Introduction
A BCA BP submission for GCB new erections requires a coordinated package of architectural plans, structural drawings, structural design calculations, site investigation reports, and multi-agency clearances before construction begins. This article sets out the technical drawing and calculation requirements that the Building and Construction Authority (BCA) expects when you submit building plans for a new Good Class Bungalow in Singapore, covering the full scope from architectural layouts through Eurocode-based structural analysis to geotechnical input.
The scope here is residential GCB new erections only: full demolition of an existing structure and construction of a new bungalow on a GCB-designated plot. Minor additions and alterations, regularisation of existing buildings, and temporary structures fall outside this discussion. The focus is on architectural and structural plans, calculation reports prepared to Eurocodes with Singapore National Annexes, and the coordination needed across BCA, URA, SCDF, PUB, NParks, and LTA for regulatory approval, meeting regulatory requirements, and satisfying applicable safety standards.
This article is written for GCB owners, developers, main contractors, architects, and engineers preparing for a full rebuild or new GCB erection during the 2024–2027 period. In short: BCA expects this package as part of its approval framework, with a complete set of coordinated architectural drawings (site plan, floor plans, sections, elevations), detailed structural drawings (foundation layouts, beam-slab arrangements, retaining wall sections, pool shells), a structural calculation book covering gravity loads, lateral stability, foundation design, and serviceability checks, plus a site investigation report certified by a professional engineer; complete, coordinated documents are essential to secure BCA approval. All documents must be endorsed by a qualified person before submission, and early BCA submission planning together with proper risk assessments helps avoid delays.
By the end of this article, you will understand:
-
What drawings a GCB building plan submission must contain and at what level of detail
-
The minimum structural calculation set required under Eurocodes with Singapore National Annexes
-
How the submission process differs between CORENET 2.0 and CORENET X, including changes taking effect from 1 October 2026
-
The most frequent reasons BCA queries GCB submissions and how to prevent them
-
How AEC Technical Advisory coordinates a complete drawing, calculation, and authority submission package for new GCB erections
Understanding BCA BP Submission for New GCB Erections
Building plan approval is the primary architectural and code-compliance gate that must be cleared before any structural works or construction can proceed on a new GCB. BCA oversees Singapore’s built environment and construction safety within an approval framework intended to reduce structural risk and maintain safety standards, and requires building plan approval before construction begins. The BP submission covers architectural layouts, spatial compliance, fire safety provisions, drainage, and accessibility. Without BCA BP approval, no permit to commence building works will be issued.
Running in parallel with the BP is a separate structural plan submission (ST), which covers all structural elements, structural drawings, and the calculation book. For GCB new erections, both BP and ST must be aligned, and coordinated BCA submission documents are essential for obtaining BCA approval efficiently: the architectural grids, finished floor levels, and building envelope shown in the BP must match exactly what the structural engineer has designed and calculated. Misalignment between these two sets of structural and building plans is one of the most common causes of BCA queries.
GCBs are the most tightly regulated class of landed housing in Singapore. A Good Class Bungalow often requires a minimum land area of 1,400 m². URA’s Envelope Control Guidelines impose stricter setback, height, roof form, site coverage, and attic volume limits than those applied to standard detached houses. These constraints make well-prepared BP packages critical; a submission that fails to demonstrate envelope compliance will not proceed past URA’s review.
Regulatory Definition of a New GCB Erection
A “new erection” in BCA and Urban Redevelopment Authority terms means full demolition of any existing structure and construction of a new bungalow within a URA-designated GCB area. These designated areas include estates such as Bin Tong Park, Dalvey Estate, Ridley Park, Cluny Hill, and Chatsworth Park. GCB status is determined by URA’s gazetted boundaries, not by the size or style of the house alone.
New erection differs from a “rebuild” or Major A&A in a concrete way: a new erection triggers full BP and ST submissions, a new site investigation, and fresh structural design calculations for all primary structural elements. There is no reliance on prior approval or previous structural data. Envelope controls, height limits, and site coverage reset entirely. By contrast, a Major A&A submission can reference portions of an existing approved structural scheme if the original building structure is partly retained.
BP clearance for a GCB new erection can only be finalised after URA Written Permission confirms that the proposed design complies with envelope controls and planning parameters. Architectural plans must align with approved planning parameters from URA for GCB projects. Without valid planning permission from URA, BCA will not grant BP approval.
