Structural Design and Analysis for Rooftop Solar Loads on Factories: Common Errors Found During PE Review
Introduction
Structural design and analysis for rooftop solar loads on factories is one of the most critical aspects of any industrial solar project in Singapore and Southeast Asia. When a Professional Engineer (PE) reviews a rooftop solar structural submission, two errors appear more frequently than any other: underestimating wind uplift and edge/corner suction loads, and assuming spare capacity of existing roof framing without proper verification. These mistakes account for the majority of PE review rejections and can delay project approval by weeks or months.
This article focuses on factory and industrial buildings-pre-engineered buildings (PEBs), steel portal frames, reinforced concrete (RC) warehouses, and lightweight trussed roofs-across Singapore and the region. Residential landed homes, small domestic rooftops, and large ground-mount solar farms fall outside the scope. The audience is solar EPCs, M&E contractors, factory owners, project managers, and consulting structural engineers preparing submissions for PE endorsement and authority approval through BCA, SCDF, JTC, and other agencies.
The practical stakes are significant. Structural design mistakes typically stem from underestimating environmental forces and live loads, and the consequences range from expensive retrofit costs and roof damage to non-compliance with SS EN 1990/1991/1993 and BCA requirements, voided insurance, fines, and genuine safety hazards including panel failure in high winds or roof collapse. Solar systems can last over 25 years with proper design-but only when the structure beneath them is rigorously assessed from the outset.
Here is what you will gain from this article:
- How to correctly model rooftop solar loads on factory roofs, including all load types, combinations, and wind zones
- The recurring design pitfalls and failure modes that PEs flag during review of industrial solar installations
- What PEs expect in documentation and submission packages for endorsement
- A step-by-step process to prepare structurally sound submissions and avoid delays
- How AEC Technical Advisory supports industrial clients with PE endorsement and structural analysis for rooftop solar deployment
Foundations of Structural Design for Rooftop Solar Panel System on Factories
In practice, structural design and analysis for rooftop solar loads on factories means determining whether an industrial roof-whatever its materials, geometry, and age-can safely support all additional solar panel system loads under both strength and serviceability criteria. This requires engineers to assess the existing structure, define every load acting on it (including the new solar array), apply code-mandated load combinations, and verify that every member from purlin to column remains within acceptable limits.
Industrial roofs differ fundamentally from residential roofs in span, weight, materials, and load paths. Factory roofs commonly span 20–40 metres or more with lightly proportioned steel members, whereas residential roofs rarely exceed 8–10 metres. The engineering methodology for verifying solar structures on these large-span factory roofs is correspondingly more complex and demands closer scrutiny during PE review.
The key Singapore-relevant codes and standards that govern this process include SS EN 1990 (Basis of Structural Design), SS EN 1991-1-1 (General Actions), SS EN 1991-1-4 (Wind Actions), SS EN 1993 (Steel Structures), SS EN 1992 (Reinforced Concrete), and BCA’s Building Control Act requirements for structural plan submissions. SCDF fire safety provisions and Green Mark solar readiness requirements also intersect with the structural design. The subsections below break down the roof types and load types most commonly mis-handled in PE review.
Typical Industrial Roof Structures Used for Solar Panels Installations
Understanding the roof structure is the starting point for any rooftop solar project. Each system carries load differently, and each has distinct vulnerabilities that PEs will scrutinise.
Steel portal frames with metal roof decking are among the most common factory roof systems in Singapore and Southeast Asia. These structures use rafters or trusses supported on steel columns, with purlins spanning between rafters and lightweight corrugated metal sheeting fixed to purlins. Loads transfer from sheeting → purlins → rafters/trusses → columns → foundations. Large-span factory roofs of this type often face unique structural loads due to their geometry and the light proportioning of members.
Pre-engineered buildings (PEBs) are manufactured steel buildings with optimised, tapered members designed for long spans with minimal internal supports. While efficient, PEBs are typically designed close to code minimum loads, leaving little room to accommodate additional solar loads without verification. Their bracing systems are also purpose-designed for original loading only.
Reinforced concrete flat roofs on RC warehouses handle dead load well due to inherent slab mass but may have issues with drainage, ponding on low-slope surfaces, and anchor embedment in ageing concrete. Composite slabs or precast planks over steel beams combine properties of both systems, with capacity depending on topping thickness and beam sizes.
