined at least every six months by an authorised examiner, as required under SS 598. Align these periodic requirements with the proposed project duration and submit evidence of compliance upfront.
| Date | Type of Inspection/Test | Conducted By | Key Findings | Corrective Action |
|---|---|---|---|---|
| DD/MM/YYYY | Pre-installation visual check | Gondola vendor supervisor | All components in serviceable condition | None required |
| DD/MM/YYYY | Proof load test (125% SWL) | Third-party inspector | Pass – no deformation or defects | Certificate issued |
| DD/MM/YYYY | Safety device functional test | Gondola vendor technician | Secondary brake engaged within limits | None required |
| Weekly | In-service inspection | Site scaffold supervisor | Ongoing – logged weekly | As needed per findings |
| 6-monthly | Thorough examination | Authorised examiner | Per SS 598 requirements | Per examiner’s report |
How AEC Technical Advisory Reviews and Endorses Gondola Temporary Works
AEC Technical Advisory’s typical workflow for commercial projects in Singapore begins with an initial enquiry and scope discussion, moves through systematic document review and structural analysis, and concludes with issuance of PE-endorsed drawings and calculations. The team strives to serve customers across Singapore’s commercial building sector with a structured, query-minimising process.
There is an important distinction between a desktop review-where the PE works from supplied information, drawings, and certificates-and situations where a site visit or structural investigation is recommended before endorsement can proceed. The latter is common when existing structural drawings are unavailable or when the building has undergone significant modifications since its original construction.
Step-by-Step PE Review Process
- Pre-submission discussion: Clarify scope-number of gondola drops, façade zones, project duration, any unusual site constraints. This saves time by ensuring the contractor prepares the right information from the start
- Document completeness check: AEC’s team uses an internal checklist to verify all seven submission categories are present. As the company carrying out the completeness review, AEC Technical Advisory flags missing items in a single consolidated query sheet to minimise back-and-forth
- Structural analysis and code compliance checks: The PE analyses slab, parapet, beams, and fixings under factored gondola loads and wind loads, referencing SS 598, Eurocode provisions, and WSH regulations
- Safety and constructability review: Method statements and RA/SWP are reviewed against the engineering design to confirm alignment-worker numbers, SWL limits, exclusion zones, rescue provisions
- Issuance of endorsed documents: PE-endorsed drawings, structural calculations, and a design note with advisory conditions and limitations
Typical turnaround is 5–10 working days after a complete submission is received. Incomplete submissions extend this significantly-sometimes by weeks if structural investigations or additional manufacturer data are required. The process mirrors the broader PE endorsement workflow for scaffolding, adapted for the specific requirements of suspended access systems.
Design Checks and Codes Referenced
The PE references several key Singapore standards and guidelines during the review:
- SS 598:2014: The primary code for suspended scaffolds, covering anchorage design, suspension members, impact factors (Table 2), wind load conditions (Table 3), safety devices, and materials
- SS EN 1808: European standard for access equipment and suspended platforms, referenced by SS 598 for definitions and test methods
- Eurocode / SS EN 1991-1-4: Wind actions on structures, used to derive site-specific wind loads
- WSH (Scaffolds) Regulations 2011: Regulatory framework requiring PE design for suspended scaffold systems
- MOM Circular MOM/OSHD/2025-02: Recent guidance on safe design and installation of outriggers and overhead supports, requiring detailed drawings of components, connections, terminations, and calculations
The PE verifies ultimate limit state and serviceability for roof slabs, beams, anchorages, parapet walls, and custom steel members under factored gondola loads and wind loads. Where gondola rollers or tie-backs interact with façade elements-glass curtain wall mullions or aluminium cladding-the PE may also assess those elements for adequacy. Understanding façade access design principles helps contractors appreciate the breadth of this review.