What BCA Building Plan (BP) Approval Covers for GCBs
For a new GCB erection, the BP scope includes: architectural layouts at every storey, sections and elevations showing floor-to-floor heights and building height relative to platform level, escape routes, fire safety provisions (coordinated with SCDF), drainage compliance (coordinated with PUB), tree protection zones (NParks), and road access (LTA). BCA ensures compliance with fire safety and accessibility standards as part of this review.
The BP interfaces with multiple technical agencies. Clearances are required from statutory bodies like PUB and SCDF for GCB submissions. NParks reviews tree protection and green buffer requirements. LTA reviews road and pavement access. Each agency’s conditions must be reflected in the submitted drawings. A Building Plan for a Good Class Bungalow in Singapore requires adherence to building control regulations, and BCA’s approval process includes multiple agency clearances running simultaneously.
BCA’s review for GCB BPs pays particular attention to site gradients (especially on sloped estates), basement impact on neighbouring properties, boundary retaining walls, vehicle access gradients, and pool locations within the permissible building envelope. Building height in GCB submissions is governed by URA envelope control guidelines, and sections must demonstrate that every part of the proposed building sits within the allowable height planes measured from platform level.
Where BP Sits in the Overall GCB Approval Sequence
The typical approval sequence for a new GCB erection follows this order:
-
Surveys and studies (topographical, cadastral, tree survey, preliminary site investigation)
-
URA Provisional Permission (PP); URA Provisional Permission takes 6–8 weeks for initial response
-
URA Written Permission (WP)
-
BCA BP + ST submissions
-
Agency clearances from PUB, NParks, SCDF, and LTA
-
Permit to Commence Building Works
-
Temporary occupation permit (TOP) / statutory completion certificate (CSC)
BP and ST can be initiated after URA PP, but they must ultimately conform to URA Written Permission. If the WP contains conditions that differ from the PP design, revised drawings and calculations will be required before BCA grants plan approval, and early submissions can also result in wasted plan fees if later WP-driven changes force a resubmission. BCA requires a Permit to Commence Building Works after BP approval and before any construction phase activity starts on site.
A compliant BP package for a new GCB starts with the correct types of drawings prepared to BCA’s technical expectations, which the next section addresses in detail.
Core Technical Drawing Requirements for New GCB BP Submissions
BCA expects a complete set of coordinated architectural and structural drawings for a GCB new erection, with enough detail to verify safety, buildability, envelope compliance, and adherence to the Building Control Act. Technical drawings must demonstrate compliance with safety, health, and accessibility standards. The drawing set must be internally consistent: architectural sections must match structural sections, and all levels must reference a single master datum.
Architectural Drawings Required in a GCB BP Package
The architectural building plan submission includes site plans showing lot boundaries, platform levels, contour lines, existing versus proposed site levels, tree protection zones, and building setback lines. Architectural drawings for a Building Plan must include clear dimensions and room designations.
The full architectural drawing set for a GCB BP typically includes:
-
Site plan: property boundaries, platform levels, reduced levels (RLs), contours, setback lines, site coverage area calculations, and annotated envelope control planes. Show existing and proposed ground levels.
-
All-storey floor plans: ground floor, upper storeys, attic (if applicable), basement. Plans at 1:100 scale with finished floor levels (FFLs), room names, wall thicknesses, and staircase positions.
-
Roof plan: showing roof form, ridgeline heights, any roof terraces, and overhangs.
-
Elevations on all four sides: building elevations must show existing and proposed ground levels alongside building heights. Annotate the permissible URA envelope height planes so the reviewer can verify compliance at a glance.
-
Sections: typical and critical sections at 1:50 scale, cut through basements, pools, retaining walls, driveways, and slopes. At least one long section and one cross-section are needed; sites with steep gradients may need three or more.
GCB-specific annotations are mandatory. Show the allowable 2-storey (or 3-storey, depending on the estate’s Master Plan zoning) height envelope, attic volume limits, and roof terrace setback from the top of the envelope (URA requires roof terraces on attic roofs to be at least 3 m below the top extent of the permissible building envelope). Site coverage calculations must demonstrate compliance with URA’s 45% site coverage limit for GCBs, including the sub-control that counts 50% of car porch roof area toward the bulk measurement.