Lightweight trussed roofs, found on smaller factories, have reduced load capacity and are more susceptible to deflection and vibration. These represent some of the highest risk structures for solar installations.
A frequent and dangerous assumption by EPCs is that these roofs have “spare capacity”-particularly metal roofs and PEBs-because they appear robust or were built decades ago when standards may have been different. PE reviewers routinely reject this assumption, especially when original drawings are missing, steel grade is unknown, corrosion has reduced member sections, or the roof is near the end of its original service life.
Structural Load Types Relevant to Rooftop Solar
Establishing a complete loading profile is vital for accurate structural assessment. The loads relevant to rooftop solar on factories fall into several categories, each frequently mis-handled in submissions.
Dead loads include the weight of PV modules, racking frames, ballast (if used), cable trays, walkways, and maintenance platforms. Solar panels add significant dead load to roof structures. A typical crystalline PV system in Singapore produces a dead load in the range of 15–20 kg/m² (approximately 0.15–0.20 kN/m²) for modules plus frames and racking. Existing dead loads include roof sheeting, insulation, and mechanical equipment-sheeting plus insulation alone can weigh around 25 kg/m² (≈0.25 kN/m²). Combined, total new permanent load can approach or exceed 0.4–0.5 kN/m², which may be critical for lightly proportioned purlins.
Imposed (live) loads cover maintenance personnel, access walkways, equipment loads near inverters and combiner boxes, and potential future additions. Solar installations can complicate roof maintenance access, and designers must account for maintenance traffic loads along likely service routes.
Environmental loads are where the most critical errors occur. Wind load calculations are crucial for solar panel stability: wind uplift and suction are highest at roof edges and corners per SS EN 1991-1-4, and the pressure coefficients at these zones can be dramatically more severe than at the roof centre. Rain ponding on low-slope roofs-exacerbated when solar rows block drainage paths-creates temporary but potentially significant loads. Water ponding can accelerate roof corrosion and structural sagging. Seismic forces can significantly impact solar installations on factory roofs in earthquake-prone zones, though this is less critical in Singapore compared with other parts of Southeast Asia. Snow loads, while usually negligible in Singapore, are relevant for projects in other regions.
A key distinction that is often confused in preliminary designs is between global building loads (affecting primary structure: rafters, trusses, portal frames, columns, bracings) and local component loads (affecting purlins, sheeting, anchors, and fasteners). Assuming uniform load distribution can cause localised structural failures-a purlin may fail locally even when the overall frame is structurally adequate.
Misinterpreting these load types is one of the most common reasons PEs reject initial solar structural submissions.
Applying Load Combinations and Codes to Rooftop Solar on Factories
Now that the relevant loads and roof types have been defined, the next critical step is combining them correctly according to structural design codes. This is where many submissions fall apart during PE review.
Industrial solar designs must follow specific load combinations and partial factors under Eurocode-based design (SS EN 1990/1991), covering both ultimate limit state (ULS) for strength and stability and serviceability limit state (SLS) for deflection, vibration, and long-term performance. Every load combination used in the analysis must be explicitly documented in calculations submitted for PE endorsement-omissions or ambiguities will trigger queries and delays.
Dead, Imposed, and Wind Load Combinations for PV Systems
The dead load of the PV system must be added to the existing roof dead load and then combined with imposed and wind loads using the appropriate partial safety factors. Common ULS combinations for rooftop solar in Singapore include:
- 1.35G + 1.5Q – factored permanent (dead) plus factored imposed (live) loads for gravity-dominant checks
- 1.35G + 1.5W – factored permanent plus factored wind, critical for uplift and anchorage
- 1.0G + 1.5W – where reduced dead load is unfavourable (e.g., net uplift exceeds dead weight, checking for overturning or anchor pull-out)
- Mixed combinations incorporating wind and imposed loads simultaneously where maintenance access under wind conditions is plausible
Incorrect or incomplete combinations are frequently flagged during PE review. The most common mistake is checking only gravity loads (dead + imposed) and ignoring uplift-essentially designing the solar panel system as if wind does not exist. Ignoring dynamic wind uplift can lead to severe roof damage. Ballast-only systems, often assumed to be self-stable, still need to be checked for sliding and overturning under wind, accounting for friction coefficients and ballast weight against calculated uplift forces.