Output Documents the Contractor Will Receive
Upon completion of the review, the contractor receives:
- PE-endorsed structural calculations: With clear load cases, code references, assumptions, and safety factors. PE endorsement must include a formal declaration of compliance with safety regulations
- PE-signed and stamped temporary works drawings: Roof plans, elevations, cross-sections, and connection details showing the exact positioning of all components
- Design note / limitations statement: Maximum SWL, wind speed thresholds for cease-work, maximum number of persons per platform, prohibited configurations, and conditions of use (e.g. weekly inspection required, re-certification at six months)
These documents serve multiple purposes: internal WSH documentation, submission to building owners or MCST for approval, supporting materials for MOM or BCA inspections, and reference material for toolbox briefings. Contractors should keep signed hardcopies on site and softcopies in project folders, and must update them if gondola positions or configurations change significantly. For a broader understanding of the PE endorsement checklist, refer to AEC Technical Advisory’s dedicated guide.
Common Submission Mistakes and How to Avoid Them
Repeated issues in temporary works submissions cause delays, increase costs, and may compromise safety if not addressed. Each problem below is drawn from experience reviewing hundreds of suspended platform projects across Singapore’s commercial building sector.
Problem 1: Incomplete or Outdated Drawings
Contractors frequently send cropped, low-resolution PDFs or outdated roof plans that do not reflect recent A&A works, installed solar panels, new plant rooms, or modified canopies. The PE then works from incorrect assumptions, which may lead to rejection or a design that cannot be built.
Solution: Retrieve the latest as-built drawings from the developer or building management. Perform a quick roof measurement check against those drawings. Mark proposed gondola positions directly on CAD files before sending to the PE. If CAD files are unavailable, clearly dimensioned hand mark-ups on printed plans with supplementary photographs are acceptable.
Problem 2: Missing Structural Information for Roof or Parapet
When slab thickness, reinforcement details, or beam capacities are missing, the PE must make conservative assumptions. This often results in heavy restrictions on permitted loads-sometimes reducing the allowed number of workers or requiring additional spreader beams, which increases project cost and time.
Solution: Engage the building’s original structural consultant if possible. If original records cannot be found, conduct simple non-destructive tests-cover meter scans and core tests-and submit results. Alternatively, adjust the gondola layout to bear on known beams or columns with documented capacities. This is especially relevant for older commercial buildings in Singapore that may have undergone multiple tenancy fit-outs.
Problem 3: Generic Method Statements Not Matching Actual Site Conditions
Copy-pasted method statements that describe a generic gondola installation but do not reflect the specific façade geometry, access routes, crane positions, or rescue arrangements for the actual commercial building are a persistent problem. The PE cannot endorse a procedure that does not match the design.
Solution: Walk the route on site before writing the method statement. Photograph critical points-roof access doors, parapet conditions, obstacles, crane staging areas. Customise the sequence to the exact roof configuration, and verify it with the gondola vendor before submission. A method statement developed from actual site conditions is almost always endorsed faster.
Problem 4: Safety Documents Not Aligned with Design Assumptions
Discrepancies between the risk assessment and the engineering design create confusion and delay. Common examples include risk assessments that assume two workers per gondola while operations plan for three, or RAs that omit falling object risks despite the gondola operating above busy pedestrian streets.
Solution: Cross-check the RA/SWP against design limits stated by the PE and equipment manufacturer. Update all documents so that worker numbers, SWL, and exclusion zones are consistent. This alignment exercise takes an hour but can save weeks of revision. For a deeper understanding of risk management for work at height, review AEC Technical Advisory’s practical guide.
Problem 5: Last-Minute Submissions Before Mobilisation
Contractors often approach the PE only days before the planned gondola installation date, leaving no time for review, revisions, additional testing, or authority-related clarifications. This is particularly problematic when structural investigations are needed or when manufacturer certificates are missing.
Solution: Adopt an internal timeline where initial PE discussion starts at least 4–6 weeks before the first gondola drop on a commercial project. Allow a buffer for at least one round of re-submissions. Early engagement with a firm like AEC Technical Advisory allows the team to flag issues while there is still time to resolve them without delaying mobilisation.
Conclusion and Next Steps
Successful temporary works PE endorsement for gondolas and suspended platforms depends on a complete, well-organised submission package covering design, safety, and documentation. Contractors who invest time in preparing thorough submissions-rather than treating the PE endorsement as a last-minute formality-consistently achieve faster approvals with fewer restrictions.