For steep GCB sites (common in Dalvey Estate, Ridout Road, and parts of Cluny Hill), additional split-level sections and front-to-back gradient sections are needed. These sites often require retaining walls at multiple levels, and BCA reviewers will check that sections accurately reflect the proposed earthworks and slope stabilisation.
Structural Drawings That Must Accompany BP for a New GCB
Structural plan submissions require detailed structural drawings and calculations, and BCA approval depends on complete, coordinated structural documentation. Foundation plans and structural details are crucial for the approval of new building erections. The structural drawing set submitted alongside (or shortly after) the BP must include:
-
General arrangement (GA) plans at each level, showing beam and slab layouts, column positions, and load-bearing wall locations
-
Foundation layout: footings, pile positions, or raft extents, with founding depths and pile types annotated
-
Retaining wall plans and sections: wall thickness, reinforcement, waterproofing layer, drainage provisions, and interaction with boundary conditions
-
Basement box drawings (where applicable): wall sections, base slab, waterproofing membrane details
-
Pool shell drawings: wall and base slab thickness, waterproofing and membrane detail, crack control reinforcement
-
Roof framing plan: timber, steel, or reinforced concrete framing with member sizes
-
Reinforcement schedules and bar bending schedules for critical members
Every structural drawing must be endorsed by the qualified person (QP), who is a registered professional engineer in the structural discipline. Drawings must be cross-referenced to the architectural grids, levels, and room names used in the BP set, so BCA can verify coordination between the two submissions. BCA submissions require endorsement by a qualified person, typically a registered architect or engineer; only a qualified person can apply for structural plan approval.
For GCBs with basements and pools near boundaries, drawings must show waterproofing details, wall thickness, tie-back or ground anchors (if any), and clearance from neighbouring properties. BCA frequently queries basement and retaining wall submissions that omit interaction details between the proposed earth retaining structures and adjacent plots, especially where later design revisions or remedial works involve structural strengthening near the boundary.
Other Supporting Drawings and Diagrams
A complete GCB BP package includes several ancillary drawing types:
-
Driveway gradient profiles: showing entry gradient from road level to car porch or basement, with percentage gradient annotated. This is reviewed by both BCA and LTA.
-
Drainage layouts: fall directions, sump positions, sewer invert levels, and surface runoff management. Drainage plans are required to ensure compliance with surface runoff management in construction projects.
-
Platform level diagrams: showing how the proposed platform relates to the Minimum Platform Level set by PUB for low-lying sites.
-
ERSS concept drawings: for GCB sites with deep basements close to public roads, drains, or neighbouring structures, a concept drawing for the earth retaining and stabilising structures may be required even if the full ERSS submission is separate.
-
Fire safety coordination drawings: fire engine access paths, turning radii, hydrant locations, hose reach coverage, escape routes. Submissions for building projects in Singapore must comply with fire safety regulations and planning parameters.
-
M&E coordination drawings: plant room positions, lift pit dimensions, major service risers, and any structure-penetrating services that affect beam or slab layouts.
These supporting documents are reviewed during the cross-agency review that forms part of BCA’s BP process. Omitting any of them is a common cause of Written Directions or requests for additional information.
Structural Calculation Requirements for New GCB Erections
BCA requires comprehensive loading and structural design calculations for all primary structural elements in a new GCB. Structural designs must comply with Eurocode standards integrated with Singapore National Annexes. The calculation book must demonstrate both ultimate limit state (ULS) safety and serviceability limit state (SLS) performance, and every designed element must be traceable to a corresponding structural drawing.
Applicable Codes and Standards (Eurocodes, Singapore NAs)
Singapore’s structural codes are based on the Eurocode series, published as Singapore Standards (SS EN) with Singapore National Annexes (NAs) that modify default Eurocode parameters. The main standards invoked for a GCB structural submission are:
-
SS EN 1990 (Basis of structural design): load combinations, partial safety factors
-
SS EN 1991-1-1 (Self-weight and imposed loads for residential occupancy) and SS EN 1991-1-4 (Wind actions)
-
SS EN 1992-1-1 (Concrete design) and SS EN 1992-3 (Liquid-retaining structures, relevant for pools)
-
SS EN 1993 and SS EN 1994 (Steel and composite members, where applicable)
-
SS EN 1997-1 and 1997-2 (Geotechnical design and site investigation)
-
SS EN 1998-1 (Seismic actions, if required under BCA’s seismic zone classification)
-
BCA design guides BC1, BC2, BC3
The Singapore National Annexes modify default Eurocode values for items such as partial factors, imposed loads for residential usage, wind speed parameters, and durability exposure classes. Calculations must explicitly state which NA version and amendment apply. BCA frequently rejects calculation books that cite SS EN codes without specifying the Singapore NA version used; this is a common and avoidable reason for queries. Mixing legacy British Standards (BS) with Eurocodes within the same structure is not permitted under BCA’s Approved Document.