Wind Uplift, Wind Loads, and Edge Zone Effects on Factory Roofs
Wind load represents a critical aspect of rooftop solar design on factories, and PEs scrutinise wind assumptions more closely than almost any other element. Wind load calculations to SS EN 1991-1-4 require dividing the roof into zones-corners, edges, and central areas-each with different external pressure coefficients (c_pe). For flat roofs with sharp eaves, corner zones can have c_pe,1 values as severe as −2.5, while central zones are considerably less negative.
The most frequent mistake is using an “average” pressure coefficient for the entire roof, treating it all as a central zone. This dramatically underestimates suction at edges and corners, leading to insufficient anchorage. Wind loads must account for various roof exposure zones and configurations.
Singapore’s National Annex specifies a basic wind speed of approximately 33 m/s (3-second gust). For low-rise industrial roofs within 2 km of the coastline, terrain category 0 (sea) applies, which can double or more the wind pressure magnitudes compared to terrain category II (rural). Designers who default to category II for all sites risk significant under-design of edge fixings and anchors.
Internal pressure effects are another commonly missed factor. Large-span factories with big roller doors or ventilation openings can experience elevated internal pressure when doors are open during wind events. This raises the net uplift on the roof, acting on panels and fixings from below. The result is that the majority of recorded PV failures on factory roofs involve wind-related issues-making this the single most important area PEs will scrutinise.
Serviceability Criteria: Deflections, Vibration, and Roof Performance
Complete structural analysis includes checking buckling, stability, and serviceability limits-not just strength. Designs must satisfy deflection limits to ensure long-term roof performance under solar loads.
For metal roofs, purlin deflection limits are typically L/180 to L/200 to prevent oil-canning of sheeting, water ponding, and leak issues. For RC slabs, deflection limits are generally L/250 or stricter depending on use. These standard values are often ignored when PV dead loads are added to existing spans.
Vibration and fatigue represent additional concerns on lightweight steel structures. Wind gusts can cause panels to transmit dynamic loading into frame fixings, and metal deck ripples can develop over time. These effects are frequently missing from PE calculations.
Maintaining roof drainage is crucial to prevent ponding and associated structural issues. On flat or low-slope RC roofs, PV layout can block drainage outlets, forming dams that accumulate water weight. This temporary but potentially severe load adds to both deflection and stability concerns. Proper airflow below panels reduces heat buildup and improves efficiency-elevated structures provide better ventilation and reduce thermal stress-but the structural implications of elevated mounting systems also require careful analysis.
Many PE review comments arise because these serviceability principles are not translated correctly into project-specific calculations.
How PEs Review Structural Designs for Rooftop Solar on Factories
PE review is not a “rubber stamp.” Under Singapore’s Building Control regulations, the PE who endorses a structural submission bears legal responsibility for the safety and structural integrity of the works. Structural engineers calculate loads from solar panels on roofs and verify that every element in the load path is adequate.
At AEC Technical Advisory, our PE-led consultancy is regularly engaged to endorse or rework solar structural submissions for industrial buildings. Our review methodology typically follows a structured flow: desktop study of existing structural documentation, drawing review, independent calculation checks, and-where necessary-site inspection and verification of existing structure condition. The following subsections detail what PEs look for and why submissions are returned for revision.
Information PEs Expect in a Solar Structural Submission
A well-prepared submission package is the single most effective way to avoid delays. PEs expect the following information, and gaps in any area typically trigger queries or rejection:
- Original structural drawings and as-built plans – or, where these are unavailable, a documented site survey with measured member sizes, reinforcement scans, and tested material strengths. Reviewing original structural documents is critical for understanding existing load capacities.
- Roof framing plans showing purlin, rafter, and truss layout with member sizes, spans, and connection types to walls or columns
- PV layout drawings including module arrangement, tilt angles, row spacing, support heights, parapet proximity, walkway locations, and weight per panel, frame, and racking system
- Load path diagrams clearly showing how loads transfer from modules → rails → purlins → rafters/trusses → columns → foundations. Load transfer paths from solar panels to the roof structure should be verified.
- Connection and anchorage design details – anchor types, embedment depths, edge distances, pull-out and shear capacities, and corrosion protection specifications
- Material properties – steel grade, concrete strength, existing vs proposed; corrosion condition assessment
- Design codes and editions used, including National Annex provisions; all load combinations with values and wind calculation methodology (basic wind speed, terrain category, pressure coefficients per zone)
- Serviceability checks – explicit deflection and ponding calculations, not just assumed-safe statements
- Manufacturer datasheets and test reports – for PV racking, anchors, and fasteners
Absence of original BCA-approved structural drawings often leads to conservative assumptions or required site investigations, which can be time-consuming and expensive. Clearly labelled structural models-whether from STAAD, ETABS, or detailed hand calculations-make approvals smoother and faster.