Your immediate next steps:
- Appoint a gondola coordinator within your project team to own the submission process and serve as the single point of contact with the PE
- Compile structural information for the building’s roof early-retrieve as-built drawings, or arrange non-destructive testing if originals are unavailable
- Engage the PE at least 4–6 weeks before the first gondola drop-discuss scope, number of zones, and any known site constraints
- Carry out a joint site walk with the PE, gondola vendor, and safety officer to verify conditions before finalising drawings
- Standardise an internal submission checklist based on the seven categories in this article, and use it for every project to develop consistent practice
Related topics contractors may need to explore include PE endorsement for façade access rail systems, scaffolding PE endorsement for commercial façade works, and BCA submission requirements for commercial A&A projects.
If you have questions about temporary works design and endorsements for an upcoming commercial project, contact AEC Technical Advisory to discuss your requirements and timeline.
Additional Resources and Practical Checklists
This section provides quick-reference material you can use directly on your projects.
Contractor’s Pre-Submission Checklist for Gondola PE Endorsement
- ☐ Project name, address, main contractor, building owner/MCST, and contact details
- ☐ Purpose and planned duration of gondola use
- ☐ Existing architectural and structural as-built drawings (roof plan, elevations, sections)
- ☐ Recent site photographs of roof edge, parapet, and constraints
- ☐ Dimensioned layout drawings showing gondola positions per façade zone (DWG + PDF)
- ☐ Structural data for support elements: slab thickness, reinforcement, beam sizes, material grades
- ☐ Non-destructive test results (if original structural drawings unavailable)
- ☐ Manufacturer product data sheets with model number, rated load, and safety device details
- ☐ Type-test certificates, factory load test reports, SS 598 compliance declarations
- ☐ Serial/batch numbers matching actual equipment to be deployed
- ☐ Mill certificates and welding records for any custom-fabricated steelwork
- ☐ Counterweight specifications: mass, material, fixing method
- ☐ Method statement: delivery, erection, operation, relocation, and dismantling sequence
- ☐ Task-specific risk assessment / Safe Work Procedure with rescue plan
- ☐ Pre-use inspection checklists and proof load test records
- ☐ Training certificates for all personnel working on the suspended scaffold
- ☐ Previous endorsement documents and inspection records (for recurring use)
Well-Prepared Submission vs Typical Problematic Submission
Well-prepared submission:
- Current as-built drawings with proposed positions marked in CAD
- Structural data confirmed by investigation or original records
- Manufacturer certificates with matching serial numbers
- Site-specific method statement with annotated photos
- RA/SWP consistent with design loads and worker numbers
- Submitted 4–6 weeks before mobilisation
Typical problematic submission:
- Outdated or cropped PDF drawings with no dimensions
- No structural data-“vendor says the parapet is strong enough”
- Generic certificates not matching actual equipment model
- Copy-pasted method statement from a different project
- RA assumes two workers; operations plan for three
- Submitted 3 days before gondola arrives on site
Recommended Visual Documentation
For the strongest submissions, include:
- Annotated roof plan photographs showing proposed outrigger positions relative to existing obstacles
- Close-up photographs of parapet condition (thickness measurement with tape visible)
- Photographs of roof slab soffit where accessible, showing beam lines and any visible reinforcement
- Sample images of the actual gondola model and safety devices to be used
- On-site photos showing correct counterweight arrangement and anchorage details from previous installations of the same system
Key Regulatory References
- SS 598:2014 – Code of Practice for Suspended Scaffolds
- WSH (Scaffolds) Regulations 2011 – Statutory requirements for scaffold design by a PE
- MOM Circular MOM/OSHD/2025-02 – Safe design and installation of outriggers or overhead supports for suspended scaffolds
- SS EN 1808 – Definitions and requirements for suspended access equipment
- MOM Code of Practice for Working Safely at Heights – Operational safety requirements
For project-specific interpretation of these standards, which are governed locally by MOM and BCA, AEC Technical Advisory, an established company, can provide guidance tailored to your commercial building’s conditions and your gondola vendor’s equipment specifications.