BCA expects a clear design basis summary at the start of the calculation report: codes used, material strengths, durability exposure class, design live loads, wind parameters, foundation assumptions, and partial safety factors.
Minimum Calculation Set for a Typical New GCB
The structural calculation book for a GCB new erection generally covers:
-
Introduction and design criteria: codes, materials, loads, safety factors, design assumptions
-
Actions and load combinations: self-weight, imposed loads per SS EN 1991, wind loads, load combinations per SS EN 1990
-
Structural analysis: 3D frame model or representative 2D frames, with output showing bending moments, shear forces, and axial loads for critical members
-
Member design: beams (including long-span and transfer beams), slabs, columns, walls, roof members, cantilever balconies, staircases, planter boxes
-
Foundation and geotechnical checks: bearing capacity, pile design (axial, lateral, tension), settlement, raft design where applicable
-
Retaining wall and basement design: earth and water pressures, sliding, overturning, global stability
-
Pool shell design: hydrostatic pressure, crack width control, waterproofing detail
-
Serviceability: deflection under characteristic and quasi-permanent loads, crack width limits, vibration checks where relevant
Not every single member needs a separate hand calculation, but the professional engineer must show representative calculations for worst-case elements and provide evidence that the overall structural model has been reviewed and validated. The first and last pages of the calculation book must carry the PE’s endorsement and certification.
Geotechnical and Foundation Design Calculations
Geotechnical assessments are important for buildings involving basements or deep excavations. For GCBs with basements or on challenging terrain (sloped sites, high water tables, variable soil strata), BCA expects foundation design to be based on properly interpreted site investigation data in accordance with SS EN 1997.
The SI report must include borehole logs, field and lab test results, groundwater table levels, soil strata descriptions, and characteristic soil parameters derived from the data. SI works must be carried out by an SAC-accredited inspection body, and the report must be signed and certified by a professional engineer (geotechnical). BCA’s Advisory Note 1/03 specifies a minimum of 3 boreholes per project site, or one borehole per 300 m², whichever yields more. Boreholes must extend beyond the founding level into hard stratum.
Foundation calculations must include bearing capacity checks, pile design (axial, lateral, tension loads, group effects), and settlement prediction. For piled foundations, load test requirements apply: at least one ultimate load test on a preliminary pile (or 0.5% of total piles), and at least two working load tests (or 1% of working piles).
Retaining wall and basement design checks must cover earth and water pressures, global stability, sliding and overturning, and construction-stage interaction where ERSS engages with permanent works. For GCBs on sloping sites, these checks are where BCA reviewers spend the most time.
Serviceability, Deflection and Crack Control in GCBs
Luxury GCBs commonly feature long-span living rooms (8 m or more), large sliding glass doors, fine stone or timber finishes, and glazed façades that are intolerant of excessive deflection. Deflection checks under characteristic and quasi-permanent loads are required for main beams and slabs, with typical limits of span/250 for total deflection and span/360 (or tighter) for deflection after installation of finishes and partitions.
Crack width control is especially important near glass façades and in water-retaining structures. Pool shells and water features designed under SS EN 1992-3 must meet crack width limits (commonly w ≤ 0.2 mm for liquid-retaining faces) to prevent leakage and durability problems. BCA is applying closer scrutiny to serviceability and durability in recent review cycles; submitting without these checks invites queries.
For GCBs with slender floor plates supporting gyms, piano rooms, or large open-plan spaces, vibration comfort checks referencing SS EN 1991 guidance may also be warranted. While not universally required, addressing vibration proactively eliminates a potential BCA or AC query on structural safety and occupant comfort.