How PEs Check Global vs Local Structural Adequacy
PEs verify overall frame stability first-columns, rafters, portal frames-before examining local members including purlins, sheeting, and fixings. The analysis checks whether existing design utilisation (from original design where available) plus additional demands from solar loads remains within acceptable limits.
For long-span steel roofs and pre-engineered buildings, PEs often perform spot checks or build independent models to validate the consultant’s analysis. This is particularly important because PEBs are designed with optimised, tapered members that may already be at high utilisation ratios.
Inconsistent member capacities or missing checks for critical members-for example, internal girders supporting both rooftop plant rooms and solar arrays-are common reasons for rejection. The function of the PE review is to ensure that no element in the load path has been overlooked, whether global or local.
Documentation and Traceability Requirements
PEs require traceable calculations with clear references to specific clauses in SS EN 1991/1992/1993 and manufacturer data sheets. Every assumption must be stated, justified, and where possible, verified through test or inspection.
Examples of documentation often missing from submissions include:
- Pull-out test data for roof anchors matched to actual substrate conditions
- Corrosion protection specifications appropriate to the site (coastal industrial estates require more stringent protection)
- Details for thermal movement-thermal movement must be considered when designing solar racking systems, as expansion and contraction of long rail runs can induce forces on fixings
- Steel grade or concrete strength assumptions for older factories built before 1990, stated without supporting evidence
It is essential to assess the age and condition of existing roofs before solar installations. Older buildings may not support additional solar loads without reinforcement, and PE reviewers will require evidence that the condition has been evaluated.
Many common errors identified in PE review come from gaps in this documentation, not just wrong numbers.
Common Structural Design Errors Found During PE Review (and How to Fix Them)
This section is the heart of this article: a problem/solution breakdown based on AEC Technical Advisory’s project experience in Singapore and the region. Each subsection describes a recurring error, explains why it occurs, and provides actionable guidance to address it before submission.
Error 1: Underestimating Existing Roof Capacity and Skipping Verification
The error: Designers assume that factory roofs were “overdesigned” and can readily accept 15–20 kg/m² of additional PV dead load with minimal or no structural checks.
Why it occurs: Older buildings may not support additional solar loads, but this fact is obscured when original drawings are missing, steel grade is unknown, corrosion has reduced section properties, or past alterations have changed load paths. This issue is especially risky for 1970s–1990s RC factories with minimal reinforcement, lightweight metal roofs with long spans, and cost-optimised pre-engineered buildings that were designed to code minimums decades ago.
How to fix it: Conducting a comprehensive roof inspection helps identify potential structural issues. Review original BCA-approved drawings where available. Where drawings are missing, conduct a site survey: measure member dimensions, scan reinforcement using cover meters, extract core test samples from concrete, and verify steel grades. Model actual member capacities before assigning solar loads. PEs may require conservative capacity limits or strengthening measures-such as additional purlins, stiffeners, or local beams-if verification is incomplete.
Error 2: Incorrect Wind Load Modelling and Ignoring Uplift
The error: Applying wind loads as a simple downward “pressure” or using flat-roof pressure coefficients for pitched metal roofs, with no distinction between roof zones.
Typical mistakes include: treating the entire roof as a central zone, ignoring internal pressure from open doors or ventilation, and assuming wind is negligible because Singapore is “non-typhoon.” While Singapore does not experience hurricanes, the design basic wind speed of 33 m/s still produces substantial uplift forces, particularly at edges and corners. Wind-induced failures can lead to significant economic losses for solar projects.
How to fix it: Follow SS EN 1991-1-4 zoning rigorously. Check both positive (downward) and negative (uplift) pressures. Verify net uplift on PV tables after accounting for dead weight. Check anchorage for both pull-out and sliding resistance. Designers should provide a brief wind-load summary table in the submission-showing terrain category, basic wind speed, c_pe values per zone, and resulting design pressures-to make PE checking quicker and more transparent. Wind load calculations must represent site-specific conditions, not generic assumptions.