Preparing a Compliant BP and ST Package for GCB New Erections
Assembling a compliant submission package requires an integrated team from the outset: architect, structural PE, geotechnical engineer, M&E engineer, fire safety engineer, and drainage engineer. Preparing documentation in sequence rather than in parallel typically adds weeks or months to the programme; early coordination reduces rework and written directions from BCA.
Step-by-Step Process for Assembling Drawings and Calculations
Begin technical documentation after the design concept is confirmed and in parallel with the URA Provisional Permission application. The following sequence reflects a well-planned BCA submission sequence for new GCB erections:
-
Commission surveys and investigations: topographical survey, cadastral boundary survey, tree survey, and preliminary site investigation to establish geotechnical parameters before finalising basement depth or foundation type.
-
Freeze massing and layout: architect and owner confirm building footprint, number of storeys, basement extent, pool position, and driveway alignment in compliance with URA GCB envelope controls. Delayed changes at later stages increase cost and redesign risk, and changes after approval may require amendments to approved plans before work proceeds.
-
Develop coordinated architectural layouts: finalise levels, sections, and structural grids. All architectural plans must carry clear dimensions, room designations, FFLs, and RLs referencing a single master datum.
-
Structural engineer builds design model and calculation report: analysis and member design to the agreed Eurocodes and Singapore NAs, covering all key structural elements from roof to foundation.
-
Produce detailed structural drawings: coordinated with the architectural set, including foundations, basements, retaining walls, pools, and reinforcement schedules.
-
Integrate fire safety coordination, drainage alignments, and access provisions: fire safety engineer reviews escape routes and appliance access; drainage engineer confirms fall, sump positions, and sewer clearance.
-
Internal checking and AC review: the QP (PE) performs internal verification. Where required (deep basements, complex retaining and stabilising structures, unusual spans, or complex temporary structures requiring PE Civil endorsement before erection for relevant site works), an Accredited Checker performs an AC’s independent structural analysis and issues a certificate or checklist. BCA structural plan applications without accredited checker’s certification take 7 working days for processing.
Coordinating BP Drawings with ST Calculations and SI Reports
Traceability is the central requirement. Every key structural element designed in the calculation book must be clearly labelled and findable on the drawings, using the same grid references, the same member mark numbers, and the same RLs. BCA reviewers cross-check architectural sections against structural sections against calculation diagrams; discrepancies in beam depth, slab thickness, or retaining wall height between the three documents trigger immediate queries.
SI reports must be referenced explicitly in foundation design sections. The calculation book should state how characteristic soil parameters were derived from lab data and borehole logs, citing specific borehole numbers and test results. Generic or assumed soil parameters, without reference to actual SI data, are treated as incomplete by BCA.
For basements and pool walls near property boundaries, BCA checks whether the structural drawings show the same waterproofing detail and wall configuration that the calculations assume. A waterproofing membrane shown on the architectural section but absent from the structural detail (or vice versa) will generate a clarification request.
Comparison: Minimal vs Robust Submission Packages
|
Criterion |
Minimal Package |
Robust Package |
|---|---|---|
|
Architectural coordination |
Basic plans and elevations; envelope compliance shown on one section only |
Full plan-section-elevation set with envelope planes annotated on all critical sections; site coverage and sub-control calculations included |
|
Structural analysis detail |
Representative calculations for main beams and columns only; limited load combinations |
Full 3D model with output for all critical members; complete load combination set per SS EN 1990 |
|
Geotechnical input |
Minimum 3 boreholes; generic soil parameter table |
Additional boreholes at basement corners and pool; detailed lab test interpretation; groundwater monitoring data |
|
Serviceability checks |
Deflection check for longest span only; no crack width checks |
Deflection for all spans exceeding 6 m; crack width for pool shell, basement walls, and façade-adjacent slabs; vibration check where relevant |
|
Clash resolution |
Limited coordination between architect and engineer before submission |
BIM-coordinated model or overlay check; pre-submission review meeting with all disciplines |
Robust packages correlate with fewer written directions and shorter total approval cycles. BCA BP approval typically takes 8–12 weeks for GCBs, and BCA requires 14–28 working days per review cycle. Each round of queries adds another cycle. A well-developed package that anticipates BCA’s cross-checks and agency requirements can reduce the total number of review cycles from three or four down to one or two, saving weeks in the overall programme.
Common Issues in GCB BP Technical Submissions and How to Resolve Them
Many GCB building plan submissions are delayed not by exotic design problems but by drawing inconsistencies, incomplete calculations, and unclear geotechnical assumptions. Below are the four most frequent issue categories, based on typical BCA query patterns, and the corrective actions that prevent them.
Mismatched Architectural and Structural Levels
The most common coordination failure is FFLs on architectural plans that do not match structural slab levels on GA drawings. This happens when the architect adjusts floor finishes thickness or platform levels after the structural engineer has finalised slab RLs. The same problem appears with driveway levels, pool deck levels, and boundary wall top-of-wall levels.
The fix is procedural: establish a single master level datum drawing shared between architect and structural engineer. If the team uses BIM, a coordinated model eliminates this class of error at source. If working in 2D CAD, a controlled revision log with sign-off from both QPs before submission catches mismatches. Every RL on the structural drawing should be arithmetically traceable to the corresponding FFL on the architectural plan (structural slab RL + finishes thickness = architectural FFL).
Incomplete or Unclear Geotechnical Basis for Basement and Foundation Design
Submitting structural calculations based on generic soil parameters, or referencing an SI report from a previous project or an adjacent site, triggers BCA queries. This is especially problematic for deep basements on sloping GCB sites where soil strata can vary within short distances.
Commission the SI to current BCA guidelines (minimum 3 boreholes per site, depth beyond founding level into hard stratum). Summarise the design soil parameters in a dedicated section of the calculation report, with explicit references to specific borehole numbers and lab test result sheets. Include critical borehole sections on the structural foundation drawing so the reviewer can see the relationship between soil conditions and founding depth without having to cross-reference a separate document. BCA’s guidelines on structural plan applications emphasise that SI data must be site-specific and current.
Under-Specified Long Spans, Cantilevers and Pools
GCB designs frequently feature cantilevered terraces of 8–10 m, rooftop infinity pools, and open-plan living rooms with minimal column support. When these signature architectural features lack detailed structural design and serviceability checks in the initial submission, BCA issues clarifications that delay the entire approval.
Include specific ULS and SLS calculations for these elements at first submission. For cantilevered members, show deflection under quasi-permanent loads, wind uplift checks, and connection details at the support. For pool shells, include hydrostatic pressure design, crack width verification to SS EN 1992-3, and waterproofing membrane specification. Deferring these to later amendments adds review cycles and extends the approval timeline.
Insufficient Fire and Access Coordination in Drawings
For large GCBs with basements, extended driveways, and multiple wings, fire appliance access, hose reach, and escape stair layouts generate frequent BCA/SCDF comments. The problem typically arises when fire safety coordination is treated as a late-stage activity rather than an integral part of the initial BP set.
Engage a fire safety engineer during schematic design. Show fire engine access paths with turning radii, hydrant locations with hose reach circles, and all escape routes on the BP drawing set. For GCBs with basement car parks, confirm that the driveway gradient complies with SCDF requirements for fire appliance access. Including all fire safety provisions in the first submission avoids a category of written directions that can add 4–6 weeks to the programme.
CORENET 2.0, CORENET X, and GCB Submission Workflows
Most individual GCB new erections have a statistical gross floor area well below 5,000 m², which means they can currently submit under CORENET 2.0. CORENET X becomes mandatory for all new projects by October 2026. From 1 October 2026, all new building works projects with GFA of 5,000 m² or more must submit via CORENET X; projects below that threshold may opt in voluntarily.
CORENET X integrates multi-agency reviews through BIM-enabled submissions, using models in IFC+SG (openBIM) format. CORENET X requires full BIM models and digital readiness from consultants. The system introduces three submission gateways: Design Gateway, Piling Gateway (optional, relevant for piled foundations), and Construction Gateway. At each gateway, regulatory agencies (URA, BCA, SCDF, PUB, NParks, LTA) review in parallel rather than sequentially, enabling a cross-agency review within a single window. CORENET X submissions take approximately 20 working days for processing.
For GCB projects below the mandatory threshold, submitting via CORENET 2.0 remains an option. Under legacy BCA ST processing, BCA structural plan applications are processed in 7 working days for a complete ST submission without Accredited Checker involvement. Under CORENET X, the 20-working-day collective response window applies across all agencies.