Error 3: Overloading Purlins and Roof Sheets Without Reinforcement
The error: Placing rails directly on thin Z-purlins or lightweight sheeting, assuming the solar load is “minor” compared to global frame capacity.
The consequences: Even when the primary structure handles the additional loads adequately, purlin flanges may be thin, spans long, or sections reduced by corrosion. Local overstress leads to excessive deflection, oil-canning of sheeting, water intrusion, or ponding. Water intrusion can occur from solar racking penetrations, compounding the damage. PEs routinely flag these results when reviewing purlin spans and member sizes against combined dead + live + wind loads.
How to fix it: Spread loads using continuous rails supported at or near primary beam locations. Add supplementary purlins or sub-framing in zones where purlin capacity is insufficient. Limit attachment points to near primary beams where possible. Re-check purlin bending and deflection under all combined loads. Simple 2D sketches or photos showing proposed strengthening help PEs visualise and approve modifications quickly.
Error 4: Inadequate Connection Design and Fastener Checks
The error: Module and rail suppliers are assumed to “handle” connections, but no structural check of fasteners to roof deck, purlins, or RC slab is provided in the submission.
Specific issues include: missing pull-out and shear resistance checks, no corrosion specification for coastal industrial estates (for example, Jurong Island sites with severe exposure), unspecified edge distances for anchors near roof edges or parapets, and use of manufacturer generic anchor datasheets without matching to site substrate conditions. Thinner glass in solar panels increases breakage rates under stress, and glass failure can lead to ground faults and inverter tripping-connection design must handle the full range of dynamic wind and dead load forces to prevent such failures.
How to fix it: Calculate design forces at each connection from wind loads applied over the tributary area. Select and verify fasteners with manufacturer data, including embedment depth, edge distances, and substrate type. Specify corrosion protection-hot-dip galvanising or stainless steel grade-appropriate to site conditions. Certification testing should require testing a minimum of 3–5 modules to confirm connection performance. Including manufacturer test reports and technical datasheets in the submission can pre-empt many PE comments.
Error 5: Ignoring Fire Safety, Access, and Roof Drainage in the Structural Layout
The error: While this is primarily a structural article, PE reviewers in Singapore coordinate with Fire Safety Engineers and BCA/SCDF guidelines. Typical mistakes include blocking roof access routes with PV tables, covering smoke hatches or dry risers, and obstructing rainwater downpipes.
Structural implications: Blocked drainage leads to higher ponding risk on RC roofs, with associated local overloading at clogged gutters. Maintaining roof drainage is crucial to prevent ponding and associated structural issues. Where fire-fighting access is mandated, structural walkways may need to be designed and detailed, creating concentrated loads that must be accounted for in the analysis. Solar permit design ensures compliance with local building codes, and failure to comply can result in fines.
How to fix it: Coordinate early with fire safety and M&E designers. Maintain clear fire access lanes per SCDF requirements. Avoid panel placement over drainage paths. Where access walkways are required, strengthen and detail them structurally. Early coordination prevents costly redesign after PE review.
Error 6: No Allowance for Future Maintenance Loads and Upgrades
The error: Designing only for static PV load and current equipment, ignoring future heavier modules, additional inverters, or maintenance traffic.
Why PEs flag this: PE reviewers may query low live load allowances, especially on roofs used for M&E plant and inspection access. A 9% reduction in aluminum content in newer modules affects module strength, and testing standards have weakened, allowing lower-quality modules to pass-meaning future replacement panels may have different structural characteristics. The current factor of safety for solar modules is 1.5, which some engineers consider inadequate for long-term durability over the 25+ year life of a solar installation.
How to fix it: Design roof members with at least minimum maintenance loads per code. Reserve structural capacity along likely maintenance routes. Warn factory owners if capacity is fully used by the current solar deployment so they understand constraints for any future upgrades. Solar panels lose 0.3%–0.4% efficiency per 1°C rise above 25°C, so elevated mounting structures that provide better ventilation may be preferred-but these require separate structural verification due to increased height and wind exposure.
Step-by-Step Process to Get Rooftop Solar Structurally Ready for PE Endorsement
The following workflow reflects the process AEC Technical Advisory uses to help industrial clients avoid back-and-forth with reviewers. Following this structured approach reduces redesign cycles and accelerates authority submissions to BCA and relevant agencies.