Early adopters of CORENET X reported time savings of up to two months compared to sequential legacy submissions. Even for GCB owners whose projects fall below the BIM mandate threshold, voluntary adoption of CORENET X can reduce total approval duration by consolidating agency feedback into a single coordinated response. The trade-off is the upfront cost and effort of preparing a BIM model and ensuring IFC+SG export quality across architecture, structure, and M&E disciplines.
Conclusion and Practical Next Steps for GCB Owners and Project Teams
A successful BCA BP submission for a new GCB erection depends on three things: a complete, coordinated set of architectural and structural drawings; transparent, Eurocode-based structural calculations with explicit Singapore NA references; and solid geotechnical input combined with early cross-agency alignment. The entire regulatory approval phase spans 3 to 6 months, and the most controllable variable in that timeline is the quality and completeness of the initial submission package.
For GCB owners and project teams preparing a new erection, these are the immediate next steps:
-
Confirm site status, GCB envelope controls, and any title restrictions with URA before committing to a design scheme.
-
Appoint an architect and structural PE with direct experience in GCB BP and ST submissions.
-
Commission topographical surveys and site investigation early, before finalising basement depth, pool position, or foundation type.
-
Insist on a coordinated pre-submission review of all drawings and calculations, with architect and structural engineer verifying level consistency, grid alignment, and envelope compliance together.
-
Plan the programme around realistic BCA processing timelines: 8–12 weeks for BP approval, 7 working days for ST without AC, and additional cycles if clarifications are needed.
AEC Technical Advisory, as a multidisciplinary consultancy in Singapore, provides one-stop coordination for architecture, structural and M&E design, PE endorsements, and all BCA, URA, SCDF, and PUB submissions for new GCB erections. From initial SI coordination through to structural calculation preparation and complete authority submissions, the firm manages every technical deliverable required for obtaining approval.
Frequently Asked Questions on BCA BP Requirements for New GCB Erections
Do I need both BP and ST submissions for every new GCB erection?
New erections of GCBs require both BP (architectural) and ST (structural) approvals. The BP is submitted by a QP (Architect), and the ST is submitted by a QP (PE Civil/Structural). Both must be coordinated: structural slab levels must match architectural FFLs, and structural grids must align with architectural layouts. BCA mandates structural plan approval for new buildings, and a permit is required before starting any structural works after approval.
What structural calculations does BCA expect for a two-storey GCB without a basement?
For a straightforward two-storey GCB without a basement, the calculation set includes: load combinations to SS EN 1990/1991, representative beam and slab designs to SS EN 1992, column designs, footing or pile design to SS EN 1997, and basic serviceability checks (deflection for main spans, crack width for any water features). Omitting foundation design or serviceability checks triggers queries even for simple structures. A qualified person must apply for structural plan approval, and the calculation book must carry PE endorsement on the first and last pages.
How does CORENET 2.0 vs CORENET X affect my GCB BP submission?
Most GCB new erections have GFA below 5,000 m² and currently qualify for CORENET 2.0 submission. From 1 October 2026, CORENET X becomes mandatory for all new projects. CORENET X submissions take approximately 20 working days for processing across all agencies, compared to sequential processing under CORENET 2.0. CORENET X requires BIM models in IFC+SG format for projects meeting the GFA trigger, but GCB projects below the threshold can opt in voluntarily without the BIM mandate.
Do I need an Accredited Checker (AC) for my new GCB erection?
AC involvement is triggered by specific project characteristics: deep basements, complex retaining and stabilising structures, unusual structural spans, or deviations from standard design. For many straightforward GCBs, a PE QP alone suffices. When an AC is required, their independent structural analysis and certificate must accompany the ST submission. BCA structural plan applications without accredited checker’s certification take 7 working days; with AC involvement, processing follows the standard review timeline. Confirm the requirement with your appointed PE based on current BCA thresholds.
Can AEC Technical Advisory manage the entire drawing, calculation and submission process for my GCB project?
AEC Technical Advisory can manage the BCA submission strategy and authority coordination needed for BCA approval, alongside architectural and structural design, SI coordination, full structural calculations to Eurocodes with Singapore NAs, PE endorsements, BIM support, and complete BCA BP/ST submissions for new GCB erections. This may also cover A&A-related structural work such as modifying load-bearing walls or structural strengthening when these arise on related projects, while the main focus remains on new GCB erections. The firm also coordinates all parallel agency submissions to SCDF, PUB, URA, and NParks, functioning as a single point of contact for the entire regulatory approval and submission process.