Practical Workflow for Consultants and EPCs
- Data Collection – Gather structural drawings, as-built details, original design reports, and current roof condition photos. For older factories built before the mid-1990s, expect common gaps: missing drawings, unknown material grades, undocumented past alterations. Reviewing original structural documents is critical for understanding existing load capacities.
- Roof Inspection and Verification – Conduct a site inspection. Measure actual member sizes and slab thicknesses. Identify corrosion, previous alterations, and cut-outs. Steel frames can enhance solar panel strength and performance, but only if their current condition is verified. Structural evaluations assess roof load capacity for solar panels based on as-found-not as-designed-conditions.
- Structural Modelling and Load Definition – Build a simple but accurate model of the roof structure. Apply PV loads and all relevant load combinations (ULS and SLS). Perform checks for strength, stability, and deflection. Seismic loads must be considered for installations in earthquake zones where applicable. Complete structural analysis includes checking buckling, stability, and serviceability limits.
- Detailing of Supports and Connections – Design rails, supports, fasteners, and any required strengthening. Coordinate with PV suppliers to ensure compatibility and constructability. Thermal movement must be considered when designing solar racking systems-long rail runs expand and contract significantly over daily temperature cycles.
- Documentation for PE Review – Prepare clear calculation reports, load summaries, drawings with marked-up load paths and strengthened areas, and an explicit list of all assumptions. Compliance with building codes ensures long-term functionality of solar systems.
- Iteration and Coordination – Address PE queries promptly, adjust design as required, and update documents for BCA submission. Different regions have varying building codes for solar installations, so ensure the correct National Annex provisions are applied.
Comparing “Minimal Check” vs “Comprehensive Check” Approaches
| Criterion | Minimal Check | Comprehensive Check |
|---|---|---|
| Scope | Single-page calculation, generic loads | Full load combinations, site-verified data |
| Site verification | None or cursory | Measured member sizes, material testing, corrosion assessment |
| Wind analysis | Average pressure, single zone | Zone-specific c_pe, terrain-appropriate, internal pressure included |
| Connection design | Generic manufacturer data | Site-matched anchor checks with pull-out/shear verification |
| Typical PE outcome | Multiple queries, conservative limits, or rejection | Faster endorsement, fewer revision cycles |
| Cost impact | Low upfront, high rework cost | Higher upfront, significantly reduced total project cost |
| Risk profile | High risk of delays and construction surprises | Lower risk, clearer allocation of responsibility |
Although comprehensive checks require more upfront effort, they typically lead to reduced total cost and risk, especially for large factory roofs over 5,000–10,000 m². In comparison, minimal-check approaches frequently result in multiple PE review cycles and may require expensive structural strengthening discovered late in the project.
Case-Based Illustrations of Common Errors and Their Resolution
The following anonymised scenarios from factories in Singapore and the region illustrate how typical errors are caught and resolved. Details focus on structural issues-loads, members, and strengthening-rather than commercial terms.
Case Study 1: Metal Roof Factory in Tuas with Under-Designed Purlins
A 1998 steel factory in Tuas with long-span Z-purlins was proposed to receive a 1 MWp rooftop PV system. The initial design assumed purlins were adequate based on global frame capacity, with no specific deflection check under the additional PV dead load of approximately 18 kg/m².
PE review flagged excessive deflection under combined dead + imposed + wind loads. Several purlin bays exceeded the L/180 deflection limit, with results showing oil-canning risk and potential ponding at mid-span locations.
The solution involved adding secondary rails supported on main rafters, selectively strengthening purlins in high-load zones, and adjusting the panel layout away from the most flexible bays. PE endorsement was granted after revisions, with minimal disruption to the installation schedule. The example demonstrates that older roofs may require reinforcement for solar installations even when the primary frame appears sound.
Case Study 2: RC Flat Roof Warehouse in Jurong with Incomplete Wind Checks
A flat roof warehouse built circa 1985 in Jurong was retrofitted for PV installation in 2023. The designer checked slab punching and flexure for gravity loads but omitted wind uplift and parapet effects for anchor design near roof edges.
PE review required a revised wind analysis per SS EN 1991-1-4, applying correct edge and corner zone pressure coefficients rather than the central zone c_pe values used in the original submission. Anchor groups near roof edges needed redesign with increased embedment and additional reinforcement at certain locations. Breakage rates can reach 50% in some field-deployed modules when fixings are inadequate, underscoring why connection design in high-uplift zones is so important.
After proper uplift checks and detailing, the project met both structural safety and authority submission requirements.
Case Study 3: Pre-Engineered Building Export Project in Batam
An industrial PEB factory in Batam, originally designed to code minimum loads, was proposed for a large rooftop solar array. The PV supplier assumed the building had large spare capacity based on its physical appearance.
PE review by AEC Technical Advisory identified that no consideration had been given to frame buckling or bracing adequacy under the additional PV loads. Re-analysis revealed that several frame members were already at high utilisation, and additional bracing members were required. PV deployment was limited to certain bays only to keep utilisation within acceptable limits.
The lesson is clear: early structural involvement prevents costly strengthening works after panel installation and reduces the risk of structural failure. Scalability of solar deployment on PEBs depends entirely on verified-not assumed-capacity.
Conclusion and Practical Next Steps
Structural design and analysis for rooftop solar loads on factories must be rigorous and project-specific. PEs frequently detect recurring mistakes-wind load underestimation, unverified existing capacity, overloaded purlins, and inadequate connection detailing-that are entirely avoidable with proper engineering discipline. The benefits of getting this right extend beyond approval: they include long-term structural safety, energy savings from reliable energy production, protection of the building investment, and avoidance of expensive retrofits.
Careful treatment of wind loads, existing capacity verification, and connection design are the three most critical areas in PE review. Addressing these properly is important not only for compliance but for the 25+ year service life of both the solar installation and the roof beneath it.
Actionable next steps:
- Audit current or upcoming factory solar projects against the error list in this article
- Engage a structural consultant early for feasibility checks before finalising PV layout
- Prepare a standardised structural submission pack template for all factory rooftop solar projects
- Plan for periodic structural inspections of older roofs already carrying PV loads
- Ensure all new designs account for future maintenance loads and potential equipment upgrades
AEC Technical Advisory supports industrial clients across Singapore with structural design, PE endorsement, and authority submissions for rooftop solar retrofits. Whether your project involves a single factory block or a multi-building industrial estate, our structural engineering services for industrial facilities ensure designs meet code requirements, withstand environmental conditions, and pass PE review without unnecessary delays.
Additional Resources and Checklists
This section provides compact, practical tools for project teams rather than additional theory.
Pre-Submission Checklist for Structural Design of Factory Rooftop Solar
- ☐ Original structural drawings and as-built records obtained and reviewed
- ☐ Roof type confirmed, member sizes measured on site, material grades verified or tested
- ☐ PV loads defined: dead load (panels + racking + cables), imposed loads (maintenance, equipment), wind loads per SS EN 1991-1-4 with correct terrain category and zone coefficients
- ☐ All load combinations documented (ULS and SLS) with explicit partial factors
- ☐ Global frame capacity checked: columns, rafters, trusses, bracing
- ☐ Local member stresses and deflections checked: purlins, sheeting, sub-framing
- ☐ Connection design completed with fastener capacities, embedment details, edge distances, and corrosion protection specified
- ☐ Fire safety access lanes, smoke vent clearances, and drainage paths coordinated with M&E and SCDF requirements
- ☐ All assumptions clearly stated, justified, and traceable to code clauses or test data
- ☐ Calculations and drawings compiled in a clear, navigable package for PE review
Where to Learn More and When to Call a PE
Relevant standards and guidelines for further reading include:
- SS EN 1990/1991/1992/1993 – Singapore Standards adopting Eurocodes for structural design, actions, concrete, and steel
- BCA Practice Notes on rooftop installations and structural plan submissions – covering trigger thresholds (e.g., support structures exceeding 2.5 m in height, panels acting as roof shelter exceeding 10 m²)
- SCDF Guidelines for PV on roofs – fire access, spacing, and smoke vent requirements
- BCA Green Mark solar readiness provisions – increasingly requiring structural proof for static and wind loads
A factory owner or EPC should involve a PE or specialist consultant when:
- The building is older, with missing structural documentation or unknown material properties
- The rooftop system exceeds 500 kWp or spans multiple factory blocks, where the engineering complexity and risk escalate significantly
- The site is in a high-wind or coastal industrial zone with severe corrosion exposure conditions
Renewable energy deployment on factory rooftops continues to accelerate across Singapore and Southeast Asia. Getting the structural design right-before PE review, not after-remains the most reliable path to safe, efficient, and timely solar installations on industrial buildings.